The Yakima Air Terminal has secured an $11 million grant for taxiway resurfacing, LED system upgrade, sign replacement, and markings correction. The project commences on October 27, 2014, with multiple phases lasting until August 25, 2015. Each phase includes specific ramp closures and construction impacts on various airport areas.
E N D
Yakima Air Terminal Alpha Taxiway Rehabilitation Improvement Project
Project Overview Project Schedule Impacts Project Status Questions Presentation Overview
The Yakima Air Terminal has received an $11,000,000 grant. The grant is to: • Resurface and widen Alpha Taxiway, Taxiway Connectors A1-A5, and portions of Bravo and Charlie Taxiways; • Resurface airfield pavement between the north taxiway edge line to the non-movement line; • Replace the existing MITL system with LED MITL, including new conduit, fixtures, and regulator; • Replace all existing directional and hold short signs; and • Correct several markings not meeting FAA standards. Project Overview
Expected construction START DATE October 27, 2014: • October 27, 2014 – November 14, 2014 • Preliminary electrical work outside regular Phases 1-7 • Inclement Weather Shutdown • Phase 1: April 20, 2015 – May 15, 2015 • Phase 2: May 16, 2015 – May 29, 2015 • Phase 3: May 30, 2015 – June 12, 2015 • Phase 4: June 13, 2015 – July 3, 2015 • Phase 5: July 4, 2015 – July 24, 2015 • Phase 6 / 7: July 25, 2015 – August 25, 2015 Project Schedule
Phase 1:April 20, 2015 – May 15, 2015 • Ramp Closures. • McCormick West, and Plath Hangar. • Partial Ramp Closures. • Fuel Tank/House and McCormick Air Center. • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
Phase 2: May 16, 2015 – May 29, 2015 • Ramp Closures. • Airlift Northwest, FedEx Air Cargo and Airport Maintenance Building. • Partial Ramp Closures. • McCormick Air Center and Private Hangars (formerly Noland-Decoto). • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
Phase 3: May 30, 2015 – June 12, 2015 • Ramp Closures. • GE Aviation, West Itinerant Ramp, Med Assets, and West Terminal Apron Ramp. • Partial Ramp Closures. • Private Hangars (formerly Noland-Decoto). • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
Phase 4: June 13, 2015 – July 3, 2015 • Ramp Closures. • East Terminal Apron Ramp. • Partial Ramp Closures. • East Itinerant Ramp. • Runway 4/22 and Bravo Taxiway Closed. • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
Phase 5: July 4, 2015 – July 24, 2015 • Ramp Closures. • No Ramps Closed. • Alternate routes required for: Cub Crafters, McAllister Museum, Advanced Medical Systems, and South Air Park. • Temporary Runway 9/27 Closure for work within the Runway Safety Area. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
Phase 6: July 25, 2015 – August 25, 2015 • Partial Ramp closures denoted by barricades. • Runway 4/22 closed intermittently. • On-going construction activity and vehicle traffic on service roads and taxiways. Impacts
Phase 7: July 25, 2015 – August 25, 2015 • Not expecting any closures, however a schedule will be provided of the impacted areas to minimize air traffic and vehicle operations within the work areas. • On-going construction activities and vehicle traffic on service roads and ramps. Impacts
If at all possible, avoid construction areas. • Please plan all operations around construction to the maximum extent possible. • If there are known operations that will be impacted by the proposed schedule, please let us know. • The Airport Management will provide NOTAMs. • Do not travel (plane or car) across barricades delineating closed pavement. • Do not provide direction to the contractor unless there is an emergency. Operations During Construction
Robert Peterson Rob.Peterson@yakimaairterminal.com Office: (509) 575-6149 (#7) Cell: (509) 833-0898 Kris Yalovich Kris.Yalovich@yakimaairterminal.com Office: (509) 575-6149 (#7) Stephanie Ray, PE sray@hlacivil.com (509) 966-7000 Michael Battle, PE mbattle@hlacivil.com (509) 966-7000 Questions