Baselining meco
This presentation is the property of its rightful owner.
Sponsored Links
1 / 9

Baselining MECO PowerPoint PPT Presentation


  • 150 Views
  • Uploaded on
  • Presentation posted in: General

Baselining MECO. Michael Hebert UC Irvine Feb 6, 2005 MECO Collaboration Meeting. We have eight weeks to develop our understanding of the project to a point where we are likely to pass a baseline review. We need:

Download Presentation

Baselining MECO

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Baselining meco

Baselining MECO

Michael Hebert

UC Irvine

Feb 6, 2005

MECO Collaboration Meeting


The bottom line up front

We have eight weeks to develop our understanding of the project to a point where we are likely to pass a baseline review. We need:

A complete Work Breakdown Structure with its associated Dictionary – in sufficient detail to make an accurate accounting of the cost and schedule of events. Typically this is down to level 7 or more to set the scale

A complete set of Cost Books to accompany the cost estimate – a collection of all of the input data and calculations used to come up with the cost numbers. Ideally vendor quotes based upon detailed drawings from engineering designs. If this is a strict baseline review, we will need one or more piece of supporting info for every cost number at the lowest level, i.e. these things are tomes

A complete Resource Loaded Schedule (RLS) –the Project file containing all of the schedule links within each subsystem, between subsystems and between MECO and AGS pieces. This should have labor leveled to the extent possible and, combined with the costs, should match the funding profile we expect

A completely updated Technical Design Report

A revised Project Management Plan

The Bottom Line Up Front

Michael Hebert, UC Irvine Baselining MECO


Current meco project organization

Current MECO Project Organization

JOINT OVERSIGHT GROUP NSF; DOE NP; DOE HEP; NSERC

RSVP PROJECT DIRECTOR and DEPUTY

W. Willis, J. Kotcher

KOPIO PM

WBS 1.2

M. Marx

MECO PM

WBS 1.3

M. Hebert

BNL PM

WBS 1.4

P. Pile

1.3.11 MECO Project Office

1.3.1 Extinction W. Molzon (acting)

1.3.5 Tracker E. Hungerford

1.3.9 Integ. & Install. MECO CME

Chief Mechanical Engineer

1.3.2 Target & Shield

M. Hebert (acting)

1.3.6 Calorimeter

P. Nemethy

1.3.10 Simulations Y. Kolomensky

Chief Electrical Engineer

1.3.3 Solenoids B. Smith

1.3.7 C R Shield

J. Kane

Cost & Schedule Manager

1.3.8 Trigger & DAQ K. Kumar

1.3.4 Muon Beamline W. Morse

Michael Hebert, UC Irvine Baselining MECO


Status of baseline info wbs

For most systems the Work Breakdown Structure is in reasonable shape in that is appears deep enough to provide the needed details. There are exceptions, however;

1.3.2 Heat Shield – for lack of someone to take on this task I have been handling this and have not dedicated enough time to evolve this to my satisfaction

1.3.9 Simulations – This would benefit from another pass and some detailed input from each of the detector systems on what they need when as design decisions are made

1.3.10 Installation and Integration – we need to either migrate installation tasks from each of the subdetectors to this area, or abandon the idea for the time being. The original notion was to unify this effort under the control of the MECO Chief Mechanical Engineer, a position we have not yet filled.

One consistent problem is that the WBS Dictionary is still very sparse below level 3 and in many cases there appears to be confusion between definition of the task/object and detailing the cost calculations. The latter are part of the Cost Book.

Status of Baseline Info – WBS

Michael Hebert, UC Irvine Baselining MECO


Status of baseline info costs cost books

We have gone through one, relatively cursory, round of cost reviewing for the experiment including the magnets. The results of that review suggest that the committees did not find major problems, but they did not have time to drill deeply into the underlying assumptions and details.

One point the LOG review made was that we appear to be very light on Technician labor, at least in relation to Scientists. Although part of this is due to AGS work being in a separate WBS, it is worth a second look

In general all costs need more scrubbing. We need to get more people looking at each of these costs (up to now it has been Bill and I and the subsystem manager). I am looking for volunteers.

Cost Books: My preferred approach is to do this electronically, although AGS and KOPIO will likely just go with binders. In detail;

The basic cost info is dumped to a PDF file from the Access database (loaded shortly before the review by RSVP PO)

Additional info (quotes, sketches, calculations on napkins) get scanned into PDF files and appended to each subsection

Status of Baseline Info – Costs & Cost Books

Michael Hebert, UC Irvine Baselining MECO


Status of baseline info rls

I was asked to come up with a labor profile over the five year construction project in the LOG Review. I was pleasantly surprised to find that there is a substantial amount of schedule information already in the Project file.

That said, the current file does not have the latest Magnet schedule info in it, nor has it undergone any sort of internal vetting.

Last week I learned that RSVP is going to request a first look at how well our cost profile matches the expected funding profile, preferably next week. I have rearranged the baselining schedule to make an attempt at that.

In particular I would like to get a list of major milestone dates in each subsystem in the next two weeks. Details in the baseline plan to follow.

Status of Baseline Info – RLS

Michael Hebert, UC Irvine Baselining MECO


Status of baseline info tdr

This document has not been updated since immediately prior to the June 2001 NSF Program review.

I believe the cost and schedule efforts will benefit from updating this sooner rather than later as it will force a rethink of everything in the system and provide background to anyone helping in the scrubbing process.

The first step in the process of updating this information is to produce or revise the Reference Design Documents for each major piece of MECO, as these amount to version-controlled parameter lists and can be plugged directly into the Cost Book to provide the drawings and channel counts needed.

Pulling the TDR together is another place where I could use one or more volunteer editors

Status of Baseline Info – TDR

Michael Hebert, UC Irvine Baselining MECO


Status of baseline info man plan

This document has remained largely unchanged since 2003, meaning it does not reflect the current management structure.

There are numerous aspects of this that remain unclear as I outlined in the previous talk.

The primary need for the baselining effort is an RSVP Management Plan and Project Execution Plan; the MECO, KOPIO, and AGS plans are likely to be appendices.

In short, I am holding off on revising this given my perception of its relatively low priority.

Status of Baseline Info – Man. Plan

Michael Hebert, UC Irvine Baselining MECO


A revised schedule of events

Pre-baseline Review in “early April”

Baseline Review in “late April”

A Revised Schedule of Events

  • First look at cost profile in two weeks

Michael Hebert, UC Irvine Baselining MECO


  • Login