1 / 25

CMS Upgrade for Super-LHC

CMS Upgrade for Super-LHC. Fabrizio Palla INFN Pisa. Outline. CMS activities for SLHC Upgrades needed to withstand a factor 10 higher luminosity Machine related questions from the Working Group 1 Bunch spacing Experimental beam pipe Space requirements Maintenance

akiva
Download Presentation

CMS Upgrade for Super-LHC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CMS Upgrade for Super-LHC Fabrizio Palla INFN Pisa Fabrizio Palla INFN Pisa

  2. Outline • CMS activities for SLHC • Upgrades needed to withstand a factor 10 higher luminosity • Machine related questions from the Working Group 1 • Bunch spacing • Experimental beam pipe • Space requirements • Maintenance • Installation and commissioning Fabrizio Palla INFN Pisa

  3. CMS has held three workshops on SLHC Feb 2004 http://agenda.cern.ch/fullAgenda.php?ida=a036368 General startup July 2004 http://agenda.cern.ch/fullAgenda.php?ida=a041379 Mostly Tracker, Trigger and Electronics July 2005 http://agenda.cern.ch/fullAgenda.php?ida=a053123 Trigger upgrades Important starting point Most CMS systems will survive and continue to operate without changes to inaccessible electronic systems Implies some constraints on future machine operation Major exceptions Tracker - which is expected to be entirely replaced for SLHC Trigger - rebuild L1 processors + there is a strong belief that Tracker information is necessary for L1 trigger SLHC & CMS Fabrizio Palla INFN Pisa

  4. Radiation Issues • Assumed integrated luminosity • LHC: 500 fb-1 • SLHC 2500 fb-1 • Main consequences • Tracking detectors will suffer the largest damage • Need to be rebuild entirely • ECAL • Endcaps need shielding • HCAL • HCAL Endcaps too much radiation, need reconsider the technology • Muons • YE4 better shielding • ME1 needs shielding Fabrizio Palla INFN Pisa

  5. Radiation Issues SLHC Radiation tolerance of current pixel system can be pushed to 3x1015 cm-2 Fabrizio Palla INFN Pisa

  6. Higher granularity and more pixels are required Power requires major effort & new ideas Chip voltages reduce with technology evolution, currents may (??), but number of channels will not Need to bring increased total currents through volumes which can’t expand Material budget should not increase Large systems are hard to build Qualification must be taken seriously True industrial production is likely to be required Sensors are one of many issues Any new material technology must be large-scale commercial within ~5 years Electronic technology evolution will bring benefits and also more complexity and much difficult work Tracker Upgrade Fabrizio Palla INFN Pisa

  7. First ideas for a New Tracker Proposed 3 Pixel Systems that are adapted to fluence/rate and cost levels • Pixel #1 max. fluence system • ~400 SFr/cm2 • Pixel #2 large pixel system • ~100 SFr/cm2 • Pixel #3 large area system • Macro-pixel ~40 SFr/cm2 • 8 Layer pixel system can eventually deal with 1200 tracks per unit pseudo – rapidity Fabrizio Palla INFN Pisa

  8. Installation of modest prototype system at tp = t0 + 5y Less cost and lower risk Less substantial case for support needed More chance of resources, on short time scale Allows trial of components or devices, which may still evolve Human time-scale Prototype contained in the volume from pixel layer 0 to 4 Need to use/reuse service space for pixels Will allow the study of New technologies Occupancy/rates Beam backgrounds Trigger Data links Intermediate prototype Fabrizio Palla INFN Pisa

  9. ECAL Endcaps Unshielded dose rate* 0.2mSv/h =1.48 Supercrystals and their internal components are inaccessible and cannot be replaced. =3 5mSv/h Repair of Supercrystal array would require the dismounting of readout electronics on rear of backplate High activation levels, access time limited *3300 fb-1 Fabrizio Palla INFN Pisa

  10. HCAL Endcaps ECAL HCAL Dose per year at SLHC Scintillator under radiation form color centers that reduces the collected light yield. Current operational limit ~ 5 Mrad Should change the technology in the HCAL endcaps Fabrizio Palla INFN Pisa

  11. Muon chambers Need better shielding of YE/4 (likely to be done before SLHC proper) Need better shielding for ME/1 Fabrizio Palla INFN Pisa

  12. Trigger at SLHC • Occupancy • Degraded performance of algorithms • Larger event size to be read out • New Tracker: higher channel count & occupancy  large factor • Reduces the max level-1 rate for fixed bandwidth readout. • Trigger Rates • Try to hold max L1 rate at 100 kHz by increasing readout bandwidth • Avoid rebuilding front end electronics/readouts where possible • Rebuild L1 processors to work at 80 MHz • Already few cases use 160 MHz processing • Use 40 MHz sampled data to produce trigger primitives with 12.5 ns resolution • Radiation damage -- Increases for part of level-1 trigger located on detector Fabrizio Palla INFN Pisa

