  1. Wellness Center Hospital Main Entrance Physicians’ Clinic Replacement Hospital Bond Issue Proposal

  2. Phased Masterplan • PHASE 1 – 67,213sf • PHASE 3 – 118,122sf • PHASE 5 – 13,223sf Total 198,558sf

  3. Existing Medical Center PermianRegional Medical Center 134,400 sf • Original Built in 1962 • Original built for 110 beds • Hospital 109,000sf, Doctor’s Clinic 25,400sf • 12 acre campus

  4. PHASE 1 PermianRegional Medical Center 67,213 sf • Wellness Center • Physician’s Clinic • Physical Therapy

  5. PHASE 2 PermianRegionalMedical Center • Demolition of Doctor’s Clinic/Storage Building • Relocate gas/electrical in NE Hospital Drive • Close/demolish portion NE Hospital Drive

  6. PHASE 3 PermianRegionalMedical Center 118,122 sf • New Main Hospital construction • New Central Energy Plant construction • Connect Phase 1 Buildings to new CEP

  7. PHASE 4 PermianRegional Medical Center • Demolition of 3-story hospital • Demolition of existing Central Energy Plant • Demolish original hospital parking/drive

  8. PHASE 5 PermianRegionalMedical Center 13,223 sf • Construction of Dining/Employee Services • Connect permanently to Skilled Nursing Facility • Connect to Central Energy Plant

  9. Departmental Masterplan

  10. Move In 1 mo. Demo 2 mo.s Move In 1 mo. Demo 3 mo.s Move In 1 mo.s Summary Timeline PermianRegional Medical Center 2012 2014 2015 2016 2013 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 Phase 1 - Physician’s Clinic/Wellness Design 6 mos Construction 12 mos Phase 2 – Demolition Phase 3 – Hospital/Central Plant Design 8 mos Construction 15 mos Phase 4 – Demolition Phase 5 - Dining/Connection Design 4 mos Construction 5 mos 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6

  11. Construction Total $ 59,305,087 Project Cost Summary PermianRegionalMedical Center Building Construction • General Construction (198,588 sf) • Demolition • Site Work • Streetwork • Infrastructure • Landscaping Other Costs • Bond Counsel Fees • Design Fees (architecture, engineering) • Printing Costs etc. • Testing • State Reviews and Inspections • Real Estate acquisition • PRMC Move-in expenses

  12. Interiors PermianRegionalMedical Center Wellness Area Public Mall

  13. Hospital Main Entrance Wellness Center Hospital Entry Plaza Design & Graphics by Bundy, Young, Sims & Potter, Inc./Trinity Hughes, 2011