620 likes | 1.01k Views
E N D
1.
Improving Efficiency & Reliability
of
STEAM TURBINE
Through R & M
BY:
AMITABH SRIVASTAVA
SR.DGM, BHEL HARDWAR
3. RESULTING TO ENHANCED EMPHASIS ON=> REDUCTION IN GENERATION COST ? HIGH EFFICIENCY OF TG CYCLE ? LOWER EQUIPMENT COST ? SHORTER GESTATION PERIOD ? REDUCED MAINTENANCE TIME => INCREASED RELIABILITY => MINIMIZING ENVIRONMENTAL HAZARDS
5. IMPROVEMENT IN STEAM TURBINE PERFORMANCE
7. CONSIDERATIONS IN RETROFITTING & UPGRADATION OF OLDER SETS
8. RETROFITTING & UPGRADATION OF OLDER SETS
9. RETROFITTING & UPGRADATION OF OLDER SETS MAJOR MODIFICATIONS IN
GUIDE & MOVING BLADE
(LATEST STATE OF ART PROFILE)
STEAM FLOWPATH
ROTORS & INNER CASINGS OF TURBINE
SHAFT SEALINGS
[ADVANTAGE IN HEATRATE / OUTPUT CAN BE WORKED OUT ON CASE TO CASE BASIS]
10.
Retrofitting of HP Turbine
with
STATE OF ART REACTION BLADING
14. EXISTING
IMPULSE BLADING
( PRESSURE DROP ONLY IN STATIONARY BLADES)
EFFICIENCY : 83.6 %
(FOR NEW MACHINE)
EFFICIENCY FOR EXISTING CONDITION : ~ 80% NEW
REACTION BLADING ( PRESSURE DROP IN STATIONARY AS WELL AS MOVING BLADES
EFFICIENCY : 86.5 % HP TURBINE
15. ACTIVITIES INVOLVED
REMOVAL OF EXISTING HP ROTOR, LINERS AND DIAPHRAGMS
INSTALLATION OF NEW LINERS FITTED WITH STATIONARY BLADES AND NEW HP ROTOR
FITTING DIMENSIONS ARE TO BE MEASURED DURING PREVIOUS OVERHAUL AND LINERS ARE MACHINED ACCORDINGLY.
REMOVED HP ROTOR AND DIAPHRAGMS CAN BE USED AS SPARE FOR OTHER SETS
16. THE RETROFIT CAN BE DONE WITHIN NORMAL OVERHAUL PERIOD.
PAY BACK PERIOD IS LESS THAN 3 YEARS
19. EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING IMPULSE DESIGN SET DUE TO HP TURBINE REFURBISHMENT INCREASE IN POWER OUTPUT : 8.6 MW
IMPROVEMENT IN HEATRATE : 4%
(FROM EXISTING PERFORMANCE LEVEL OF THE SET WITH RATED STEAM PARAMETERS & THROTTLE STEAM FLOW)
30. EXPECTED PERFORMANCE IMPROVEMENT IN THE EXISTING SET DUE TO LP TURBINE REFURBISHMENT INCREASE IN POWER OUTPUT : 10.1 MW
IMPROVEMENT IN HEATRATE : 102 KCAL / KWH
(FROM EXISTING PERFORMANCE LEVEL OF THE SET WITH RATED STEAM PARAMETERS & THROTTLE STEAM FLOW)
35. TECHNICAL PROPOSAL
36. CROSS SECTIONAL VIEW OF 210 MW STEAM TURBINE
37. EXISTING DESIGN:
39. HP INLET INSERTS
40. HP INLET INSERTS
41. IMPROVEMENTS IN PROPOSED DESIGN:
42. IMPROVEMENTS IN PROPOSED DESIGN: (CONTD.)
43. IMPROVEMENTS IN PROPOSED DESIGN: (CONTD.)
44. HP EXHAUST ELBOWS
45. HP EXHAUST ELBOWS
46. HP EXHAUST ELBOWS
47. SCOPE OF SUPPLY
48. 210 MW STEAM TURBINE (REACTION DESIGN SET-KWU)
49. SCOPE OF SUPPLY (CONTD.)
50. WORK REQUIRED TO BE DONE AT SITE:
51. WORK REQUIRED TO BE DONE AT SITE: (FOR HP Turbine)
52. WORK REQUIRED TO BE DONE AT SITE:(CONTD.)
53. WORK REQUIRED TO BE DONE AT SITE:(CONTD.)
54. WORK REQUIRED TO BE DONE AT SITE:FOR IP Turbine
55. CONDITION AFTER R & M OF HPT & IPT (UNDER RATED CONDITION):
56. EXPECTED PRESENT PERFORMANCE:
57. COMPARISON OF PERFORMANCE:
58. PAY BACK PERIOD
59. PAY BACK PERIOD