Pulsar Construction Schedule. Assembly vendor-Altron Inc loacated in Anoka, MN QTY 2 first article Production 43 units PC vendor is Proto Express (placed by Altron). All long lead components have been purchased by The Univ of Chicago They are being shipped today
E N D
Pulsar Construction Schedule • Assembly vendor-Altron Inc loacated in Anoka, MN • QTY 2 first article • Production 43 units • PC vendor is Proto Express (placed by Altron)
All long lead components have been purchased by The Univ of Chicago • They are being shipped today • First blank boards must be tested and approved by The University of Chicago • Vendor expects to deliver first item by end of April • (HaroldMJS): • Negotiations are in progress. • Harold’s best current estimate is that after we approve the first board, the rest will come in about 3 weeks.