New england single source contingency
This presentation is the property of its rightful owner.
Sponsored Links
1 / 3

New England Single Source Contingency PowerPoint PPT Presentation


  • 88 Views
  • Uploaded on
  • Presentation posted in: General

New England Single Source Contingency. Peter Brandien, Vice President System Operations NEPOOL Reliability Committee August 25, 2010. Overview.

Download Presentation

New England Single Source Contingency

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


New england single source contingency

New England Single Source Contingency

Peter Brandien, Vice President System Operations

NEPOOL Reliability Committee

August 25, 2010


Overview

Overview

One of the action items from the July 20 RC Meeting was to provide an analysis of the HQ Phase II limit for the summer months of June-Sept 2007-2009 similar to what was done for the NY-NE Interface

These limits are posted to the ISO-NE website: http://www.iso-ne.com/trans/ops/limits/ssc/ssc.do

The following table provides the information requested


New england single source contingency

Real Time HQ Phase II Transfer Capability (MW)