YUBA RIVER BASIN PROJECT Schedule and Cost Change Request (SACCR) CVFPB Agenda Item 10 PowerPoint PPT Presentation


  • 137 Views
  • Uploaded on
  • Presentation posted in: General

YUBA RIVER BASIN PROJECT Schedule and Cost Change Request (SACCR) CVFPB Agenda Item 10. April 17, 2009. Overview. Yuba County Water Agency: Local sponsor Goal: Provide at least 300-year protection to the City of Marysville and 200-year protection to RD 784. Maximize federal funds by:

Download Presentation

YUBA RIVER BASIN PROJECT Schedule and Cost Change Request (SACCR) CVFPB Agenda Item 10

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


YUBA RIVER BASIN PROJECTSchedule and Cost Change Request(SACCR)CVFPB Agenda Item 10

April 17, 2009


Overview

  • Yuba County Water Agency: Local sponsor

  • Goal: Provide at least 300-year protection to the City of Marysville and 200-year protection to

    RD 784.

  • Maximize federal funds by:

    • Completing GRR

    • Secure credit from state & local expenditures as

      part of the TRLIA levee improvements

    • Defer non-Federal costs on Marysville

      until Congress Authorizes the GRR

1


Project Elements

  • General Reevaluation Report (GRR) - RD 784

  • Marysville Ring levee

2


GRR Scope

  • Evaluate the Federal interest in reducing the risk of flooding in RD 784

  • Alternatives to include the TRLIA Program, and additional alternatives that provide greater and lesser levels of protection for the area

  • GRR will establish the eligible credit from the TRLIA work that can be used towards Marysville or additional improvements in RD 784

3


Why the GRR Scope Increased

  • We Learned a lot from the 1997 Flood Event

  • 1998 FS did not identify a need for work on the Lower Feather, Bear & WPIC Levees for 200-year protection

  • After the 1997 Flood Event

    • New underseepage guidelines required more work to achieve a given level of protection

    • Revisions to hydrology

  • The DWR Floodplain Mapping Study (Early 2000s)

    • Identified FEMA deficiencies in RD 784

    • Lower RD 784 freeboard deficiency

    • Yuba River left bank stability problem

4


Brief History of the GRR

  • Reclamation Board Increased the GRR Scope and Cost in 2004 – LRR Increased to a GRR

  • Corps has Requested Scope and Schedule Revision (2) to cover:

    • Sunk Costs > $8M

    • Additional Design Fees, Field Work, and Modeling

    • Additional Evaluation of Ecosystem Restoration, Environmental Data and In-House Labor

      Details Included in Board Package

5


GRR Schedule

  • Alternative Formulation Briefing –

    July, 2009

  • F6 Public Review (Draft EIS) –

    October, 2009

  • Chief of Engineers Report –

    June, 2010

6


Marysville Ring Levee

  • Strengthen 7.5 miles of levees

  • $50M estimate

    • 65% Federal: $32M

    • 35% Non-Federal: $18M

    • State: $12.6M

    • Local Share: $5.4M

  • 2008 Corps approval of Ring Levee as a “Separable Element”

    (OK to Begin construction while GRR is underway)

  • 7


    Marysville Strategy

    • Begin construction – no delay or risk from the GRR (separable element)

    • Secure adequate appropriations

    • Minimize State/local cost-share:

      1. Section 103(l) cost-share deferral, Corps Approval on April 3, 2009

      (There is still a Non-Federal 5% cash requirement)

      2. Secure credits from TRLIA

      and RD 784 for the local cost-share

    8


    Marysville Schedule

    • Engineering Documentation Report (EDR) - Aug 2009

    • Project Partnership Agreement –

      (PPA) - Nov 2009

    • Award First Construction Contract –

      Apr 2010

    9


    Requested Action

    1.0 Approve Corps SACCR dated March 19, 2009 to increase costs by $10,500,000.

    2.0 Amend the LDA with YCWA to increase the total agreement costs.

    3.0 Amend the DA with the Corps to increase the total agreement costs.

    Approval Will:

    • Allow planning/design efforts to continue on both the GRR and Marysville Levee

    • Avoid additional schedule delays to the GRR and Marysville construction

    10


    Thank You