An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. August 05, 2013 All Experimenters’Meeting

  2. Startup 2013 Machine Status: • Proton Source Commissioning and Studies • RFQ Injector Line (RIL) • Linac • Booster • Main Injector • Startup and Tuning

  3. Power Outages • PS3 Power Outage • Oil Switch Replacement • Impacts PS3, PW5, & PC3 • Run on generator for ~1 week • Connect generator Monday, July 29th @ 0800 – 1000 • Disconnect generator Friday, August 9th @ 0800-1000

  4. Power Failures • Feeder 46B • Wednesday, July 24th @ 2142 • Impact – Possible F0 ventilation system • Fault located between P71 & F4 • Further isolation and repairs necessary

  5. Kautz Road SubStation • Status • MI backfed from Master SubStation • Using Feeder 45 for MI conventional power which is normally T85 on KRS • We ordered 6+ new surge arrestors (4.7k each) from Hubbell and they were delivered on Friday, July 26th • Schedule: (Weather Dependent) • Monday, August 5th replace T85 surge arrestors • No machine impact (In Progress) • Tuesday, August 6th replace T87 surge arrestors • No beam during work 8-10 hours • After replacement, test both T85 and T87 • There will be a 20 minute MI conventional power outage to remove the backfeed, not scheduled.

  6. MI Startup Activities (~1 Week) • Turn on power supplies and establish ramps • Establish 8 Gevbeam • Match MI8 line lattice with IPM • Tune abort line @8 Gev • Establish 120 Gevbeam • Smooth orbits up the ramp • Tune abort line @ 120 Gev • High field Orbit smoothing (quad moves) (Have data for 1st) • Requires tunnel access (2x8 hrs) • Calibrate tune table • MI8 line lattice matching (1st of 2 passes complete) • Dedicated beam study • Extraction line tune up (NuMI) (Attempting extraction) • Tune up for operation • Deliver low intensity beam to NuMI beam line for target scans • Estimated to take an additional week after MI is tuned up for operations

  7. Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.html