Nushagak Cooperatives Inc. July 30, 2007 Quarterly Report Denali Commission

This quarterly report includes updates on various projects such as the JW cooling system upgrade, insulation work, and installation of generators and transformers. It also provides a timeline for completing remaining tasks in 2007.

rrayford
Download Presentation

Nushagak Cooperatives Inc. July 30, 2007 Quarterly Report Denali Commission

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Nushagak Cooperatives Inc. July 30, 2007 Quarterly ReportDenali Commission Including JW cooling system upgrade Insulation of Supplemental heat piping

  2. Quarterly work report • Continuing installation J/W system • Preliminary work performed to facilitate installation of Generators 14 and 15. • ASRC Energy personnel to arrive on July 25, 2007 to assess Tank Liner work. • Preliminary work performed to facilitate installation of new station service transformers.

  3. JACKET WATER PIPE INSULATION

  4. New after cooler piping wall penetration

  5. Insulation of supplemental heat piping

  6. Heat exchanger insulation(SHE)

  7. J/W cooling system insulation

  8. After cooler wall penetratin

  9. New after cooler piping

  10. Removal of old J/W and after cooler piping

  11. New after cooling pipe

  12. Superior side J/W rerouting and service connection

  13. Work to be Completed-Remainder of 2007 • Complete J/W cooling system Superior side • Replace Tank Farm liner by 12/30/2007 • Install 2 Ea. Pad mount station service transformers (arriving on Sept Barge). • Install 2 Ea. Caterpillar 3512C Generator sets, Units 14 and 15(arriving Sept Barge).