M&V Part 4: M&V Plan Review

M&V Part 4: M&V Plan Review. M&V Plan Review. FEMP Documents M&V Overview Checklist (Phase 2) Final M&V Plan Checklist (Phase 3) Risk & Responsibility Allocation Option A and Stipulation Detailed Guidelines Options B / C / D. Phase 1. Phase 2. Phase 3. Phase 4.

rico
Download Presentation

M&V Part 4: M&V Plan Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. M&V Part 4: M&V Plan Review

  2. M&V Plan Review • FEMP Documents • M&V Overview Checklist (Phase 2) • Final M&V Plan Checklist (Phase 3) • Risk & Responsibility Allocation • Option A and Stipulation • Detailed Guidelines • Options B / C / D

  3. Phase 1 Phase 2 Phase 3 Phase 4 Phase 2: Project Development • Contractor Responsibilities • Develop M&V approach (M&V Overview). • Explain and justify approach. • Agency Responsibilities • Review M&V approach and provide feedback.

  4. Phase 1 Phase 2 Phase 3 Phase 4 M&V Overview Checklist • The following items should be described: • Project site and measures. • What savings will be claimed. • M&V approach for each measure. • Baseline equipment and conditions. • Proposed equipment and conditions. • Annual measurement and verification activities.

  5. Phase 1 Phase 2 Phase 3 Phase 4 Phase 3: Negotiation and Award • Contractor Responsibilities • Perform Detailed Energy Survey (DES) and document baseline information. • Modify M&V plan to satisfy agency needs and desires. • Agency Responsibilities • Review and Approve M&V Plan. • Witness and observe DES.

  6. Phase 1 Phase 2 Phase 3 Phase 4 Final M&V Plan Checklist • The following items should be described: • Project site and measures. • What savings will be claimed. • M&V approach for each measure. • Details of how calculations will be made, including equations. • Baseline equipment and conditions (from DES).

  7. Phase 1 Phase 2 Phase 3 Phase 4 Final M&V Plan Checklist • continued... • Post-Installation equipment and conditions. • What metering equipment will be used. • What annual verification and measurement activities will be performed. • Initial and annual M&V costs.

  8. Risk & Responsibility Allocation • How to allocate Risks & Responsibilities? Typically: • Performance: Contractor. • Usage: Agency. • Financial: Shared. • M&V approach should focus on: • Verifying performance. • Characterizing usage. • Minimizing uncertainty cost-effectively.

  9. Need to balance M&V rigor with project risk. Measure things that need measuring. Consider required precision. Law of Diminishing Returns applies. Typically, initial M&V costs will be 3% to 15% of the capital cost; annual M&V costs will be 3 – 15% of the savings. Cost Effectiveness

  10. M&V Costs M&V Cost $ Value of information M&V Rigor

  11. Western Region SuperESPC

  12. Selection Matrix Warning: This is a gross generalization!

  13. Option A Option B Option C Option D Simple: Option A • Option A is intended to be simple and low-cost. • Verifies savings of individual components. • Equipment performance is measured. • Usage may be measured or stipulated. • In some cases, FEMP allows performance stipulation.

  14. Option A Option B Option C Option D Option A and Stipulation • Not ‘stipulated savings’! • Stipulations shift risk to agency. • OK for usage. • Not OK for performance (some exceptions).

  15. Option A Option B Option C Option D Option A Guidelines • Option A most common in SuperESPC. • Potential for misapplication. • Discusses how to use Option A. • Discusses how to apply stipulations. • See Detailed Guidelines For FEMP M&V Option A (2002)

  16. Option A Option B Option C Option D Example: LE-A-01 • FEMP method for Lighting Efficiency, Option A, method #1 • Allows using ‘standard fixture tables’ to determine lighting power instead of measurements (stipulated performance). • Usage (operating hours) stipulated. • Good for small projects (<$10,000/year)

  17. Option A Option B Option C Option D Stipulation Risk • LE-A-01 allows stipulation of both usage and performance parameters. • If the stipulated values are wrong, the savings estimates will be wrong. • The agency assumes all risk, contrary to the intent of a performance contract.

  18. Option A Option B Option C Option D Stipulation Problem

  19. Option A Option B Option C Option D Stipulation Lessons • Guaranteed savings $50,000; $24,000 observed in utility bill. • Poorly-defined baseline prevents adequate after-the-fact analysis. • Option C methods are not sufficiently accurate to support or reject savings claims.

  20. Option A Option B Option C Option D Example: LE-A-02 • FEMP method for Lighting Efficiency, Option A, method #2 • Common fixture types measured using a statistically-valid number of measurements (3-6). • Operating hours usually stipulated, but can be measured. • Good for large projects (>$100,000/yr)

  21. Option A Option B Option C Option D Option A Risk Allocation • The contractor should measure performance since they control this. • The operating hours may be stipulated. Measuring the operating hours reduces uncertainty and risks to both parties. • The agency bears the risk of unrealized savings due to changing schedule or incorrect operating hours.

  22. Option A Option B Option C Option D More Rigorous: Option B • Verifies at component level. • Requires periodic performance measurements- annual to hourly. • Usage can be stipulated or measured.

  23. Option A Option B Option C Option D Option B Risk Allocation • Energy use and claimed savings will vary from year to year. • The contractor assumes all project risk (performance & usage) since savings are based on measured energy use. • The contractor would be wise to include in the M&V plan: • limits on their exposure • methods of adjusting the baseline or usage

  24. Option A Option B Option C Option D Simple: Option C • Regression method using existing utility meters. • Captures interactions between measures to find total savings. • Requires collecting and tracking information that affects energy use: • weather • occupancy • production

  25. Option A Option B Option C Option D Option C Risk Allocation • The contractor may not find the savings if less than 15% of the baseline use. • The contractor bears all project risk. • The agency bears the responsibility of tracking changes that affect energy use. • It may take 1 year to determine savings. • Weather and other factors will influence savings estimates.

  26. Option A Option B Option C Option D More Rigorous: Option D • Computer simulation method of evaluating total building performance. • Requires calibration to be useful. • Requires measurements to calibrate model. • Weather data usually ‘typical’, not real.

  27. Option A Option B Option C Option D Option D Risk Allocation • Contractor bears performance risk. • Agency bears usage risk (stipulated hours and weather). • M&V costs may be high. • Short-term measurements and long-term verification still needs to be performed.

  28. Option A Option B Option C Option D Results Warning: These are gross generalizations! It is possible to shift risks and changes costs.

  29. Review & Discussion • Performance must be verified if guarantee is to have value. • Agency often assumes usage risk. • Uncertainty is inherent in M&V. • M&V costs need to be balanced against project risks.

  30. Review Questions • How do we measure savings? • When might an agency accept performance risk?