1 / 21

IBL cooling tube routing proposal

bverlaat@nikhef.nl. IBL cooling tube routing proposal. Bart Verlaat 19-01-2011. IBL Cooling pipes layout idea :. Concentric tube. Single outlet tube. Single inlet tube. Inlet Manifold. Outlet Manifold. Inlet Capillaries. IBL CO 2 cooling routing proposal.

tale
Download Presentation

IBL cooling tube routing proposal

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. bverlaat@nikhef.nl IBL cooling tube routing proposal Bart Verlaat 19-01-2011

  2. IBL Coolingpipeslayoutidea: Concentric tube Single outlet tube Single inlet tube Inlet Manifold Outlet Manifold Inlet Capillaries

  3. IBL CO2 cooling routing proposal • A survey of the routing possibilities in Atlas has been carried out to come up with a more detailed proposal than the one on the previous slide. • Routing in difficult areas was simulated with 50mm PVC piping. A Mock-up is made which can be measured and modeled into CAD. • The dimensions of the neighboring hardware were measured to find space for additional hardware and accessibility. Measurements will be used to check the available 3D models. • Preliminary check of measurements is done with existing 2d drawings from CDD. • A principle design of the full tube routing is made • Where to put manifolds, valves, etc. • What isolation can be applied (Foam / Vacuum).

  4. IBL cooling tube routing CAD measurements Cooling pipes Cooling pipes LAR cryogenic plant Existing support structures Vertical cables LAR cryo pipes Cooling pipes Sector 5 BIL muon Cooling pipes Bart’s CAD office

  5. Measured cooling tube routing and support environment in the Atlas overall drawing

  6. Cooling tube routing mock-up in detector

  7. IBL cooling tube routing at inner detector. • From the ID-end plate a nice path following the dry-air chimney was found to the top of the tile calorimeter. • In the empty space between inner muon chamber of sector 5 and the tile calorimeter a path was found to accessible area between sector 5, BIL and BML layers. In this space the transition from IBL feed and return tubing to the concentric transfer tube can be made. • Delicate equipment can be placed in this area as it is easily accessible. • Valves, filters, sensors. • Manifolds? • Tubes to ID-end plate can be vacuum insulated and can be installed prefabricated. • Insulation of transition hardware can only be foam insulated. Placement of a condensation catch channel underneath is possible.

  8. IBL cooling branch IDEP Inlet Manifold IDEP Outlet Manifold PP0 Weld Connector PP0 Weld Connector Q≈100 Watt / stave PP1 Connector PP1 Connector Inlet Capillary (Flexible) 0.8mmID x 5289mm (2609.5+2679.5) IBL Boiling tube: 2.0mmID x 1308mm (Heated length 708mm) Outlet tube 2.0mmID x 2679.5m Outlet tube 3.0mmID x 2609.5m or 2.0mmID x 2609.5m (TBD) 14 staves = 14 parallel branches.

  9. Longitudinal routing near lower BIL muonchamber corner. Passage through almost empty channel Routing and clamping on top of “chimney” Entering ID-endplate left of “chimney” 50mm pvc dummy tube with 45’ connectors IBL CO2 cooling tube routing at calorimeter end flange

  10. IBL Cooling junction at sector 5 Top view C-side view Connection to A-side Cooling components area Concentric transfer tube LAR pipes LAR pipes BIL muon chambers Concentric transfer tube Cable channels platform Connection to A-side Connection to C-side Connection to C-side ID end plate Vacuum insulated cooling tubes Foam insulated cooling tubes

  11. End cap region pictures Passage between S5 BIL muon and Tile calorimeter Passage of Tile calorimeter cable channel PVC mockup @ Aside (Fits also @ Cside) Entry of Tile calorimeter cable channel IDEP interface Routing on top of chimney Clearance above endcap tile calorimeter for installation passage

  12. Sector 5 junction pipe pictures Free installation space for junction box Junction routing at S5 A-side C-side Passage between S5 BIL muon and Tile calorimeter C-side Passage between S5 BIL muon and Tile calorimeter Passage of BIL muon layer Passage of BIL muon layer Junction routing around muon alignment beams Junction tubes on top of cable channel /below LAR pipe

  13. IBL transfer tube inside Atlas detector • A straight path from the sector 5 cooling junction to the outside was found following the cryogenic LAR piping towards the cryogenic LAR plant at level 6. • The straight path allow us to make the concentric transfer tube in the detector to be vacuum insulated. • Concentric vacuum assembly can be made using 6m tubes. At the LAR cryogenic plant sufficient space is available for inserting 6m long tubes. • Construction of 6m long tubes (standard trading length) gives weld joint locations in accessible areas. • BIL/BML sector 5 (Junction box) • BML/BOL sector 7 (Area behind small toroid access door) • LAR cryogenic plant at level 6. • Routing and inserting was simulated using 50mm PVC piping.

  14. Concentric transfer line in Atlas detector 12.9 m BML/BOL sector 7 (Area behind small toroid access door) BIL/BML sector 5 (Junction box) LAR cryogenic plant at level 6 6 m 6 m Concentric transfer line Existing mechanical supports

  15. Vacuum insulated transfer tube pictures (S5 and S7) Transfer line at S5 Transfer line underneath platform in S5 S7 accessible area for welding Only obstacle in the way: ladder in S7: 1cm shift required. Transfer line following LAR cryo-pipes from S5 to S7 Transfer line next to LAR cryo-pipes in S7 Transfer line terminal at S5

  16. Vacuum insulated transfer tube pictures LAR cryogenic plant Inserted transfer line at LAR Cryogenic plant Transfer line exits BOL layer at S7/8 Transfer line exits BOL layer at S7/8 Transfer line arrives at LAR Cryogenic plant Insertion of a 6m tube at LAR cryogenic plant (1) Insertion of a 6m tube at LAR cryogenic plant (2) Insertion of a 6m tube at LAR cryogenic plant (3)

  17. Transfer tube routing to cooling plant • A nearly horizontal path was found to the cooling plant area in USA15 • Tubes follow LAR vacuum tube towards cavern wall and go along wall to the tube and cable tunnel. • Tubes can be installed on top of C3F8 cooling channels to USA15 • Vacuum pump can be installed on cavern wall next to LAR vacuum pump • Insulation will be foam from LAR cryogenic plant towards CO2 cooling plant

  18. Follow C3F8 pipes in USA15 Cavern tube routing Start at LAR cryo plant Follow C3F8 pipes in tunnel Terminate at proposed IBL cooling plant platform Follow LAR vacuum pipes Follow pipes at cavern wall

  19. IBL cooling plant location • A nice free space was found on an empty platform at the upper layer of USA15. • Tube routing towards this space is easy. • Is this space available for the CO2 plant?

  20. Tube length summary

  21. Summary and conclusions • Proposed tube routing from IBL to cooling plant is feasible and looks relatively easy to apply. • Vacuum insulation in the detector • Except at junction area, but very accessible for a proper insulation. Condensation catch channels will be installed as guarantee. • Pre-fabricated vacuum channel from junction to ID-end plate. • Vacuum insulated transfer line possible to manufacture in place. • Junction area is easy to access, this will be the location for most of the sensitive hardware. • It will be investigated to locate the manifolds as well in the junction area. • Long capillary tubing!! • Accessible manifolds. • Possibility to disconnect an IBL cooling channel. • Can CO2 plant be placed at the free platform in USA15?

More Related