320 likes | 492 Views
E N D
1. STUMPing for the EnvironmentCity of ColumbusDraft 2009 Solids Treatment and Utilization Master Plan Rob Van Evra
Treatment Engineering
City of Columbus DOSD
5 CITIES PLUS 2010
August 10, 2010
2. Solids Master Plan Considerations Stakeholder input and SWAB guidance
Mayors Climate Protection Agreement
Carbon footprint reduction
Get Green Columbus Action Plan 2010
Energy efficiency
Beneficial use/reuse/recycle
Wet weather capacities
Future nutrient limitations
3. WWTP Biosolids Breakdown Jackson Pike WWTP produces approximately 27 dry tons of WWTP biosolids each day
Southerly WWTP produces approximately 65 dry tons of WWTP biosolids each day
4. Compost Facility Composts WWTP biosolids with yard waste and woodchips to create Com-Til, a fertilizer and soil amendment product available to the public and to landscapers
Permitted to accept approximately 40 dry tons of biosolids per day
Currently operates at approximately 30 dry tons of biosolids per day
5. Biosolids Processes Modeling Evaluate all biosolids alternatives using many years of collected WWTP and Compost Facility operational data
Optimize entire WWTP/Compost process network based on specified parameters
Costs
Energy usage
Greenhouse gas emissions
6. New Network
7. Modeling Biosolids w/ Eco-Flow Investigated a wide variety of scenarios for biosolids treatment and utilization using the Ohio State University Center for Resilience’s Eco-FlowTM model
Extreme scenarios (e.g. only a single disposal option)
Diverse scenarios
Model-chosen pathways
Include new process technologies
Over 25 options at each plant
8. Quadruple Bottom Line Analyzed social, environmental, economic and technical ramifications of all options
Performed on all Eco-FlowTM scenarios
Best options included:
Utilization by Third Parties
Combinations of Land Application and Composting
Poor options included:
Incineration
Elimination of Digestion
9. Risk Probability Analysis Capital Improvement Recommendations from the draft STUMP analyzed for risk cost probabilities and consequences of any future changes in:
Regulatory requirements
Commodity prices
Environmental priorities
Technological innovations
Third-Party involvement
Asset Management Program Finalization (2010)
10. Recommended Scenario JPWWTP: 70% land application, 30% compost, digestion, sell (or clean) biogas
SWWTP: 50% land application, 50% compost, digestion, sell (or clean) biogas
Compost Facility: add 3rd pad, on-site grinding, and future bridge construction
Bottom Line – UTILIZATION IS THE KEY!
11. Recommended Plan
With the recommendations selected, a plan was developed for implementation:
12. Recommended Plan Identify, Examine and Pursue Opportunities for Third-Party Purchases:
Biogas
Biosolids
13. Recommended Plan De-emphasize reliance on incineration
Maintain air permits for the extended lifespans of the incinerators
Make upgrades to incinerators to allow optimal operation
2014 for JPWWTP
2015 for SWWTP
14. Recommended Plan Landfilling
Continue working with local landfills (2010)
Maintain availability of this disposal option
15. Recommended Plan Utilization of Anaerobic Digester Biogas
Raw biogas is currently used at both plants for boilers and as needed for incineration
If possible, sell raw biogas to a third party or electric utility for their use (2010)
Begin pilot tests of biogas cleaning systems at both plants to achieve pipeline quality (JPWWTP 2011, SWWTP 2012)
Cleaned biogas can be sold to local gas utility
Compressed Natural Gas Facilities (2017)
16. Recommended Plan Expansion of and Enhancement to Land Application Program
Multiple Contractors
Multiple Application Methods
GIS-based Application/Data Collection
Timing/Loading/Incorporation Coordination
Increase Plant Storage and Remote Storage
17. Recommended Plan Land Application Program Expansion
Refurbish land application tanks at JPWWTP (2012)
Construct land application tanks at SWWTP (2013)
Expand available fields for land application (2010)
18. Recommended Plan Centrate Phosphorus Recovery & Reuse
Recommend a pilot test at SWWTP before full scale implementation (2010)
Recommended for both treatment plants (2015)
Fertilizer produced by the process could be a source of revenue
Could decrease % ratio of phosphorus in land- applied biosolids and also reduce WWTP biosolids
Possible reduction in the amount of chemical addition needed for nutrient removal as low nutrient limits for WWTP effluents are implemented in the future
19. Recommended Plan Compost Facility Improvements
Part 1: Construct 3rd compost pad w/ biofilter to negatively aerate curing and add grinder to provide more fresh bulking agent (2011)
Follow-up odor analysis to be conducted after Part 1 (2013)
Part 2: Bridge between SWWTP and the Compost Facility (2016)
20. STUMP Team Malcolm Pirnie, Inc.
Cosmo Bertino, PE
Kathleen Smith, PE
Dan Gernant, PE
Eric Auerbach, PE
Ribway Engineering Group – Debby Evans
The Ohio State University Center for Resilience
Dr. Joseph Fiksel
Dr. Kieran Sikdar
Dr. Emrah Cimren
Dr. Mark Posner
21. Questions or Comments?Rob Van Evrarevanevra@columbus.gov(614) 645-79611250 Fairwood Avenue, Room 0020Columbus, Ohio 43206
22. Site Layouts
23. Compost Facility Site Layout
24. Compost Facility/SWWTP Bridge
25. Southerly WWTP
26. SWWTP Site Layout
27. Jackson Pike WWTP Bullets
28. JPWWTP Site Layout
29. Methodology
30. Grouping of Similar Eco-FlowTM O&M Cost, Energy, and GHG Outcomes
31. Selected Scenario from Each Grouping
32. Selected Scenarios with Best GHG Performance per Dollar
33. Selected Scenarios with Best GHG Performance per Dollar