Present Status of PPP Institutes as on September-2009. Name of the I.T.I. :- INDUSTRIAL TRAINING INSTITUTE,AMBAJOGAI,BEED.Name of the Scheme:- PUBLIC PRIVATE PARTNERSHIPWhether ITI is covered under Top Ten:- YES.1.INNOVATIVE DECISIONS TAKEN BY I.M.C..

Samuel
Download Presentation

monthly progress report of iti covered under ppp. reporting month september 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. Monthly progress report of ITI covered under PPP.Reporting Month September 2009 INDUSTRIAL TRAINING INSTITUTE,AMBAJOGAI, DIST.BEED. WELCOMES YOU

    3. 2.Chairman owns the IMC & ITI & devote sufficient time for ITI(Initiatives taken by IMC)

    4. 3.Planning of utilization of 2.5 Crore (Exp.In Lakhs)

    5. 4. Status of Expenditure under PPP ITI(Expenditure in lakhs)

    6. 5.Good practices implemented in ITIs

    7. 6.10 it is to come up to the level of Aundh,Pune by the end of Dec.2009

    8. 6(a). Beatification of Premises

    9. 6(b).Providing Audio visual room & conference hall. Construction Under Progress

    10. 6 (C). Modernization of Class rooms Class Rooms Are New & Equipped with new furniture /White boards.

    11. 6 (d). Construction of Hostel Building 75% completed HOSTEL TO ACCOMMODATE 50 TRAINEES.

    12. 6 (e). Construction of First Floor. Flooring & Electrification with coloring remaining.

    13. 6 (f). Garden in Front of the Main Building. Leveling is complete/Work will commence within a month/Ample water is available.

    14. 7.Restructuring of non performing IMCs.

    15. 8.Admission Status Aug.2009-Trdes introduced under PPP only

    16. 9. Enrolment of trainees in August 2009 session under PPP

    17. 10.Training career & Placement cell

    18. 11.Environmental Management Framework

    19. 13.Progress of Civil Work (WB)

    20. 14.Construction Status (PPP)

    21. 15.Procurement Status (PPP)

    22. 16.Revenue Generation

    23. 17.Action Plan For Next 6 Months