  13. Muon L1 Trigger rate at L = 1034 cm-2 s-1 Note limited rejection power (slope) without tracker information Must develop Tracker Trigger at L1 Export some HLT algorithms to L1? Lot of activities going on Tracker Trigger at L1 Fabrizio Palla INFN Pisa

  14. DAQ System LHC DAQ design: A network with Terabit/s aggregate bandwidth is achieved by two stages of switches and a layer of intermediate data concentrators used to optimize the EVB traffic load. RU-BU Event buffers ~100GByte memory cover a real-time interval of seconds SLHC DAQ design: A multi-Terabit/s network congestion free and scalable (as expected from communication industry). In addition to the Level-1 Accept, the Trigger has to transmit to the FEDs additional information such as the event type and the event destination address that is the processing system (CPU, Cluster, TIER..) where the event has to be built and analyzed. The event fragment delivery and therefore the event building will be warranted by the network protocols and (commercial) network internal resources (buffers, multi-path, network processors, etc.) Real time buffers of Pbytes temporary storage disks will cover a real-time interval of days, allowing to the event selection tasks a better exploitation of the available distributed processing power. Fabrizio Palla INFN Pisa

  15. Beam pipe • CMS does not expect any change in the beam pipe material • Beryllium beam pipe at the IP • Beam pipe diameter set by the dynamic aperture of the reproducibility of the beam • Current diameter at the IP is 58 mm • Q: how much can be reduced to allow tests of new structures close to the beam for normal LHC running? • Forward beam pipe diameter can go to 400 mm after HF and its shadow Fabrizio Palla INFN Pisa

  16. Forward shielding rotating system is near the limits of mechanical strength new concept or supplementary system needed Fabrizio Palla INFN Pisa

  17. Forward region:shielding upgrade pots for 2’nd set of jacks at each end built into UXC floor. would form basis of support for a supplementary structure closing around the existing RS time needed to open and close CMS would increase significantly (~1 week per shutdown) Fabrizio Palla INFN Pisa

  18. Bunch spacing • The consequences of switching away from 12.5 ns to 10 or 15 ns could be severe for CMS. • If we can stay with 12.5 ns we may not have to rebuild much of our ECAL, HCAL and Muon front end electronics. • If we change to 10 ns or 15 ns then we most likely have to rebuild most of this electronics. • Need a review within CMS to give exact statements … but guess that the cost could easily exceed 100 MCHF. • Q: it will be beneficial for us if we could only have a “default” scenario and a backup one for the parameters of the SLHC • Offer solid starting point for R&D for the experiments • Allow costs/benefits to be quantified Fabrizio Palla INFN Pisa

  19. Shorter L* • Any element of the machine inside CMS will have consequences in the forward detectors and need to be studied and evaluated once having in hand a proposal from the machine group. • Can accommodate some elements, but it will depend from the proposal • Might re-design the forward shielding • Probable increased sensitivity to beam accidents: super BCM needed • It would be extremely beneficial the experience gained in running the LHC Fabrizio Palla INFN Pisa

  20. The increased activation will seriously affect the maintenance of the detector <10 hours at the Tracker end-flange and 1 hour at the inner ECAL Endcap to reach 5mSv = 1year allowed dose. Those detectors that will not be replaced after the LHC should be very reliable by then Not excluded some systems will be less radiation tolerant than expected. Remote handling might become mandatory in the design of the new detectors and should probably developed for the old ones. Maintenance Fabrizio Palla INFN Pisa

  21. Installation and commissioning issues • Not all changes can be made in a single shutdown. • Installing new shielding might be in conflict with some new detectors installation • Most likely one or more extended shutdowns ( 1 year) will be needed • Tracker installation will take 6 months • Commissioning of the new detectors will be an additional delay • We will get more inputs from the LHC experience • Likely to take at least 6 months after the last cable is connected • Q: How much time is foreseen for installation of the new machine? Fabrizio Palla INFN Pisa

  22. backup Fabrizio Palla INFN Pisa

  23. Fabrizio Palla INFN Pisa

  24. Cost & Power estimate for new Tracker • Pix Sys #1 : 3 layers • 330 mW/cm2 • High f pix400 SFr/cm2 • Pix Sys #2 : 2 layers • 130 mW/cm2 • Large pix100 SFr/cm2 • Pix Sys #3 : 3 layers • 45 mW/cm2 • Macro pix40 SFr/cm2 • Eta =1.4  Area = 18.3 m2 • Mechanics etc. not in costs! • Strip detector~25 mW/cm2 CMS SLHC workshop Feb 2004

  25. Level-1 Latency • Present Latency of 3.2 sec becomes 256 crossings • Assuming rebuild of tracking & preshower electronics will store this many samples • Do we need more? • Yield of crossings for processing only increases from ~70 to ~140 • It’s the cables! • Parts of trigger already using higher frequency • How much more? Justification? • Combination with tracking logic • Increased algorithm complexity • Asynchronous links or FPGA-integrated deserialization require more latency • Finer result granularity may require more processing time • ECAL digital pipeline memory is 256 40 MHz samples = 6.4 sec • Propose this as SLHC Level-1 Latency baseline Fabrizio Palla INFN Pisa

More Related