OMS 101. How to survive implementing a new Outage Management System. Dave Blew Public Service Electric & Gas Newark, NJ. PSE&G. 1.9 million electric customers System peak 9,500 MW 4 operating divisions along corridor from New York to Philadelphia 1,400 square miles 75% of population

chambray
Download Presentation

OMS 101

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. OMS 101 How to survive implementing a new Outage Management System Dave Blew Public Service Electric & Gas Newark, NJ

  2. PSE&G • 1.9 million electric customers • System peak 9,500 MW • 4 operating divisions along corridor from New York to Philadelphia • 1,400 square miles • 75% of population • 2,317 distribution circuits (4/13kV) • 540 sub-transmission circuits (26/69kV)

  3. OMS Products Installed • Major components from M3i • Call Management (Pragma Up) • Connected Circuit Model (Pragma Line) • Switching (Pragma Switch) • Dispatching (Pragma CAD) • Reporting (Pragma Proof) • Remote Use (Pragma Web)

  4. Contractors • M3i – OMS application (Montreal, Quebec) • ESRI – GIS vendor (Redlands, CA) • Minor & Minor - application developer • ASI - data conversion • CAI – CIS interface • DAQ – SCADA interface • COE – Change management contractor • Performance Edge – training materials • Walkabout – Mobile Data Terminals (MDTs) • Verizon – CDPD RF service to MDTs

  5. Benefits • Improved operations and dispatching • Less paperwork - direct feed from CIS • Better information back to customer • More details on each outage event • Improved storm management • Graphical data display

  6. Critical Issues • Project scope • Resource drain • “Connected Model” completion • Transition period • Expectations of senior management • Training (do not short change) • Implementing at the same time as NJ BPU releases formal reliability standards

  7. Recommendations • Get the connected model right • Set expectations of executives early on • Plan for transition period • Do not under estimate stake holder management all throughout project

  8. Questions