1 / 10

Progress Report Interim Joint Committee on Transportation Royce Meredith, KYTC Program Manager

BRIDGING KENTUCKY Restore | Renew | Replace. Progress Report Interim Joint Committee on Transportation Royce Meredith, KYTC Program Manager. Date: August 6, 2018 :. Program Overview. Date:. $700M. Major Impact. Estimated $700 million over six years

stevensimon
Download Presentation

Progress Report Interim Joint Committee on Transportation Royce Meredith, KYTC Program Manager

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BRIDGING KENTUCKY Restore | Renew | Replace Progress ReportInterim Joint Committee on Transportation Royce Meredith, KYTC Program Manager Date: August 6, 2018 :

  2. Program Overview Date: $700M Major Impact Estimated $700 million over six years Rehabilitate, repair, or replace more than 1,000 critical structures Deliver all bridges for construction by 2024 1,000 bridges 6 years BRIDGING KENTUCKY Restore | Renew | Replace

  3. Program Overview Date: BRIDGING KENTUCKY Restore | Renew | Replace

  4. Program Overview Date: Statewide Initiative Bridges in all 120 counties Distributed across the Commonwealth Focus on bridges in biennium BRIDGING KENTUCKY Restore | Renew | Replace This Photo by Unknown Author is licensed under CC BY-SA

  5. Progress to Date Date: Building the Program Assembled strong team Quick-start, 120-day plan Setting up program and systems Starting evaluations simultaneously BRIDGING KENTUCKY Restore | Renew | Replace

  6. Progress to Date Date: Preparing for Construction “We’re not going to rehab a bridge that should be replaced, and we’re not going to replace a bridge that should be rehabbed.” Screening / evaluating bridges Using data-driven, life-cycle cost approach Determining rehabs vs. replacements Industry forums BRIDGING KENTUCKY Restore | Renew | Replace

  7. Program Overview Date: Prioritization Focus on three factors • Budget • Condition of structure • Project challenges Address closed bridges Biennium bridges first BRIDGING KENTUCKY Restore | Renew | Replace

  8. Next steps Date: Biennium Bridges $340 million approved in FY 2018-19 Nearly 350 bridges Deliver to construction in 2019-20 biennium BRIDGING KENTUCKY Restore | Renew | Replace

  9. Next steps Date: Work Starting Fast Finalize program setup Bridge Screening Wrapping Up Move projects to construction BRIDGING KENTUCKY Restore | Renew | Replace

  10. Next steps Date: Construction Phase Several bridges under construction Starting rehab projects this year Large volume of rehabs/replacements in 2019 BRIDGING KENTUCKY Restore | Renew | Replace

More Related