1 / 39

Constraint Schedule Management

Constraint Schedule Management. February 7, 2006. Agenda. What is CSM? Workshop Goals Background The Conceptual Design What’s Next. What is CSM?. TBL’s proposed method for managing it’s network flowgate ATC & constraints: Based on nodal Sources and Sinks

waldemar
Download Presentation

Constraint Schedule Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Constraint Schedule Management February 7, 2006

  2. Agenda • What is CSM? • Workshop Goals • Background • The Conceptual Design • What’s Next

  3. What is CSM? TBL’s proposed method for managing it’s network flowgate ATC & constraints: • Based on nodal Sources and Sinks • Utilizing Reservation, e-Tag, Generation & Load Forecast information to apply predictive and proactive analysis to make commercial transmission decisions • Strives to prevent flows exceeding flowgate OTC whenever possible • Endeavors to use industry standard tools and processes while supporting our Tariff

  4. Workshop Goals • Describe the work that preceded this meeting • Demonstrate that BPA’s internal network is constrained • Clarify TBL’s approach to studying CSM • Provide detail for some CSM conceptual design elements: • Source/Sink vs. POR/POD • PUFs & the Nodal Concept • Impacts on reservations & the predictive reservation process • Impacts on scheduled transactions • Impacts on non-scheduled transactions • Curtailments • Redispatch of non-scheduled transactions • Identify the design elements the CSM team will be defining in the upcoming weeks • Communicate the public involvement process & upcoming timeline

  5. How We Got Here: Background • Picked up from where regional CSM team left off • Evaluated 6 options • Selected nodal grouping option combined with reservation impact deeming option based on TBL criteria. • Started out assuming we would calculate flowgate impacts based on nodal PORs & nodal PODs • Held two customer workshops & numerous customer meetings • Conducted extensive internal analysis & design development efforts

  6. CSM Options Considered: Background OATT 33.2 – 33.5

  7. NW Transmission System Problems During Summer OperationBPA Transmission Business LineMike VilesJanuary 2006

  8. Transmission Loading Characteristics • NW load peaks in Winter • Heaviest power flows are east to west • California peaks in Summer • Heaviest power flows are north to south

  9. Figure 1: NW Paths & Seasonal Direction of Powerflow Summer Transfers Winter Transfers Constrained Transmission Path

  10. Summer 2005 Problem Areas • North of Hanford Path • Monitors flow of power on two 500-kV lines on eastside of Cascade Mountains. • Paul-Allston Path • Monitors flow of power on two 500-kV lines between Olympia and Longview. • Allston-Keeler Path • Monitors flow on one 500-kV line between Longview and Portland

  11. Problems • Exceeding the Operational Transfer Capability (OTC) of these paths • Operating above an OTC creates risk of unreliable system response to critical contingences • WECC requires that the actual flow on these paths get below the OTC within 30 minutes

  12. Response to OTC Excursions • In August 2005 there were 29 periods when the OTC of one of these paths was exceeded for at least 5 minutes (Table 1) • 20 of these OTC excursions required dispatcher action to reduce the flow on the path (Table 2) • In some cases, the dispatcher action is significant

  13. Summary of System Problems During Summer Operation • The transmission system was operated “closer to the edge” in summer 2005 than summer 2004 and 2003 (i.e., more OTC excursions) • OTC excursions can result in significant dispatcher action to control

  14. What We Learned from You: Background • Changing current PORs & PODs to nodal PORs & PODs would have a negative impact with minimal benefit • Flowgate impact assessment based on POR/PODs reflects only one segment of the whole transaction and is not accurate in many cases • Using nodal source & nodal sink data provides more accurate flowgate impact analysis • Requiring additional schedules for in-control-area NT transactions would not be viable • Achieving the CSM objectives without affecting the customers’ reservation process would be beneficial

  15. CSM Conceptual Design Source/Sink vs. POR/POD • Technical analysis indicated that POR/POD (previous concept) did not provide true indication of flowgate impacts • Examination of the reservation & e-Tag model revealed that Source & Sink (if specific enough, i.e. nodal) provides true indication of energy flows • With the accurate impacts of each schedule known (via nodal Source and Sink): • Non-Firm ATC inventory can be calculated for internal flowgates • ATC impacts of a reservation on the network flowgates can be computed • The non-firm flows can be effectively managed separately from the firm flows • Relief on a flowgate during a constraint can be effective without being unduly discriminatory

  16. CSM Conceptual Design Source/Sink vs POR/POD (Example #1):

  17. CSM Conceptual Design Source/Sink vs POR/POD (Example #2):

  18. CSM Conceptual Design Source/Sink vs POR/POD (Example #3):

  19. CSM Conceptual Design PUFs & the Nodal Concept: • PUFs are an impedance based measurement of the electrical system impacts of an injection of energy into and withdrawal out of the interconnected WECC transmission system • TBL has developed a methodology for grouping electrical system sources & sinks (customer delivery points & generation integration points) into “Nodes” that have similar electrical effects on all BPA network flowgates • Using these nodes in conducting transmission business allows TBL to calculate the impacts on our flowgates, while minimizing the amount of detailed data required • A grouping of electrical system sources & sinks with +/- 10% similarity is proposed as the starting point for discussion • This concept is portable to other control areas’ systems and flowgates

  20. CSM Conceptual Design PUFs & the Nodal Concept (continued): +/- 10%

  21. CSM Conceptual Design Making Transmission Reservations: • No change required in POR/POD granularity for making a transmission request in any market • Nodal source & nodal sink will not be required on reservations • Specification of nodal source & nodal sink will be optional for reservations • If nodal source and sink are provided, the schedule source/sink nodes must match those in the reservation at the nodal level • Using nodal sources and sinks to assess ATC impact allows TBL to look at the impact of all segments of the transaction

