1 / 17

Network Rationalization SSC - 4 Walls Initiative

Network Rationalization SSC - 4 Walls Initiative. Expected SSC Savings. Key Principles. There IS an overnight delivery standard for commercial mail There IS NOT an overnight delivery standard for Single Piece First Class Mail (SPFCM)

Download Presentation

Network Rationalization SSC - 4 Walls Initiative

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Network Rationalization SSC - 4 Walls Initiative

  2. Expected SSC Savings

  3. Key Principles • There ISan overnight delivery standard for commercial mail • There IS NOT an overnight delivery standard for Single Piece First Class Mail (SPFCM) • There is an overnight delivery performance for both commercial mail and single piece first class mail • Anticipate that 66% of current overnight delivery performance will remain under Phase 2 Network Rationalization

  4. Letter/Flats Processing - Outgoing • All collection mail must be worked day of entry • Service Standards for 2D and 3D have not changed • Realignment of surface network to secure arrival of 2 day committed mail to destinating office by 8:00am • Revaluation of STC network • Evaluate Fedex Contract impact • Continuous processing of FIM mail

  5. Letter Mail Destinating Operations • Two Critical Entry Times for Commercial Mail • 8:00am • Mail tendered by 8:00am destined for that plant’s local delivery area requiring a primary sortation, will have an overnight delivery standard • Noon • Mailers who enter presorted mail, properly prepared and containerized and entered by CET as of noon, will have an overnight first class service standard for mail destinating to the local plants service area

  6. Periodicals CET Matrix – Phase II Periodicals CETs – Under Phase II

  7. Driving Efficiency • Future NETWORK – All Plants • Preserves Approx. 66% of Overnight Delivery Volume • Revised Entry Times • Reduced Equipment • Reduced Footprint

  8. Priority Mail – No Change 0800 1200 1600 2000 2400 0400 0800 Current Processing Originating (1700-0115) Destinating (0800-0400) Future Processing Originating (1700-0115) Destinating (0800-0400)

  9. Originating FCM Letters/Flats 0800 1200 1600 2000 2400 0400 0800 Current Processing Cancellation (1700-2200) Outgoing Primary (1730-2300) Outgoing Secondary (1800-2400) Future Processing Expansion of outgoing operating windows only for those sites consolidating originating mail Cancellation (1700-0050) Outgoing Primary (1730-0100) Outgoing Secondary (1800-0130)

  10. Destinating Letters 0800 1200 1600 2000 2400 0400 0800 Current Processing Incoming Primary (0800-2000) DPS Processing (2200-0600) Remittance/Caller Service (0800-0600) Future Processing Incoming Primary (0800-1200) DPS Processing (1200-0600) Remittance/Caller Service (0800-0600)

  11. DPS Processing • DPS to start at noon and continue until 6:00am • Ensures some turnaround SPFC is delivered overnight • Staging lanes critical • Increase of first class on hand volumes

  12. Remittance Processing • Anticipated that delivery times for Remittance mail will improve • Moving 2D committed volumes to 8:00am and continuous process of FIM will improve FIM process by 10-12 hours • All turnaround FIM will have an overnight delivery performance

  13. Destinating Flats 0800 1200 1600 2000 2400 0400 0800 Current Processing Incoming Primary (0800-2000) Carrier Route Processing (2200-0600) FSS Processing (1200-0600) Future Processing Incoming Primary (0800-1600) Carrier Route Processing (1600-0600) FSS Processing (1200-0600)

  14. FIM/Remittance Mail Model PM Window7-8 PM Window 6-7 Non-Committed Primary Originating FIM Window DPS First & Second Pass with CR-RT Committed Primary AMP (Outlying) 897 Window City (Near) 897 Window T-3 Full Time Staff T-1 Full Time Staff T-2 FlexStaff Fully Utilized Machine Staffing Model Examples T-3 Full Time Staff T-3 Full Time Staff T-2 Full Time Staff T-1 FlexStaff T-2 Full Time Staff T-3 FlexStaff T-1 Full Time Staff T-3 Full Time Staff T-1 Flex Staff T-2 FlexStaff

  15. F1 Savings • PROCESSING OPERATIONS • Operating Window Changes • Work Equipment to Capacity • Reduced Equipment Set, Elimination of Phase 1 DBs • Utilize RPGs and DPS Optimization Tool • Complement Impacts & Staffing Realignments – Use Baseline Staffing Model

  16. F3A Savings • Transportation • Match new processing profile to transportation • Optimize trips from plant to multiple stations • Consider trailer utilization • Eliminate early DPS runs • Zero Base schedules to match new processing profile

  17. F3B Savings • MAINTENANCE • Reduced machine need; down to the machine number which gives us a machine type; each machine type has a PM value associated with it some more labor intensive than others • Greater opportunity for Operations to compact/condense machine usage; said otherwise no reason to dirty up (use) a DB for small runs on t-2 and 3; as this will reduce our benefit or need to PM them and to provide OPMS for them        • Example would be running LAMM whether 1st or standard mail on one machine and then use the same machine to run primary and secondary runs on instead of moving to a different machine because you have time to sweep it down later. • On Saturday night when you go to start 1st pass runs for Monday delivery don’t run every machine (zone) just because you have the Ops staff only run them if the Monday morning volume warrants it. Every minute that machine is on we have a minimum amount of work on the equipment that must be done.     • Be smart about the machines you want to keep; they are all DB’s and we should be able to make them run well i.e.… a phase 6 vs phase 2 – 5 or a DIOSS D vs  B • Stacker module increases have an impact on PM’s but is minimal; increase number bins where it makes sense • Standardize equipment types as best you can because that will help us save on part usage and storage space i.e.. an opportunity to get rid of phase 2 stacker modules that may not have been modified in the past • Consider how you will alleviate bypass/residue/residual volumes in your smaller plants that remain open