activity on arrow aoa network diagrams l.
Download
Skip this Video
Loading SlideShow in 5 Seconds..
Activity on Arrow (AoA) Network Diagrams PowerPoint Presentation
Download Presentation
Activity on Arrow (AoA) Network Diagrams

Loading in 2 Seconds...

play fullscreen
1 / 6

Activity on Arrow (AoA) Network Diagrams - PowerPoint PPT Presentation


  • 2476 Views
  • Uploaded on

Activity on Arrow (AoA) Network Diagrams. K, L depends on A, B. K depends on A, B. A. A. K. K. a. b. B. B. L. K depends on A but L depends on both A, B. K depends on A, B and L depends only on B. A. K. A. K. c. d. B. L. B. L. A. K. A. K. C. f. C. M. e. B. L. B.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Activity on Arrow (AoA) Network Diagrams' - JasminFlorian


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
activity on arrow aoa network diagrams
Activity on Arrow (AoA) Network Diagrams

K, L depends on A, B

K depends on A, B

A

A

K

K

a.

b.

B

B

L

K depends on A but L depends on both A, B

K depends on A, B and L depends

only on B

A

K

A

K

c.

d.

B

L

B

L

slide2

A

K

A

K

C

f.

C

M

e.

B

L

B

L

K depends on A, C and L depends on B, C

  • K depends on A, C; L depends on B, C
  • and M depends on C
air traffic control tower
Air Traffic Control Tower

A proposed ATC tower uses a control console which has to be meet the needs of the particular airfield.

Activities InvolvedDuration (weeks)

Design console 3

Order console 2

Fabricate and deliver console 16

Install console 2

Test console 4

Design tower 5

Design foundations 1

Order foundations material 1

Deliver foundations material 1

Construct foundations 1

Order tower construction materials 2

Deliver tower construction materials 3

Erect tower 8

1. Draw the AoA network diagram (assuming that design of the foundations is dependent on the design of the tower).

2. Fill in all the information in the Table’s outline of the Early, Late, Floats and determine the Critical Path

aoa network diagram atc tower
AoA Network Diagram (ATC tower)

Order console

Design console

Fabricate and deliver console

2

4

2

3

16

Order

fnd.

material

Deliver

fnd.

material

Design

tower

Design

fnds.

Construct

fnd.

Erect

tower

Install

console

Test

console

0

8

10

12

14

18

20

22

24

5

1

3

3

3

3

3

3

Order tower

material

Deliver tower

material

16

3

3

slide6
Note: When to use IDENTITY and LOGIC “dummy” activities indicated in the CPA notes on Prof. Rowlinson’s Y2 notes

Refer to:

Lockyer, Keith (1984) Critical Path Analysis and other Project Network Techniques, Pitman, London. (pg 19-22)

Main Library 658.4032 L81