1 / 9

Warm Springs Extension Alignment

Warm Springs Extension Alignment. South Ventilation Structure. South Subway Portal. Tie-in Point for SVBX Project. North Ventilation Structure. North Subway Portal . Paseo Padre Pkwy. Mission Blvd. Auto Mall Pkwy . S. Grimmer Blvd. Washington Blvd. Stevenson Blvd. Walnut Ave.

ratana
Download Presentation

Warm Springs Extension Alignment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Warm Springs Extension Alignment South Ventilation Structure South Subway Portal Tie-in Point for SVBX Project North VentilationStructure North Subway Portal Paseo Padre Pkwy. Mission Blvd. AutoMall Pkwy. S. Grimmer Blvd. Washington Blvd. Stevenson Blvd. Walnut Ave. BART Overpass Irvington Station (Future) Lake Elizabeth Warm Springs/South Fremont Station Fremont Central Park Fremont Station Fremont Central Park Subway Line, Track, Station and Systems BART Overpass (City of Fremont Grade Separation Project) 0 0

  2. Subway Work Progress

  3. LTSS Work Progress

  4. WSX Project Schedule • Subway Contract • Project Completion Spring 2013 • LTSS Contract • Revenue Service Fall 2015

  5. Project Location

  6. HMC and Hayward Shop Modifications Site Plan 2 3 1 Non-Revenue Vehicleand M&E (Maintenance & Engineering) Shop and Storage Yard Hayward Shop New Track Access Vehicle-level Overhaul Shop Component Repair Shop Central Warehouse Hayward Maintenance Complex (HMC)

  7. Contract 1 Site Plan BART Mainline Component Repair Shop Hayward Shop Modifications

  8. Contract 2 Site Plan Tie-ins and crossover