GLAST Large Area Telescope LAT Flight Software System Checkout TRR Current Status

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope LAT Flight Software System Checkout TRR Current Status Sergio Maldonado FSW Test Team Lead Stanford Linear Accelerator Center. Current Status. RFAs Development status Open JIRA Items Test Environment (NCR)

Download Presentation

GLAST Large Area Telescope LAT Flight Software System Checkout TRR Current Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope LAT Flight Software System Checkout TRR Current Status Sergio Maldonado FSW Test Team Lead Stanford Linear Accelerator Center

  2. Current Status • RFAs • Development status • Open JIRA Items • Test Environment (NCR) • Procedure/Script Status (dry runs) FSW System Checkout TRR: Current Status

  3. RFA Status • 6 Flight Unit Peer Review RFAs • Closed: 1 • Responses submitted and awaiting closure: 5 • Action Plan • Ensure all RFAs closed prior to FSW System Test TRR FSW System Checkout TRR: Current Status

  4. Development Status • Current status • Known liens • Implementation of output to the Science Data Interface • Command/control/telemetry/mode interface to event data (LPA) • Action plan • Build 0-5-0 will include event filtering plus implementation of subset of output across SDI to enable completion of a subset of test scripts • Subsequent build 0-5-1 will provide all remaining functions FSW System Checkout TRR: Current Status

  5. FSW in QT Build FSW System Checkout TRR: Current Status

  6. Open JIRA Items FSW System Checkout TRR: Current Status

  7. Open JIRA Items (2) FSW System Checkout TRR: Current Status

  8. Open JIRA Items (3) FSW System Checkout TRR: Current Status

  9. Test Environment Status • Current status • VSC science data decoder SW • Action plan • Complete ASAP FSW System Checkout TRR: Current Status

  10. Procedure/Script Status • All test procedure documents baselined: • Most likely need update depending on status • Test script development nearing completion: • Many scripts have been run to completion and are ready for QT • Some scripts have related FSW liens, but will be ready for QT once the liens are satisfied FSW System Checkout TRR: Current Status

  11. Script Status (2) FSW System Checkout TRR: Current Status

  12. Script Status (3) FSW System Checkout TRR: Current Status

  13. Script Status (4) FSW System Checkout TRR: Current Status

  14. Script Status (5) FSW System Checkout TRR: Current Status

  15. Script Status (6) FSW System Checkout TRR: Current Status

  16. Script Status (7) FSW System Checkout TRR: Current Status

  17. Script Status (8) FSW System Checkout TRR: Current Status