Yuba river basin project schedule and cost change request saccr cvfpb agenda item 10
This presentation is the property of its rightful owner.
Sponsored Links
1 / 12

YUBA RIVER BASIN PROJECT Schedule and Cost Change Request (SACCR) CVFPB Agenda Item 10 PowerPoint PPT Presentation


  • 132 Views
  • Uploaded on
  • Presentation posted in: General

YUBA RIVER BASIN PROJECT Schedule and Cost Change Request (SACCR) CVFPB Agenda Item 10. April 17, 2009. Overview. Yuba County Water Agency: Local sponsor Goal: Provide at least 300-year protection to the City of Marysville and 200-year protection to RD 784. Maximize federal funds by:

Download Presentation

YUBA RIVER BASIN PROJECT Schedule and Cost Change Request (SACCR) CVFPB Agenda Item 10

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Yuba river basin project schedule and cost change request saccr cvfpb agenda item 10

YUBA RIVER BASIN PROJECTSchedule and Cost Change Request(SACCR)CVFPB Agenda Item 10

April 17, 2009


Overview

Overview

  • Yuba County Water Agency: Local sponsor

  • Goal: Provide at least 300-year protection to the City of Marysville and 200-year protection to

    RD 784.

  • Maximize federal funds by:

    • Completing GRR

    • Secure credit from state & local expenditures as

      part of the TRLIA levee improvements

    • Defer non-Federal costs on Marysville

      until Congress Authorizes the GRR

1


Project elements

Project Elements

  • General Reevaluation Report (GRR) - RD 784

  • Marysville Ring levee

2


Grr scope

GRR Scope

  • Evaluate the Federal interest in reducing the risk of flooding in RD 784

  • Alternatives to include the TRLIA Program, and additional alternatives that provide greater and lesser levels of protection for the area

  • GRR will establish the eligible credit from the TRLIA work that can be used towards Marysville or additional improvements in RD 784

3


Why the grr scope increased

Why the GRR Scope Increased

  • We Learned a lot from the 1997 Flood Event

  • 1998 FS did not identify a need for work on the Lower Feather, Bear & WPIC Levees for 200-year protection

  • After the 1997 Flood Event

    • New underseepage guidelines required more work to achieve a given level of protection

    • Revisions to hydrology

  • The DWR Floodplain Mapping Study (Early 2000s)

    • Identified FEMA deficiencies in RD 784

    • Lower RD 784 freeboard deficiency

    • Yuba River left bank stability problem

4


Yuba river basin project schedule and cost change request saccr cvfpb agenda item 10

Brief History of the GRR

  • Reclamation Board Increased the GRR Scope and Cost in 2004 – LRR Increased to a GRR

  • Corps has Requested Scope and Schedule Revision (2) to cover:

    • Sunk Costs > $8M

    • Additional Design Fees, Field Work, and Modeling

    • Additional Evaluation of Ecosystem Restoration, Environmental Data and In-House Labor

      Details Included in Board Package

5


Yuba river basin project schedule and cost change request saccr cvfpb agenda item 10

GRR Schedule

  • Alternative Formulation Briefing –

    July, 2009

  • F6 Public Review (Draft EIS) –

    October, 2009

  • Chief of Engineers Report –

    June, 2010

6


Marysville ring levee

Marysville Ring Levee

  • Strengthen 7.5 miles of levees

  • $50M estimate

    • 65% Federal: $32M

    • 35% Non-Federal: $18M

    • State: $12.6M

    • Local Share: $5.4M

  • 2008 Corps approval of Ring Levee as a “Separable Element”

    (OK to Begin construction while GRR is underway)

  • 7


    Marysville strategy

    Marysville Strategy

    • Begin construction – no delay or risk from the GRR (separable element)

    • Secure adequate appropriations

    • Minimize State/local cost-share:

      1. Section 103(l) cost-share deferral, Corps Approval on April 3, 2009

      (There is still a Non-Federal 5% cash requirement)

      2. Secure credits from TRLIA

      and RD 784 for the local cost-share

    8


    Yuba river basin project schedule and cost change request saccr cvfpb agenda item 10

    Marysville Schedule

    • Engineering Documentation Report (EDR) - Aug 2009

    • Project Partnership Agreement –

      (PPA) - Nov 2009

    • Award First Construction Contract –

      Apr 2010

    9


    Requested action

    Requested Action

    1.0 Approve Corps SACCR dated March 19, 2009 to increase costs by $10,500,000.

    2.0 Amend the LDA with YCWA to increase the total agreement costs.

    3.0 Amend the DA with the Corps to increase the total agreement costs.

    Approval Will:

    • Allow planning/design efforts to continue on both the GRR and Marysville Levee

    • Avoid additional schedule delays to the GRR and Marysville construction

    10


    Yuba river basin project schedule and cost change request saccr cvfpb agenda item 10

    Thank You