1 / 21

Extends A WARM WELCOME

B.W.S.S.B. Extends A WARM WELCOME. TO ALL THE PARTICIPANTS IN THE WORKSHOP. Pumping 780 Million Litres of Water per Day to Bangalore City through Cauvery Water Supply Scheme Stage-I, II, III and IV. PRESENT SCENARIO. PRESENT SCENARIO.

casey
Download Presentation

Extends A WARM WELCOME

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. B.W.S.S.B ExtendsAWARM WELCOME TO ALL THE PARTICIPANTS IN THE WORKSHOP

  2. Pumping 780 Million Litres of Water per Day to Bangalore City through Cauvery Water Supply Scheme Stage-I, II, III and IV PRESENT SCENARIO

  3. PRESENT SCENARIO • Handling 410 Million Litres of sewage and treating them in 5 sewage treatment plants located in different parts of the City.

  4. Customer friendly initiatives • Electronics Clearing System introduced; • Informative Website in position; • Interactive Voice Response System in position; • Monthly Water Adalats in each Sub-Division effectively working; • Customer Charter launched; • Many transparent measures introduced for the benefit of customers;

  5. Sl.No Slabs ( in litres) Amount in Rs. Minimum 90.00 1 0-15000 6.00 2 15001-25000 8.00 3 25001-50000 12.00 4 50001-75000 30.00 5 75001-100000 36.00 6 100000 & above 36.00 DOMESTIC TARIFF STRUCTURE

  6. Sl.No Sl.No Slabs (in litres) Category Amount in Rs. Amount in Rs. 1 Minimum INDUSTRIES 60.00/K.L. 360.00 1 0-10000 36.00 2 10001-20000 39.00 3 20001-40000 44.00 4 40001-60000 51.00 5 60001-100000 57.00 6 100001 & above 60.00 NON-DOMESTIC TARIFF STRUCTURE INDUSTRIES TARIFF STRUCTURE

  7. CURRENT PROJECTS ON HAND • Commissioning of seven sewage treatment plants under Cauvery Water Supply Scheme Stage-IV, Phase-I, adding an additional capacity of 245 MLD . • Projected to be completed by December 2003

  8. CURRENT PROJECTS ON HAND • Comprehensive networking of all BWSSB offices in Bangalore through LAN WAN. • Proposed to be completed by first week of Feb. 003.

  9. CURRENT PROJECTS ON HAND • Two tertiary treatment plants – Vrishabhavathi Valley (60 MLD) and Yelahanka (10 MLD) to be commissioned during Feb. 2003

  10. CURRENT PROJECTS ON HAND • National River Conservation Plan works with an estimated cost of Rs. 47 crores under implementation

  11. CURRENT PROJECTS ON HAND • Newly added areas being networked with water supply and UGD facilities at an estimated cost of Rs. 143 crores.

  12. CURRENT PROJECTS ON HAND • An ambitious project for reducing Unaccounted For Water (UFW) and bringing it down to less than 15 % under implementation. • Proposed to be completed by December 2003.

  13. AusAID Master Plan Project Four Components Planning for Water Supply, Sewerage & Environmental Sanitation. Services Upgrading and Extension for the Urban Poor and Vulnerable Communities. Institutional Capacity Building and Strengthening. Water Supply and Sewerage Pilot Projects.

  14. Water supply requirements(MLD)B.W.S.S.B. Service Area

  15. Capital cost estimates for Water Supply rehabilitation (2001-25) (In Rs. Crores)

  16. Summary of Capital Costs

  17. Customer friendly initiatives to be launched during the first half of 2003 • Spot billing system • 24-hour KIOSKS • Web enabled access to customer history • Web enabled interactive redressal system

  18. THANK YOU

More Related