co2 cooling and ibl interface meeting tooling cooling line at pp1 n.
Download
Skip this Video
Loading SlideShow in 5 Seconds..
CO2 cooling and IBL interface meeting Tooling cooling line at PP1 PowerPoint Presentation
Download Presentation
CO2 cooling and IBL interface meeting Tooling cooling line at PP1

Loading in 2 Seconds...

play fullscreen
1 / 18

CO2 cooling and IBL interface meeting Tooling cooling line at PP1 - PowerPoint PPT Presentation


  • 168 Views
  • Uploaded on

CO2 cooling and IBL interface meeting Tooling cooling line at PP1. Didier Laporte CNRS – LPNHE Paris 06 février 2014 EDMS IN2P3 : I-036854 – V2. Assembling tooling. First cooling line. Montage splitter box, Début montage des lignes, soudure. 6/8 lines on tools. Fitting stoppers.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'CO2 cooling and IBL interface meeting Tooling cooling line at PP1' - candra


Download Now An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
co2 cooling and ibl interface meeting tooling cooling line at pp1

CO2 cooling and IBL interface meetingToolingcooling line at PP1

Didier Laporte

CNRS – LPNHE Paris06 février 2014

EDMS IN2P3 : I-036854 – V2

first cooling line
First cooling line
  • Montage splitter box,
  • Début montage des lignes, soudure
mainframe
Mainframe

Elcom 20x20

to do list
To do list :
  • Update of the lines (6 / 8 ), LAPP
  • Design side A, LPNHE
  • Splitter box interface, LAPP
  • Escargot interface, LAPP
  • Protection for travel, LPNHE
  • Connection links at PP1 (for tests), LPNHE
  • Command to do (Elcom), LAPP/LPNHE
  • Delivery date ?