CENF Safety Analysis Status 6 Feb 2014

CENF Safety Analysis Status 6 Feb 2014. CENF Project is in 3 zones (preparation for the safety folder): Primary beam line. Target and Secondary beam areas. EHN1 experimental area extension. Safety aspects for Construction, Operation and Dismantling are treated separately.

thuyet
Download Presentation

CENF Safety Analysis Status 6 Feb 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CENF Safety Analysis Status6 Feb 2014

  2. CENF Project is in 3 zones (preparation for the safety folder): • Primary beam line. • Target and Secondary beam areas. • EHN1 experimental area extension. • Safety aspects for Construction, Operation and Dismantling are treated • separately. • Operation includes commissioning, shutdown activities etc.

  3. Preliminary Risk Analysis for CENF SB areas • Motivation is for the “Access System” , which has two parts: Access control and Beam protection. • Interlocks cannot protect from activated materials • Access system will ensure correct ventilation for access • Specialist access is needed for equipment in cooling room/service pit • Non- Access system safety systems: • Many hazards will be controlled by procedures: DIMR, Beam Permits.. • BIW, AUG, Training. • Safety zones for crane operations. • Fencing around pits. • Smoke detection • Radiation and ventilation pressure monitoring. CENF: APR progress

  4. Target and Secondary AdR results: • which will be resumed in an EDMS document(when I get access to CENF node) • discussions clarified many areas, potential issues were defused before they became costly problems- a positive benefit from the exercise (as has been seen in other cases). • following the study some ideas have been modified, these will be integrated in the summary document too. Any changes will have verification through the EDMS approval process (no new meetings). • The AdR will be reviewed at the transition to the construction phase. • Other issues to have further clarification include : • water tightness of the DP works, • drainage and radiation issues (target area and DP activated water), • construction and commissioning  issues with the DP, • Dismantling plans, • Use of morgue space and blocks handling/ temporary storage.

  5. Preliminary Risk Analysis for CENF SB areas • Noteworthy points: • Ventilation monitoring of δP (for operation) and flushing for access, this is a new development for the CV group. • Weakest link: the search procedure (as for all radiation areas), as in other areas the procedure will have a written protocol. • Beam Permit : this is an important element in the overall preparation for beam. A risk analysis shows that it is sufficiently reliable for its purpose. • Ion exchangers are radiation hot spots: worse than beam effects. An unexpected result: activated materials are a higher residual risk than beam, due to good shielding design. CENF: APR progress

  6. Next Step: The EHN1 extension • An AdR is needed for the Experimental area, • Existing measures in EHN1 have no risk analysis published. • The new facility introduces different hazards. • Project details are still evolving but many aspects can be considered as fixed. • Specialist Input will be needed for Cryo hazards estimates and control methods. • Gran Sasso risk analysis needs revision as risks have changed (not separate halls, cryo “windows”, secondary beam, large population in vicinity..) • Dedicated issues for the project meetings? Should be driven by project team, not safety.