NMCD CMIS Project Closeout. Presenters: Larry Pacheco, CIO Dan Donoghue, PM. August 25, 2010. CMIS Project Overview. CMIS Background. Project funding : $1.1m General Fund/$600k NMCD

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' NMCD CMIS Project Closeout' - brooke-simon


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1
NMCD CMIS Project Closeout

Presenters:

Larry Pacheco, CIO

Dan Donoghue, PM

August 25, 2010

cmis background
CMIS Background
  • Project funding : $1.1m General Fund/$600k NMCD
  • CMIS is the principal electronic offender management system at NMCD. CMIS manages approximately 26,000 offenders from pre-sentencing through probation and parole.
  • Project Goals:
    • Move from client-server to web-based
      • Allow easier maintenance
      • Enhance security
      • Add functionality
      • Consolidate screens
  • Leverage other states’ work through NCOMS consortium.
nmcd ncoms
NMCD & NCOMS
  • NCOMS –National Consortium of

Offender Management Systems

  • Sharing code with other states
      • Idaho to NMCD – OMP
      • NMCD to Utah– F-Track
      • Alaska to NMCD – Booking
      • NMCD to Missouri - Security
      • NMCD to Missouri – OMP
      • Missouri to NMCD - Property
    • Quicker and more cost effective
    • $20-30M system for approximately $5M
cmis status
CMIS Status
  • Budget
    • $1.7m spent/$1.1m from Legislature
  • Schedule
      • 5 change requests
      • Project completed on time
  • Scope – No scope changes
  • IV&V – Project green
  • Vendor – 50 of 52 deliverables accepted
accomplishments
Accomplishments
  • Developed 7 ½ modules over two years. RFP only called for 4.
  • Trained applications staff on new technologies
  • Successful user acceptance
  • Successful train-the-trainer sessions
  • Successfully introducing a paradigm shift for OMP implementation
  • Moved from a maintenance shop to a projectized shop
cmis future plans
CMIS Future Plans
  • FY11 – Continue deploying modules developed in FY09 and FY10.
  • Develop three new modules according to CTA specifications.
  • FY12 – Requesting $400,000 in C2 funding to accelerate module development and deployment.
  • Continue developing and deploying CMIS modules according to CTA specifications.