Physicians’ Clinic

Wellness Center. Hospital Main Entrance. Physicians’ Clinic. Replacement Hospital Bond Issue Proposal. Phased Masterplan. PHASE 1 – 67,213sf PHASE 3 – 118,122sf PHASE 5 – 13,223sf Total 198,558sf. Existing Medical Center. Permian Regional Medical Center.

awena
Download Presentation

Physicians’ Clinic

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Wellness Center Hospital Main Entrance Physicians’ Clinic Replacement Hospital Bond Issue Proposal

  2. Phased Masterplan • PHASE 1 – 67,213sf • PHASE 3 – 118,122sf • PHASE 5 – 13,223sf Total 198,558sf

  3. Existing Medical Center PermianRegional Medical Center 134,400 sf • Original Built in 1962 • Original built for 110 beds • Hospital 109,000sf, Doctor’s Clinic 25,400sf • 12 acre campus

  4. PHASE 1 PermianRegional Medical Center 67,213 sf • Wellness Center • Physician’s Clinic • Physical Therapy

  5. PHASE 2 PermianRegionalMedical Center • Demolition of Doctor’s Clinic/Storage Building • Relocate gas/electrical in NE Hospital Drive • Close/demolish portion NE Hospital Drive

  6. PHASE 3 PermianRegionalMedical Center 118,122 sf • New Main Hospital construction • New Central Energy Plant construction • Connect Phase 1 Buildings to new CEP

  7. PHASE 4 PermianRegional Medical Center • Demolition of 3-story hospital • Demolition of existing Central Energy Plant • Demolish original hospital parking/drive

  8. PHASE 5 PermianRegionalMedical Center 13,223 sf • Construction of Dining/Employee Services • Connect permanently to Skilled Nursing Facility • Connect to Central Energy Plant

  9. Departmental Masterplan

  10. Move In 1 mo. Demo 2 mo.s Move In 1 mo. Demo 3 mo.s Move In 1 mo.s Summary Timeline PermianRegional Medical Center 2012 2014 2015 2016 2013 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 Phase 1 - Physician’s Clinic/Wellness Design 6 mos Construction 12 mos Phase 2 – Demolition Phase 3 – Hospital/Central Plant Design 8 mos Construction 15 mos Phase 4 – Demolition Phase 5 - Dining/Connection Design 4 mos Construction 5 mos 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6

  11. Construction Total $ 59,305,087 Project Cost Summary PermianRegionalMedical Center Building Construction • General Construction (198,588 sf) • Demolition • Site Work • Streetwork • Infrastructure • Landscaping Other Costs • Bond Counsel Fees • Design Fees (architecture, engineering) • Printing Costs etc. • Testing • State Reviews and Inspections • Real Estate acquisition • PRMC Move-in expenses