1 / 16

ceo UPDATES, as of 1-31-2012

EXECUTIVE COMMITTEE MEETING FEBRUARY 24, 2012. ceo UPDATES, as of 1-31-2012. Assets. PhP781.3M AS OF 1-31-12, WITH A PHP0.613M INCREASE FROM YEAR-END 2011 PHP52M SHORT OF TARGET OF PhP833M. Loans portfolio. PHP534M A/O 1-31-12, DOWN BY PHP4M FROM PREVIOUS MONTH (12-31-11)

sanam
Download Presentation

ceo UPDATES, as of 1-31-2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EXECUTIVE COMMITTEE MEETING FEBRUARY 24, 2012 ceoUPDATES, as of 1-31-2012

  2. Assets • PhP781.3M AS OF 1-31-12, WITH A PHP0.613M INCREASE FROM YEAR-END 2011 • PHP52M SHORT OF TARGET OF PhP833M

  3. Loans portfolio • PHP534M A/O 1-31-12, DOWN BY PHP4M FROM PREVIOUS MONTH (12-31-11) • PHP37M SHORT OF TARGET • PORTFOLIO AT RISK – 12%

  4. Liabilities / funding • INCREASE OF PHP1M FROM DECEMBER 2011 LEVEL • TOTAL APPROVED LINES : PHP680M • OUTSTANDING BALANCE: PHP679M • AVAILABLE BALANCE: PHP1M

  5. Other funding updates • INCOFIN US$1M – TO BE LEVERAGED WITH LBP • LBP – LEVERAGING AT 1:1.25 • LBP – TO RELEASE PHP80M (ON TOP OF EXISTING PHP100M, WHEN INCOFIN DOLLARS COME IN) • SYMBIOTICS INCREASE IN OUR LINE BY US$2M • CO-FINANCING AGREEMENT WITH BPI-GLOBE-BANKO, PHP200M, BY MID-MARCH

  6. Equity • AT PHP101.8M A/O 1-31-12 • INCREASE OF PHP1M FROM YEAR-END 2011 • COMMON SHARES • CARE – 23.6M - 47% • SEAD - 8.9M - 18% • PFIs - 17.2M - 34% • PREFERRED “A” • CARE - 10.06M • PREFERRED “B” • CARE - 9.83 M • PFIs - 15.92M

  7. Income • NET INCOME BEFORE TAX & DIVIDENDS OF PHP181KA/O 1-31-12 • PHP930K SHORT OF PROJECTED PHP1.1M

  8. Ratios • ROE – 0.18% • ROA – .02% • PAR - 4% (FOR FUNDERS) • D:E RATIO – 6.68%, ADJUSTED • D:E RATIO – 8.94%, UNADJUSTED • CAR – 18.86%

  9. SMART IAP & SMARTowns • 72 MIMOS OPERATING A/O 1-31-12 • Recent launches – LAPUYAN MPC, PAGLAUM MPC, TUPECO • 7,990 TRANSACTIONS IN ALL MIMOS, FOR THE SECOND HALF OF 2011 • PHP16.9M TOTAL MONEY-IN TRANSACTIONS, PHP16.7M MONEY-OUT, FOR THE SECOND HALF OF 2011 • KEY ACCOUNT PARTNERSHIP ESTABLISHED WITH DL3 ; PFI ACCREDITATION FOR E-LOADING ONGOING • 0.5% EARNINGS FOR SEEDFINANCE FROM LOADING • SMART MONEY FOR LOAN RELEASES ONGOING AT FCCT

  10. Mobile-BEAT • MCPI ASSESSMENT OF FPIF, POSSIBLE PHASE 2 OF FPIF MIDDLE OF THE YEAR • USAID SIMM PROJECT, SET TO START BY APRIL OR MAY 2012, PER JOHN OWENS • SMART MONEY ACCREDITATION PROGRAM BY MABS FOR RBs, STARTING • MARCH 9 – LUZON • MARCH 14 – VISAYAS • SEEDFINANCE AS ACCREDITED MABS SERVICE PROVIDER FOR THESE TRAINING SESSIONS

  11. ENCASH ATM Banking • 16 PFIs PARTICIPATING • 34 ATMs ONSITE • COORDINATION BETWEEN ENCASH AND SEEDFINANCE SYSTEMS ON CASH LEVELS TO ENSURE NO OFFLINE

  12. SF-MAX • ONGOING • MANUALIZATION OF POLICIES & PROCEDURES WITH PFIs • PMEF VALIDATION/ASSESSMENT • CONDUCT OF FGDs FOR PINOY ME PROJECTS IN MINDORO, PANAY, MINDANAO • SMART MONEY ACCREDITATION PROGRAM WITH MABS, FOR RURAL BANKS • UPCOMING • USAID – SIMM PROJECT • PMEF-DAR ON ARISP

  13. Social Performance Management • STRATEGIC REALIGNMENT WORKSHOP FOR SEEDFINANCE – FEBRUARY 27-29, 2012 • STRATEGIC REALIGNMENT WORKSHOP FOR 3 PILOT PFIs DONE • PPI & CPP ORIENTATION FOR BOTH SEEDFINANCE & PFIs – POSSIBLY STARTING BY APRIL, 2012 • OUTREACH MAPPING LAUNCH, BY MID-MARCH 2012

  14. Funding & networking • LENDWITHCARE • MICRA PHIL FOUNDATION PARTNERSHIP • BRIDGE INVESTMENTS – POSSIBLE INVESTMENT FOR RURAL BANK PARTNERS

  15. Human Resources • MONTHLY INCENTIVE PROGRAM – RECOMMENDATION TO HR COMMITTEE FOR EXTENSION • 4% ACROSS THE BOARD SALARY INCREASE TO ACCOUNT FOR INFLATION EFFECTED • TRAINING NEEDS ANALYSIS ONGOING – TARGET COMPLETION DATE – 3-31-2012 • COMPENSATION & BENEFITS SURVEY ONGOING – TARGET COMPLETION DATE – 3-15-12

  16. THANK YOU