PCRR release mechanism examples. December 3, 2007. Business process clarification NPRR – “release mechanism”. ERCOT proposes to remove the “release mechanism” language in the protocols as existing design provides a more elegant solution

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha

Download Presentation

PCRR release mechanism examples

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript



Business process clarification nprr release mechanism
Business process clarification NPRR – “release mechanism”

  • ERCOT proposes to remove the “release mechanism” language in the protocols as existing design provides a more elegant solution

  • The following slides aim to explain the “release mechanism” compared to proposed implementation

  • Assumptions made in this example (which may not exist in reality):

    • The network capacity for 2010-2011 is the same for all months

    • The nominated MW is the same for all months

    • The nominated MW amount is fully allocated; no monthly true-up allocation required

TPTF – CRR Issues


Available network capacity for 2010 and 2011
Available network capacity for 2010 and 2011 mechanism”

100 MW (capacity)

100 MW (capacity)

Year 2010

Year 2011

annual

allocation

before the

annual auc.

annual

auction

before the

monthly auc.

Jan monthly

auction

after the

monthly auc.

TPTF – CRR Issues


Nominations for 2010 and 2011 submitted by noies
Nominations for 2010 and 2011 submitted by NOIEs mechanism”

100 MW (capacity)

100 MW (capacity)

60 MW (nominated)

60 MW (nominated)

Year 2010

Year 2011

annual

allocation

before the

annual auc.

annual

auction

before the

monthly auc.

Jan monthly

auction

after the

monthly auc.

TPTF – CRR Issues


All nominations for 2010 and 2011 allocated but only some released
All nominations for 2010 and 2011 allocated – but only some released

100 MW (capacity)

100 MW (capacity)

60 MW (allocated)

60 MW (allocated)

60*55% = 33 MW (released)

60*15% = 9 MW (released)

Year 2010

Year 2011

annual

allocation

before the

annual auc.

annual

auction

before the

monthly auc.

Jan monthly

auction

after the

monthly auc.

TPTF – CRR Issues


Remainder network capacity up to 55 and 15 auctioned
Remainder network capacity (up to 55% and 15%) auctioned some released

100 MW (capacity)

100 MW (capacity)

60 MW (allocated)

60 MW (allocated)

100*55% - 33 MW = 22 MW (auctioned)

55%

60*55% = 33 MW (released)

100*15% - 9 MW = 6 MW (auctioned)

15%

60*15% = 9 MW (released)

Year 2010

Year 2011

annual

allocation

before the

annual auc.

annual

auction

before the

monthly auc.

Jan monthly

auction

after the

monthly auc.

TPTF – CRR Issues


Balance of pcrrs up to 90 or additional 35 released to noies
Balance of PCRRs (up to 90% or additional 35%) released to NOIEs

100 MW (capacity)

100 MW (capacity)

100*55% - 33 MW = 22 MW (auctioned)

60 MW (allocated)

60*90% - 33 = 21 MW (released)

60*55% = 33 MW (released)

100*15% - 9 MW = 6 MW (auctioned)

60*15% = 9 MW (released)

Year 2010

Year 2011

annual

allocation

before the

annual auc.

annual

auction

before the

monthly auc.

Jan monthly

auction

after the

monthly auc.

TPTF – CRR Issues


Remainder network capacity up to 90 auctioned
Remainder network capacity (up to 90%) auctioned NOIEs

100*90% - 33 - 21 - 22= 14 MW(auctioned)

100 MW (capacity)

100 MW (capacity)

100*55% - 33 MW = 22 MW (auctioned)

60 MW (allocated)

90%

60*90% - 33 = 21 MW (released)

60*55% = 33 MW (released)

100*15% - 9 MW = 6 MW (auctioned)

60*15% = 9 MW (released)

JAN

Year 2010

Year 2011

annual

allocation

before the

annual auc.

annual

auction

before the

monthly auc.

Jan monthly

auction

after the

monthly auc.

TPTF – CRR Issues


Balance of pcrrs additional 10 for jan 2010 released to noies
Balance of PCRRs (additional 10%) for Jan 2010 released to NOIEs

100*90% - 33 - 21 - 22= 14 MW(auctioned)

100 MW (capacity)

100 MW (capacity)

60*100% - 33 - 21= 6 MW(released)

100*55% - 33 MW = 22 MW (auctioned)

60 MW (allocated)

90%

60*90% - 33 = 21 MW (released)

60*55% = 33 MW (released)

100*15% - 9 MW = 6 MW (auctioned)

60*15% = 9 MW (released)

JAN

Year 2010

Year 2011

annual

allocation

before the

annual auc.

annual

auction

before the

monthly auc.

Jan monthly

auction

after the

monthly auc.

TPTF – CRR Issues


Summary of crrs distributed
Summary of CRRs Distributed NOIEs

Current PCRR release mechanism does not provide 10% cushion

Proposed implementation simplifies the process

TPTF – CRR Issues


Available network capacity for 2010 and 20111
Available network capacity for 2010 and 2011 NOIEs

100 MW (capacity)

100 MW (capacity)

Year 2010

Year 2011

annual

allocation

annual

auction

Jan monthly

auction

TPTF – CRR Issues


All nominations for 2010 and 2011 allocated
All nominations for 2010 and 2011 allocated NOIEs

100 MW (capacity)

100 MW (capacity)

60 MW (nominated & allocated)

60 MW (nominated & allocated)

Year 2010

Year 2011

annual

allocation

annual

auction

Jan monthly

auction

TPTF – CRR Issues


Network capacity up to 55 and 15 auctioned
Network capacity (up to 55% and 15%) auctioned NOIEs

100 MW (capacity)

100 MW (capacity)

60 MW (allocated)

60 MW (allocated)

100*55% - 33 MW = 22 MW (auctioned)

55%

60*55% = 33 MW (base loaded in Auction)

100*15% - 9 MW = 6 MW (auctioned)

15%

60*15% = 9 MW (base loaded in Auction)

Year 2010

Year 2011

annual

allocation

annual

auction

Jan monthly

auction

TPTF – CRR Issues


Network capacity up to 90 auctioned
Network capacity (up to 90%) auctioned NOIEs

100*90% - 60 - 22 = 8 MW(available for auction)

100 MW (capacity)

100 MW (capacity)

22*100% = 22 MW (based loaded in auction)

60 MW (allocated)

90%

60*100% = 60 MW (base loaded in auction)

100*15% - 9 MW = 6 MW (auctioned)

60*15% = 9 MW (base loaded in Auction)

JAN

Year 2010

Year 2011

annual

allocation

annual

auction

Jan monthly

auction

TPTF – CRR Issues


Summary of crrs distributed1
Summary of CRRs Distributed NOIEs

TPTF – CRR Issues