An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STAR Status 4/17/2007 J. Sowinski

  2. STAR Progress on Rare Trigger Integrated Luminosity Goal is 300mb-1 Requires 3.6mb-1/day on average 51mb-1 Achievable in ~3hrs tape spinning/day

  3. STAR Progress on MinBias with Narrow Vertex Goal 60M usable evts Est.~80M rec. Need to Rebalance Requires 1.1M evts/day Achievable with 5hrs tape spinning/day 3.7M evts

  4. STAR • Issue with tracking program (minbias) • SSD air compressor failure Sunday eve. • Part expected in today Internal cooling system leaking oil. Interlocks appeared to catch it in time.