Draper’s Corner

Drapers Corner Intersection Improvement Project City Council Update Thursday November 12, 2009. Draper’s Corner. Intersection Reconstruction. Project began on the 10 year Transportation Improvement Program (TIP) Funded with special appropriations in the Federal transportation funding bill.

thelma
Download Presentation

Draper’s Corner

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Drapers Corner Intersection Improvement Project City Council Update Thursday November 12, 2009 Draper’s Corner Intersection Reconstruction

  2. Project began on the 10 year Transportation Improvement Program (TIP) • Funded with special appropriations in the Federal transportation funding bill. • Project is a Municipally Managed project that is funded by the Federal Highway Administration through the New Hampshire Department of Transportation. • The engineer for the project is CLD consulting Engineers of Manchester New Hampshire selected through the QBS process. Executed design services contract on April 2008. • Project to include new signals on mast arms, additional turn lanes, culvert replacement, aerial utility relocations, and non-participating underground utility upgrade within the project limits Project Overview

  3. West Pleasant Street Maple Avenue Tyler Brook Maple Avenue Hillstead Road Charlestown Road

  4. Hillstead Road Maple Avenue East

  5. West Pleasant Street Maple Avenue West

  6. Charlestown Road

  7. Design Phase • QBS Selection Process • Engineering Studies • Preliminary Design • Final Design • Bid Documents Environmental Phase • Natural Resource Coordination • Cultural Resource Coordination Right of Way Phase • Determine Need • Public Hearing • Negotiations Construction Phase NHDOT/Municipally Managed Process – Project Development

  8. Existing Approach Configuration • Hillstead Road Single through and turn lane • Maple Avenue East Single through and turn lane • West Pleasant Street Single through and turn lane • Maple Avenue West Single through and turn lane • Charlestown Road Single through and turn lane Proposed Approach Configuration • Hillstead Road Single through and turn lane • Maple Avenue East Dedicated left, through and slip • West Pleasant Street Dedicated through/left, dedicated right • Maple Avenue West Dedicated left, through and slip • Charlestown Road Dedicated through/left, dedicated right

  9. Schedule and Funding • Engineering, 2007 through 2009 24 Months • Right of Way, 2009/2010 12-15 Months • Construction, 2010 thru 2011 15 Months Original Budget • Professional $ 200,000 100% 0% Engineering (PE) • ROW $ 50,000 100% 0% • Construction $ 494,000 100% 0% • Construction $1,006,000 80% 20% • TOTAL $1,750,000 $1,298,800 $201,200 $ 750,000 Grant $1,000,000 80/20 Split

  10. Questions?