An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Managing ProjectProcesses

  2. Characteristics of a Project • A unique, one-time effort • Requires completion of a large number of interrelated activities • Resources, such as time and/or money, are limited • Typically has its own management structure

  3. Critical Path Method (CPM) • Designed to provide intense micro-control • System is dynamic; it continues to provide periodic reports as project progresses

  4. Manager’s View of CPM • List of project activities • Precedence relationship among activities • Estimate of each activity’s duration CPM processing procedures • Estimated duration of project • Identification of critical activities • Amount of slack for each activity

  5. d 6 3 b f h a 5 1 2 8 c g i 4 e 7 CPM Terminology • Activity • A task or certain amount of work required in the project • Requires time to complete • Represented by an arc (AOA) or a node (AON) • Dummy activity (AOA only) • Indicates only precedence relationships • Does not require any time of effort

  6. d 6 3 b f h a 5 1 2 8 c g i 4 e 7 CPM Terminology • Network • Shows sequential relationships among activities using nodes and arrows

  7. CPM Terminology • Path • Connected sequence of activities leading from starting event to ending event • Critical path • Longest path (time); determines project duration • Critical activities • All of the activities that make up critical path

  8. CPM Terminology • Earliest start (ES) • Earliest that an activity can begin; assumes all preceding activities have been completed • Earliest finish (EF) • ES + activity time • Latest finish (LF) • Latest that an activity can finish and not change project completion time • Latest start (LS) • LF - activity time

  9. Steps in CPM Analysis • Draw the CPM network • A graphic view of relationships among required activities • Path analysis • Determine length of each path (time required to complete each path) • Longest path is the critical path

  10. Steps in CPM Analysis • Network analysis • Working from left to right, find the EF and ES for each activity • Working from right to left, find LF and LS for each activity • Compute activity’s slack • Total Slack = LS - ES = LF - EF • This slack is shared with other activities • Free slack • Time an activity may be delayed without impacting the ES of successor activities

  11. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. B Select site and do site survey. C Select equipment. D Prepare final construction plans and layout. E Bring utilities to the site. F Interview applicants and fill positions in nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. H Construct the hospital. I Develop an information system. J Install the equipment. K Train nurses and support staff. St. Adolf’s Hospital

  12. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop an information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J St. Adolf’s Hospital

  13. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J St. Adolf’s Hospital Completion Time

  14. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 Start St. Adolf’s Hospital Completion Time

  15. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 Start B 9 St. Adolf’s Hospital Completion Time

  16. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 C 10 Start B 9 St. Adolf’s Hospital Completion Time

  17. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 C 10 Start B 9 D 10 St. Adolf’s Hospital Completion Time

  18. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 C 10 Start B 9 D 10 E 24 St. Adolf’s Hospital Completion Time

  19. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 C 10 Start B 9 D 10 E 24 St. Adolf’s Hospital Completion Time

  20. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 C 10 G 35 Start B 9 D 10 E 24 St. Adolf’s Hospital Completion Time

  21. Immediate Activity Description Predecessor(s) A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 C 10 G 35 Start B 9 D 10 H 40 E 24 St. Adolf’s Hospital Completion Time

  22. Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 C 10 G 35 Start B 9 D 10 H 40 E 24 St. Adolf’s Hospital Completion Time

  23. Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 C 10 G 35 Start B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  24. Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  25. Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  26. Path Expected Time (wks) A-F-K 28 A-I-K 33 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  27. Path Expected Time (wks) A-F-K 28 A-I-K 33 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  28. Path Expected Time (wks) A-F-K 28 A-I-K 33 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 Immediate Activity Description Predecessor(s) I 15 A Select administrative and medical staff. — B Select site and do site survey. — C Select equipment. A D Prepare final construction plans and layout. B E Bring utilities to the site. B F Interview applicants and fill positions in nursing, support staff, maintenance, and security. A G Purchase and take delivery of equipment. C H Construct the hospital. D I Develop and information system. A J Install the equipment. E,G,H K Train nurses and support staff. F,I,J A 12 F 10 K 6 C 10 G 35 Start Finish B 9 D 10 H 40 J 4 E 24 St. Adolf’s Hospital Completion Time

  29. I 15 F 10 A 12 K 6 C 10 G 35 Start Finish H 40 J 4 B 9 D 10 E 24 St. Adolf’s Hospital Earliest Start and Earliest Finish Times

  30. I 15 Earliest start time F 10 A 12 K 6 0 C 10 G 35 Start Finish H 40 J 4 B 9 D 10 E 24 St. Adolf’s Hospital Earliest Start and Earliest Finish Times

  31. I 15 Earliest finish time Earliest start time F 10 A 12 K 6 0 12 C 10 G 35 Start Finish H 40 J 4 B 9 D 10 E 24 St. Adolf’s Hospital Earliest Start and Earliest Finish Times

  32. I 15 F 10 A 12 K 6 0 12 C 10 G 35 Start Finish H 40 J 4 B 9 D 10 0 9 E 24 St. Adolf’s Hospital Earliest Start and Earliest Finish Times