  22. CSM Conceptual Design Determining Reservation Impacts: • If you do specify a nodal source & sink, the flowgate impacts of the request will be based on specified nodal source(s)/sink(s) • If you do not specify a nodal source & sink, the flowgate impacts of the request will be based on deemed nodal source(s)/sink(s) • The deemed nodal source(s)/sink(s) will be determined using past scheduling activity on similar reservations • Deemed nodal source(s)/sink(s) will be transparent to the requestor • A scenario analyzer will allow the requestor to view the deemed impacts • You can assess the deemed source(s)/sink(s) to determine whether or not to specify a nodal source/sink • The deeming algorithm will be continuously tested and refined

  23. CSM Conceptual Design Impacts on Scheduled Transactions: • All of the sources & sinks required on TBL schedules must be at a nodal level of granularity • Flowgate impacts of scheduled transactions will be computed using nodal source & sink data for purposes of: • Calculation of HNF ATC • Calculation of curtailment distributions across products, customers and transactions • Transmission tagged & scheduled to deliver consolidated generation (like BPASLICE) will need to be scheduled using nodal sources • Transmission tagged & scheduled to serve consolidated load (like BPAPOWER), will need to be scheduled using nodal sinks

  24. CSM Conceptual Design Impacts on Non-Scheduled Transactions: • Non-scheduled transactions must provide their appropriate share of congestion relief • TBL has developed a CSM concept for managing the portion of congestion caused by non-scheduled NT transactions served by federal power sales • This concept does not require these transactions to be scheduled if they are not scheduled today • This concept is based on determining flowgate impacts of non-scheduled transactions served by federal power sales by performing a powerflow analysis using nodal load forecasts and nodal federal power sales patterns

  25. CSM Conceptual Design Curtailments: • Flowgate impacts must be calculated for all known network flows (scheduled & non-scheduled) in order to enable network curtailment/redispatch • All scheduled transactions must be curtailed via the e-Tag • Distribution of curtailment MW’s amongst transactions will be determined based on “effective” and “non-discriminatory” requirements in the TBL OATT • TBL will use NERC priorities for curtailments

  26. CSM Conceptual Design Redispatch of Non-Scheduled NT Transactions: • TBL is required to reduce firm NT and PTP flowgate impacts simultaneously & equitably to manage a constraint • “Attachment K” to the TBL OATT provides guidance about NT redispatch for the applicable rate period

  27. CSM Conceptual Design Redispatch of Non-Scheduled NT Transactions (continued): • Our Design: • Calculate the pro rata share of non-scheduled federal NT service and scheduled service impacting a flowgate • Relieve congestion via federal redispatch for non-scheduled federal NT service • Relieve the balance of the congestion via curtailment of schedules • TBL will obtain the federal generator base points on a nodal level (updated as needed) • TBL will require timely and accurate nodal NT load forecasts • A power flow using this data will determine the flowgate impacts of non-scheduled NT service • This allows for calculation of the redispatch requirements to relieve the NT portion of the flowgate constraint if needed

  28. CSM Conceptual Design Sequence of Constraint Relief: Curtail PTP Non-Firm Secondary (1-NS) Curtail PTP Non-Firm Hourly (2-NH) Curtail Non-Firm Network (6-NN) Scheduled Transactions (7-F) Non-Scheduled Transactions Redispatch (OATT Attachment K) for federal Hydro-served NT Load in the BPA Control Area OATT Curtailments Non-OATT Curtailments Load Shedding

  29. CSM Conceptual Design What We’re Currently Working On: • Precisely how ATC will be calculated & managed for all markets? • What method will be used to determine which Non-Firm schedules are cut during a curtailment? • What method will be used to determine which Firm schedules are cut during a curtailment? • Affects on Energy Imbalance?

  30. CSM Conceptual Design Future Analysis: • Will LTF contract holders be held to scheduling practices using nodal sources and sinks consistent with the PORs/PODs requested in their contract? • How will CSM affect: • Loss returns • Federal reserve obligations • Dynamic schedules • Slice • AGC (both for us and for adjacent CA’s)

  31. What’s Next? Phase 2 of Conceptual Design Rollout: • Targeted for Spring, 2006 • TBL will share our proposed design for implementing ATC, Non-Firm & Firm curtailments on the network and energy imbalance • Share the remainder of proposed design • Provide forum for CSM model discussion & answering questions • Clarify any restrictions regarding the use of long-term contracts in scheduling • Provide you with a template for documenting the impacts of implementing CSM on your business & systems

  32. What’s Next? Impact Analysis of Conceptual Design: • You will have a 60-day comment period • We are available to work with you at your request in assessing the impacts of the proposed CSM design on your organization • We will compile all customer impacts • We will schedule an impact review session during a customer workshop • Reevaluate design if necessary based on impacts

  33. What’s Next? Implementation Activities: • TBL will work with its adjacent control areas to implement changes to their registered sources & sinks to be nodal • TBL will include a test period in the implementation plan to measure and improve CSM processes before use in curtailment and redispatch • Implementation will be phased into logical segments • TBL will provide substantial communication to customers leading up to and throughout the implementation process

  34. What’s Next? Decision Point: • Sponsor Go/No-Go Implementation Decision • Targeted for June of 2006 • Based on: • Completed conceptual design • Completed business case • Proposed implementation plan (high level) • Customer impacts data and summarization

  35. Thank you Your comments are appreciated!

More Related