Data Collection Module (DCM) (review, fabrication plan & chain test)

This document provides an overview of the Data Collection Module (DCM) review, fabrication plan, and chain test. It includes information about the DCM functions, block diagram, crate, data flow, final design review, and status. The document also covers the timing-FEM-DCM chain test and the DCM fabrication plan.

rhayden
Download Presentation

Data Collection Module (DCM) (review, fabrication plan & chain test)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Data Collection Module (DCM)(review, fabrication plan & chain test) • DCM team • Cheng-Yi Chi ( DCM, TOF FEE, BB FEE) • Jamie Nagle (DCM) • Bill Sippach (DCM, TOF FEE, BB FEE) • Herb Cunitz (DCM, TOF FEE, BB FEE) • Li Zhang (DCM, TOF FEE, BB FEE) June 10, 98 FEE Review Cheng-Yi Chi

  2. DCM Functions • Zero-suppress FEM data • Receive Level-1 trigger primitives • Apply calibration constants • Error and alignment checking / handling • Re-format data to the Event Builder • Data Monitoring / Histogramming / Calibration • First Stage of the event building • Generating higher level trigger primitives • Provide FEM data buffer June 10, 98 FEE Review Cheng-Yi Chi

  3. DCM Block Diagram June 10, 98 FEE Review Cheng-Yi Chi

  4. DCM Crate June 10, 98 FEE Review Cheng-Yi Chi

  5. Data Collection Module (DCM) VME64X Backplane Zero-Suppression Daughter Card LVL-1 Input Fiber Connection SHARC DSP 9-15-97 C.Y. Chi, J.L. Nagle Columbia University Data Flow through DCM June 10, 98 FEE Review Cheng-Yi Chi

  6. Data Collection Module Heat Transfer Plate VME 64X Handler SHARC DSP Zero Suppression Daughter card June 10, 98 FEE Review Cheng-Yi Chi

  7. Partitioner Data flow control FPGA includes VME block read buffer ALTERA EPF10K40 FIFO’s Event Dataflow To sub-event buffer Busy From L1 L1 Primitives June 10, 98 FEE Review Cheng-Yi Chi

  8. DCM Final Design Review • Final design Review (Jan. 29 1998) • (John Haggerty, Glenn Young, Chris Witzig, Paul Stankus, Edmond Desmond, Seymour Rankowitz) • Important actions from FDR • additional few pull-down resistors added on to token-passing timing/control lines on DCM (fixed problems for the first modules in the token chain) • 5th DSP on the DCM module will be 4 Mbits version of SHARC DSP, instead of 2 Mbits version (as requested by DCM team) June 10, 98 FEE Review Cheng-Yi Chi

  9. Timing-FEM-DCM chain test • February 1998 TOF - DCM chain test (in Nevis) • April 1998 GTM-DC FEM-DCM • GTM-PC FEM-DCM Chain Test. • (~ 2 Days effort) • Julia Velkovska, Tom Hemmick, Chuck Pancake (Stony Brook), • Jamie Nagle (Nevis) • Joe Mead, Simon Durant (BNL) (Timing, ONCS) • Melissa Smith (ORNL) • Problems Found • DCM daughter card, Diode direction was reversed (frequency lock) • On GTM, reset had to be put in for initial GLINK fill frame transmission June 10, 98 FEE Review Cheng-Yi Chi

  10. DCM Status • DCM compressor daughter cards are done • DCM main board is done (waiting for chain test with Partitioner card & backplane) • DCM Partitioner card testing is 80% done • Remaining goal is a chain test between the sub-event buffer and Partitioner June 10, 98 FEE Review Cheng-Yi Chi

  11. DCM Fabrication Plan • Parts Order started at End of March. 90% of parts on hand now (including all DSP’s & Optical Transceivers) • Fabricating compressor daughter card PC boards • P.O. for daughter card assembler placed • Start DCM main board fabrication process later this month • We have two complete test stands at Nevis • Third one will be placed in PHENIX counting house ASAP • Project completion date before End of Year June 10, 98 FEE Review Cheng-Yi Chi