  33. I 15 F 10 A 12 K 6 0 12 C 10 G 35 Start Finish H 40 J 4 B 9 D 10 9 19 0 9 E 24 9 33 St. Adolf’s Hospital Earliest Start and Earliest Finish Times

  34. I 15 12 27 F 10 A 12 K 6 0 12 12 22 C 10 G 35 12 22 Start Finish H 40 J 4 B 9 D 10 9 19 0 9 E 24 9 33 St. Adolf’s Hospital Earliest Start and Earliest Finish Times

  35. I 15 12 27 F 10 A 12 K 6 0 12 12 22 C 10 G 35 12 22 Start Finish H 40 J 4 B 9 D 10 9 19 19 59 0 9 E 24 9 33 St. Adolf’s Hospital Earliest Start and Earliest Finish Times

  36. I 15 12 27 F 10 A 12 K 6 0 12 12 22 C 10 G 35 12 22 22 57 Start Finish H 40 J 4 B 9 D 10 9 19 19 59 0 9 E 24 9 33 St. Adolf’s Hospital Earliest Start and Earliest Finish Times

  37. I 15 12 27 F 10 A 12 K 6 0 12 12 22 C 10 G 35 12 22 22 57 Start Finish H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 E 24 9 33 St. Adolf’s Hospital Earliest Start and Earliest Finish Times

  38. I 15 12 27 F 10 A 12 K 6 0 12 63 69 12 22 C 10 G 35 12 22 22 57 Start Finish H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 E 24 9 33 St. Adolf’s Hospital Latest Start and Latest Finish Times

  39. I 15 12 27 F 10 A 12 K 6 0 12 63 69 12 22 Latest finish time 63 69 C 10 G 35 12 22 22 57 Start Finish H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 E 24 9 33 St. Adolf’s Hospital Latest Start and Latest Finish Times

  40. I 15 12 27 F 10 A 12 K 6 Latest start time 0 12 63 69 12 22 Latest finish time 63 69 C 10 G 35 12 22 22 57 Start Finish H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 E 24 9 33 St. Adolf’s Hospital Latest Start and Latest Finish Times

  41. I 15 12 27 48 63 F 10 A 12 K 6 0 12 63 69 12 22 63 69 53 63 C 10 G 35 12 22 22 57 Start Finish H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 59 63 E 24 9 33 St. Adolf’s Hospital Latest Start and Latest Finish Times

  42. I 15 12 27 48 63 F 10 A 12 K 6 0 12 63 69 12 22 63 69 53 63 C 10 G 35 12 22 22 57 Start Finish 24 59 H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 E 24 9 33 35 59 St. Adolf’s Hospital Latest Start and Latest Finish Times

  43. I 15 12 27 48 63 F 10 A 12 K 6 0 12 63 69 12 22 63 69 53 63 C 10 G 35 12 22 22 57 Start Finish 24 59 14 24 H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 E 24 9 33 35 59 St. Adolf’s Hospital Latest Start and Latest Finish Times

  44. I 15 12 27 Earliest start time Earliest finish time 48 63 Latest start time Latest finish time F 10 A 12 K 6 0 12 63 69 12 22 63 69 53 63 2 14 C 10 G 35 12 22 22 57 Start Finish 24 59 14 24 Critical path H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59 St. Adolf’s Hospital Latest Start and Latest Finish Times

  45. St. Adolf’s Hospital Gantt Charts

  46. I 15 12 27 48 63 F 10 A 12 K 6 0 12 63 69 12 22 63 69 53 63 2 14 C 10 G 35 12 22 22 57 Start Finish 24 59 14 24 H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59 St. Adolf’s Hospital Activity Slack Analysis

  47. Activity Slack I 15 12 27 48 63 F 10 A 12 K 6 0 12 63 69 12 22 63 69 53 63 2 14 C 10 G 35 12 22 22 57 Finish Start 24 59 14 24 H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59 St. Adolf’s Hospital Activity Slack Analysis

  48. Activity Slack I 15 12 27 48 63 Slack = LS – ES or Slack = LF – EF F 10 A 12 K 6 0 12 63 69 12 22 63 69 53 63 2 14 C 10 G 35 12 22 22 57 Finish Start 24 59 14 24 H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59 St. Adolf’s Hospital Activity Slack Analysis

  49. Activity Slack I 15 12 27 48 63 SlackK = 63 – 63 or SlackK = 69 – 69 F 10 A 12 0 12 12 22 53 63 2 14 C 10 G 35 12 22 22 57 Finish Start 24 59 14 24 H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59 St. Adolf’s Hospital K 6 63 69 63 69 Activity Slack Analysis

  50. Activity Slack I 15 12 27 48 63 SlackK = 0 or SlackK = 0 F 10 A 12 K 6 0 12 63 69 12 22 63 69 53 63 2 14 C 10 G 35 12 22 22 57 Finish Start 24 59 14 24 H 40 J 4 B 9 D 10 9 19 19 59 59 63 0 9 19 59 59 63 9 19 0 9 E 24 9 33 35 59 St. Adolf’s Hospital Activity Slack Analysis