Jan Timulak DECOM, a.s . . Some economic aspects of back-end of peaceful use of nuclear energy

Jan Timulak DECOM, a.s . . Some economic aspects of back-end of peaceful use of nuclear energy. Decommissioning. Preferred concept: immediate continuous dismantling Key issue: Decommissioning of NPP A1

prentice
Download Presentation

Jan Timulak DECOM, a.s . . Some economic aspects of back-end of peaceful use of nuclear energy

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Jan Timulak DECOM, a.s. . Some economic aspects of back-end of peaceful use of nuclear energy Seminar "Financing of back-end of peaceful use of nuclear energy"

  2. Decommissioning • Preferred concept: immediate continuous dismantling • Key issue: Decommissioning of NPP A1 • Complete decommissioning of NPP A1 and significant part of the V1 decommissioning represent so-called: DEBT OF FINANCIAL SOURCES (historical debt) • Act No. 528/2006 (amended the previous one): account of the NPP A1 enabled to “borrow” the finances from the account of NPP V1 Seminar "Financing of back-end of peaceful use of nuclear energy"

  3. Debt of financial sources • The contribution of NPP operator to State Fund according the Law No. 254/1994 Coll. was determined onlyon the base of decommissioning cost (the cost for spent fuel management was not considered – storage cost, deep disposal development) Seminar "Financing of back-end of peaceful use of nuclear energy"

  4. Economic aspects Total value of historical debt (in 2010 price level) :  2,277 billions € • Full decommissioning of NPP A1, including disposal of decommissioning wastes (in near surface or deep repository) • Part of the decommissioning of NPP V1 and V2 costs, including management of the spent fuel, aliquot to production of electricity before establishing the Fund Seminar "Financing of back-end of peaceful use of nuclear energy"

  5. Contribution of A1 NPP Billions € • Present stage (01.01.2010) 0,056 • Decommissioning cost 0,723 • Refunding to account V1 0,077 • Contr. to deep repository 0,095 • Total 0,839 Seminar "Financing of back-end of peaceful use of nuclear energy"

  6. Contribution of V1 NPP Billions € • Present stage (01.01.2010) 0,239 • Refunding from account A1 0,077 • Decommissioning cost 0,667 • Spent fuel storage cost 0,116 • Contr. to deep repository 0,595 • Total 1,062 Seminar "Financing of back-end of peaceful use of nuclear energy"

  7. Contribution of V2 NPP Billions € • Decommissioning cost 0,758 • Spent fuel storage cost 0,244 • Contr. to deep repository 1,254 • Back-end total cost 2,256 • Total (16,67 % of back-end cost) 0,376 Seminar "Financing of back-end of peaceful use of nuclear energy"

  8. Economic aspects Costs (2010 pricelevel): • A1 decommissioning – 723 mil. € • V1 shut down – 41 mil. € • V1 decommissioning – 592 mil. € • V2 decommissioning preparation – 8 mil. € • V2 shut down – 56 mil. € • V2 decommissioning – 641 mil. € • EMO 1,2 decommissioning preparation – 8 mil. € • EMO 1,2 shut down – 113 mil. € • EMO 1,2 decommissioning – 584 mil. € Seminar "Financing of back-end of peaceful use of nuclear energy"

  9. Economic aspects Costs (2010 price level): • EMO 3,4 decommissioning preparation – 8 mil. € • EMO 3,4 shut down – 56 mil. € • EMO 3,4 decommissioning – 641 mil. € • Disposal of decommissioning RAW – 372 mil. € • Deep repository – 4143 mil. € • SNF storage – 787 mil. € • Orphan sources management – 43 mil. € • Institutional repository control – 10 mil. € • NJF administration – 60 mil. € Total costs – 8886 mil. € Seminar "Financing of back-end of peaceful use of nuclear energy"