1 / 11

CENF – Civil Engineering Extension B887 Status – 18 September 2014

This document provides information about the civil engineering extension for Building 887, including updates on the tender process and the next steps for construction. It also includes technical aspects of the extension, such as location and main activities for each work package.

heard
Download Presentation

CENF – Civil Engineering Extension B887 Status – 18 September 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CENF – Civil Engineering Extension B887Status – 18 September 2014 Done: (1/2) • Preliminary civil engineering drawing and Functional specification approved by CERN on 18/03/2014 (EDMS 1365362 and 1350076) • Civil engineering Tender Design phase started on 2/04/2014 by ARCADIS • Submission of the « Permis de construire » on 19/05/2014 • Market survey issued to the firms on 11/06/2014 → Two work packages (WP1-Civil engineering & WP2-Steel structure and cladding) Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi 18 September 2014 1

  2. CENF – Civil Engineering Extension B887 Done: (2/2) • Tender documents ready and EDMS approval procedure launched on 10/07/2014 → 9 firms qualified for WP1, 7 firms for WP2 and 4 firms for WP 1+2 • Specification Committee meeting held on 29/07/2014 • Tender documents sent to the firms on 18/08/2014 • Construction Design phase started on 18/08/2014 by ARCADIS • Bidders Conference held on 4/09/2014 Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi 18 September 2014 2

  3. CENF – Civil Engineering Extension B887 Next steps: • Bids expected on 2/10/2014 • Preparatory works to start on October 2014 (abattage, déviation de réseaux, etc) • Construction Design expected on November 2014 • Adjudication foreseen on December 2014 FC • Contract signature • Start of the works expected on January 2015 (if possible, anticipate Excavation works as early as possible) Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi 18 September 2014 3

  4. CENF – Civil Engineering Extension B887 Technical Aspect: Location The Extension will extend northwards from the building for about 70 m in the direction of the beams. Site Installation Area Tunnel TDC85 Extension Experimental Hall B.887 (EHN1) Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi 18 September 2014 4

  5. CENF – Civil Engineering Extension B887 Technical Aspect: General info The Extension's dimensions are 72 m long by 50 m wide and 20 m high. Metallic Structure Existing EHN1 Pits The extension includes two large pits of 7.35m and 9.0m deep. The top metallic structure is similar to the existing building, allowing for an easy continuation of the overhead crane and services. Extension The technical gallery will be prolonged. Swallow service trenches will provide the access from the sidewalls to the pits. Technical Gallery Service Trenches The works are broken down into two work packages: Work package 1 - Civil engineering Work package 2 - Structural steelwork Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi 18 September 2014 5

  6. CENF – Civil Engineering Extension B887 Technical Aspect: WP1 main activities (1/2) B -Construction sheet piles (or Reduce Cost Alternative Option) -Construction diaphragm wall and final tie beams -Construction of reinforced concrete structure (raft foundations, slabs, walls, etc.) -Demolition of the existing gable retaining wall Plan view A A B Section B-B Section A-A Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi 18 September 2014 6

  7. CENF – Civil Engineering Extension B887 Technical Aspect: WP1 main activities (2/2) The works to be carried out will include: -General worksite installation -Rerouting and cutting existing underground networks -Mass and ditch earthworks -Drawdown of the water table -Road works, car parks and landscaping. -Rainwater treatment structures (worksite and definitive) Notes: Particular attention should be kept to the extracted cut material within 5.50m of distance from the TDC85 Radiological Protection: People allow to enter the technical gallery or inside the existing building 887 should equipped (passive/operational dosimeter) and accredited by CERN. No special measure need to be planned to work outside Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi 18 September 2014 7

  8. CENF – Civil Engineering Extension B887 Technical Aspect: WP2 main activities (1/2) -Structural steelwork and associated components (Main and Secondary structures, Internal structures, Travelling crane structures) -Metalwork: guardrails, stairs, ladders, doors -Removal of the north gable of the existing building (not before the extension is water-tight and air-tight) Please note that primary framework shall be erected after completion of the infrastructures and therefore above the pit and that this work package shall provide the necessary worksite protections Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi 18 September 2014 8

  9. CENF – Civil Engineering Extension B887 Technical Aspect: WP2 main activities (2/2) -façade -roofing -doors -glazed windows -ladders with safety cages -safety barriers -rainwater pipes -cryogenics roof -etc. Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi 18 September 2014 9

  10. CENF – Civil Engineering Extension B887 Schedule Anticipatedstart of the works (if possible) + 18 months Source : ARCADIS → to beupdatedaftertenderingprocedures Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi 18 September 2014 10

  11. CENF – Civil Engineering Extension B887 Thanks for your attention.. Questions? Extension of Building 887 - Neutrino Platform General Meetings N.Lopez – M.Manfredi 18 September 2014 11

More Related