The Gates Center faculty lunch on January 19, 2005, addressed key details regarding the proposed SCS building. Attendees, including the SCS Building Committee led by Guy Blelloch, discussed location, size, and massing of the building, which is projected to be 200-220K gross square feet. Goals included creating an SCS quad with green space and ensuring easy access to nearby structures. The final architect selection is expected soon, followed by schematic design and construction documentation. Input from all faculty is encouraged throughout this planning phase.
E N D
Gates Center Faculty Lunch: Jan. 19, 2005
Outline • Location, Size and Massing • Architect Selection/Timeline • The Interior Space : What do we want?
SCS Building Committee • Small committee • Guy Blelloch (Chair) • Randy Bryant • Sharon Burks • Peter Lee • Jim Skees • Manuela Veloso • ??? • Everyone is encouraged to give input.
Morewood Old Navy Building A Hiccup West Campus
Looks like the building will be 200-220K Gross Square Feet (GSF) • Original Proposal = 150K • Wean Hall = 290K (We have about ½) • NSH = 155K • With 220K we would still have to keep about 30K of Wean Hall. With 150K we would have to keep about 100K. Note: Assignable Square Feet (ASF) = .6 GSF
Exactly what parts of SCS move into the new building has not yet been decided
Some Constraints Maintain Alignment and create pathway
Some Constraints Preserve view of Oakland??
Some Goals Create a SCS quad with greenspace
Some Goals Indoor above grade Connection to NSH
Some Goals Easy Connection to the Cut
Some Goals Visitor’s entrance on Forbes
Some Goals Underground Parking
Some Constraints Accessible undergraduate “core”
Some Constraints Lots of light and nice views
Example Design bridge Terrace even with cut (3 floors below)
Undergraduate core
Greenspace and views
Selecting an Architect • A Committee Headed by Christina Gabriel • SCS: Peter Lee, Randy Bryant, Guy Blelloch • Trustees: Lucian Caste, Oscar Harris • Architecture: Gerard Damiani, Laura Lee • FMS : Paul Tellers • Request for Qualifications (sent and received) • Select final 3-5 by February
Original Timeline Jan 05 Jan 06 Jan 07 Jan 08 Jan 09 completion architect selected schematic design construction docs groundbreaking our input into the design fundraising Probably a month or two behind
Interior Organization Many Questions • Special Wishes • Grouping • Types of common spaces • Conference room features and sizes • Undergraduate/Research connecitivity Time Critical: How do these affect the layout