Yakima Air Terminal. Alpha Taxiway Rehabilitation Improvement Project. Project Overview Project Schedule Impacts Project Status Questions. Presentation Overview. The Yakima Air Terminal has received an $11,000,000 grant. The grant is to:

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Alpha Taxiway Rehabilitation Improvement Project' - agalia


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
presentation overview
Project Overview

Project Schedule

Impacts

Project Status

Questions

Presentation Overview
project overview
The Yakima Air Terminal has received an $11,000,000 grant. The grant is to:
    • Resurface and widen Alpha Taxiway, Taxiway Connectors A1-A5, and portions of Bravo and Charlie Taxiways;
    • Resurface airfield pavement between the north taxiway edge line to the non-movement line;
    • Replace the existing MITL system with LED MITL, including new conduit, fixtures, and regulator;
    • Replace all existing directional and hold short signs; and
    • Correct several markings not meeting FAA standards.
Project Overview
project schedule
Expected construction START DATE July 14, 2014:
    • Phase 1: July 28– August 22
    • Phase 2: August 23 – September 5
    • Phase 3: September 6– September 19
    • Phase 4: September 20 – October 10
    • Phase 5: October 11 – October 31
    • Phase 6 / 7: November 1 – November 30
Project Schedule
impacts
Phase 1: July 28– August 22
    • Ramp Closures.
      • McCormick West, and Plath Hangar.
    • Partial Ramp Closures.
      • Fuel Tank/House and McCormick Air Center.
    • Temporary Runway 9/27 Closure for work within the Runway Safety Area.
    • On-going construction activities and vehicle traffic on service roads and ramps.
Impacts
impacts1
Phase 2: August 23 – September 5
    • Ramp Closures.
      • Airlift Northwest, FedEx Air Cargo and Airport Maintenance Building.
    • Partial Ramp Closures.
      • McCormick Air Center and Private Hangars (formerly Noland-Decoto).
    • Temporary Runway 9/27 Closure for work within the Runway Safety Area.
    • On-going construction activities and vehicle traffic on service roads and ramps.
Impacts
impacts2
Phase 3: September 6– September 19
    • Ramp Closures.
      • GE Aviation, West Itinerant Ramp, Med Assets, and West Terminal Apron Ramp.
    • Partial Ramp Closures.
      • Private Hangars (formerly Noland-Decoto).
    • Temporary Runway 9/27 Closure for work within the Runway Safety Area.
    • On-going construction activities and vehicle traffic on service roads and ramps.
Impacts
impacts3
Phase 4: September 20– October 10
    • Ramp Closures.
      • East Terminal Apron Ramp.
    • Partial Ramp Closures.
      • East Itinerant Ramp.
    • Runway 4/22 and Bravo Taxiway Closed.
    • Temporary Runway 9/27 Closure for work within the Runway Safety Area.
    • On-going construction activities and vehicle traffic on service roads and ramps.
Impacts
impacts4
Phase 5: October 11 – October 31
    • Ramp Closures.
      • No Ramps Closed.
      • Alternate routes required for: Cub Crafters, McAllister Museum, Advanced Medical Systems, and South Air Park.
    • Temporary Runway 9/27 Closure for work within the Runway Safety Area.
    • On-going construction activities and vehicle traffic on service roads and ramps.
Impacts
impacts5
Phase 6: November 1– November 30
    • Partial Ramp closures denoted by barricades.
    • Runway 4/22 closed intermittently.
    • On-going construction activity and vehicle traffic on service roads and taxiways.
Impacts
impacts6
Phase 7: November 1 – November 30
    • Not expecting any closures, however a schedule will be provided of the impacted areas to minimize air traffic and vehicle operations within the work areas.
    • On-going construction activities and vehicle traffic on service roads and ramps.
Impacts
operations during construction
If at all possible, avoid construction areas.
  • Please plan all operations around construction to the maximum extent possible.
    • If there are known operations that will be impacted by the proposed schedule, please let us know.
    • The Airport Management will provide NOTAMs.
  • Do not travel (plane or car) across barricades delineating closed pavement.
  • Do not provide direction to the contractor unless there is an emergency.
Operations During Construction
questions
Robert Peterson

[email protected]

Office: (509) 575-6149 (#7)

Cell: (509) 833-0898

Kris Yalovich

[email protected]

Office: (509) 575-6149 (#7)

Stephanie Ray, PE

[email protected]

(509) 966-7000

Michael Battle, PE

[email protected]

(509) 966-7000

Questions