I-80 Robb Drive to Vista Boulevard Design-Build Project. APWA. Jeff Lerud , PE, CPM Project Manager. I-80 Robb Drive to Vista Boulevard Design-Build Project. Concept 1. Pavement Reconstruction: Keystone Ave. to 4 th St. Keystone Ave . 4 th St. Existing Pavement Conditions.
E N D
I-80 Robb Drive to Vista Boulevard Design-Build Project APWA Jeff Lerud, PE, CPM Project Manager
I-80 Robb Drive to Vista Boulevard Design-Build Project
Concept 1 Pavement Reconstruction: Keystone Ave. to 4th St. Keystone Ave. 4th St.
Concept 2 and 3 Concept 2: Intelligent Transportation System (ITS) Concept 3: Signing and Striping Improvements
Intelligent Transportation System ITS Devices • Dynamic Message Signs (DMS) • Travel Time Signs (TTS) • Also • Flow Detectors • CCTV Benefits • Quicker Incident Response Times • Informing the Motorists of Accidents and Travel Times • TRIP RELIABILITY
Concept 2 and 3 Concept 2: Intelligent Transportation System (ITS) Concept 3: Signing and Striping Improvements
Concept 4 and 5 Concept 4Restripe I-80 EB to I-580 SB on-ramp Concept 5Widen Virginia St. WB off-ramp to two lanes
Concept 6 E. McCarran Blvd: Widen EB off-ramp
Concept 7 Storm Drain System Improvements at Robb Drive EB on-ramp to I-80
Concept 8 Sparks Blvd: Loop Ramp; Triple Lefts
Concept 9 Auxiliary Lanes: E. McCarran Blvd to Vista Blvd.
Concept 10 Rock Blvd: Widen EB off-ramp
Concept 11 Robb Dr: Widen WB off-ramp
keeprenosparksmoving.com • Traffic alerts • Customize your Commute • Live cameras • Alternate routes • Construction info • Photos
LANDSCAPE & AESTHETICS I-80 ROBB DRIVE TO VISTA BOULEVARD
Rock Blvd. Keystone Ave. Evans Ave. Robb Drive Sparks Blvd. N. Wells Ave. US-395 Kietzke Lane Ralston St. Pyramid Way McCarran Blvd. West Vista Blvd. McCarran Blvd. West Robb Dr.
Rock Blvd. Keystone Ave. Evans Ave. Vista Boulevard Sparks Blvd. N. Wells Ave. US-395 Kietzke Lane Ralston St. Pyramid Way McCarran Blvd. West Vista Blvd. McCarran Blvd. West Robb Dr.
Project Status • Design will be completed by December, 2011. • The westbound PCCP will be complete this year • The eastbound PCCP work will begin spring, 2012 • Overall project will be completed by December, 2012
Questions? Thank you! Jeff Lerud, Project Manager 775-888-7589 jlerud@dot.state.nv.us