Explore the discussions from the Joint Sequim City Council and Board of Directors meeting in September 2014. Key points cover lessons learned, varied opinions, common themes, and allocation concerns. New recommendations include enhancing the instructional environment, boosting safety, and planning new constructions at the elementary and high school levels. Detailed cost breakdown is provided for transparency. Additional needs and tax implications are also addressed.
E N D
Facilities PlanFall 2014 Joint Sequim City Council and Sequim Board of Directors’ Meeting Monday, September 29, 2014
Summer Coffee Chats • Lessons Learned • Variety of Opinions • Common Themes • Too Much Money • Too Many Projects • Not Enough Priorities
Highest Priorities • Space for Students • Improve Instructional Environment • Improve Safety and Security
New Recommendation • New Elementary • Greywolf Additions • Four (4) Classrooms • Gymnasium • Serving Kitchen • High School Additions • Six (6) Science Classrooms • Band and Choir Classrooms • Minor Renovation of Performing Arts Center • Demolish Community School (1950)
How Much? • New Elementary $ 27,807,000 • Greywolf Additions $ 7,242,000 • High School Additions $ 11,005,000 • Community School Demolition $ 662,400 • Total $ 46,716,400
Additional Needs • District’s Base Kitchen • Haller Elementary • Minor Renovations to A and B Buildings • Relocate Olympic Peninsula Academy to Haller Elementary • Consider Future Use of C and D Buildings for Kindergarten Center or Intermediate School • Convert Community School (1979) to Maintenance and Warehouse Building • High School • Minor Renovations to Existing Science Building