EIP & NASDAT Status

EIP & NASDAT Status. 1/14/2011. Status. EIP Pre-Production (2 units) Enclosure design complete All major materials procurements issued Subassemblies: Ethernet Switch: Fabrication DCMON: Subcontractor PCB layout SSPC: Fabrication AC Distribution: Assembly

chesmu
Download Presentation

EIP & NASDAT Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EIP & NASDAT Status 1/14/2011

  2. Status • EIP Pre-Production (2 units) • Enclosure design complete • All major materials procurements issued • Subassemblies: • Ethernet Switch: Fabrication • DCMON: Subcontractor PCB layout • SSPC: Fabrication • AC Distribution: Assembly • Box-level Assembly Drawing: 25%

  3. Status • NASDAT Pre-Production (1 unit) • All major materials procurements issued (includes enclosures) • Exception: Internal IMU not purchased • Subassembly Status: • Analog Isolation Card: Design Complete, prototype tested • Interface Isolation Card: PCB Layout • Power Distribution Card: Requirements Definition • Note: Box assembly will be in-house

  4. Status • AC Distribution PCB:

  5. Status • SSPC Completed PCB Layout:

  6. Status • DCMON PCB Parts Placement:

  7. Status • Ethernet Switch Connector Board PCB: • Ethernet Switch Main PCB (Sixnet):

  8. Status • NASDAT Interface Isolation Card:

  9. Status • Changes Since PDR (EIP): • EIP cable ID • Each EIP gets unique ID (simplifies network) • (4) EIP Ethernet Connectors (was 2) • 8 10/100 ports, 4 1G ports (unchanged) • Finalized connector locations • All inputs on left, all outputs & data on front • GPS feed on right (GH only) • WoW / Gear / Cockpit Switch #1 • Using Polyfuses for cockpit switch #1

  10. Electrical • New EIP harness connectors are available from ASF for aircraft use: • D38999/26WC98PN (Interlock): 150pc • D38999/26WG16PN (AC/DC): 250pc • TV06RQW-21-75S (Ethernet): 100pc • CA-628485-134 (RJ45->quadrax): 10pc

  11. Ethernet • EIP Box Connector: See Pinouts • (2) 100Mbit x 4 & (2) 1Gbit x 2 • Mates to TVP06RQW21-75S ($800/ea) • Bulkhead Connector: • Amphenol 10-646787-75S ($1.7k/ea, $1.2k @ 12pc) • Pin / Socket, 21-75 shell style • Leak Rate: 1*10-3 cm3/s (~0.3 ft3/mission) • Mates to TVP06RQW21-75S & TVP06RQW21-75P ($600/ea) • Cable: Tensolite NF24Q100 ($4/ft) • Cost Estimate: $15k/ER2, $4k/WB57 • These items have not been purchased

  12. Mechanical • Enclosure Drawing: a9444-ASF11-341 • Expect sheet metal in house ~2/14/11 • Dimensions are same as legacy ER-2 EIP • 10.6” W x 6.72” L x 4.32” H • 38% volume reduction over GH package by consolidating EIP & ethernet switch

  13. Mechanical PDR (9/14/10) Pre-Production (12/21/10)

  14. Mechanical FRONT LEFT RIGHT Note: cross-hairs & leaders due to images pasted from EIP sheet metal drawing

  15. Schedule / Milestones • EIP Milestones: • Aircraft Fit Check: 2/4/11 • Start of Pre-Production: 3/23/11 • CDR: 4/15/11 • Start of Production: 5/11/11 • Production Complete: 7/11/11 • Risks / Issues: • ARRA funding cuts off 7/29/11 • Integration of hardware with aircraft – dates?

  16. Schedule / Milestones • NASDAT Milestones: • Start of Pre-Production: 4/11/11 • CDR: 4/15/11 • Start of Production: 5/31/11 • Production Complete: 3/2012 • Risks / Issues: • NASDAT assembly schedule tied to deployment staffing