1 / 26

Reliability Redispatch Pilot Presentation for NIPPC June 13, 2007

Reliability Redispatch Pilot Presentation for NIPPC June 13, 2007. Term of Pilot 6/26/07 through 9/30/07. Project Status. Software Development complete Hardware environments configured and operational Dispatch and scheduling procedure changes documented

mia-paul
Download Presentation

Reliability Redispatch Pilot Presentation for NIPPC June 13, 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Reliability Redispatch Pilot Presentation for NIPPCJune 13, 2007 Term of Pilot 6/26/07 through 9/30/07

  2. Project Status • Software Development complete • Hardware environments configured and operational • Dispatch and scheduling procedure changes documented • Dispatch, scheduling and bidder training underway • Pilot agreement nearing completion

  3. Bid Tool Overview • Redispatch Bid Content • Generator • Day and Hour ending • Quantity (MW) available within 10 min. • Price per MWh • Increase (INC) and/or Decrease (DEC)

  4. Bid Validation Rules Bid Data • INC Only Bid • DEC Only Bid • INC and DEC Bid • Neither – Zero Bid • INC Bid includes INC MW & INC Price • DEC Bid includes DEC MW & DEC Price

  5. Bid Validation Rules Megawatts • Whole # > Zero • Not exceeding Generator’s established Maximum INC/DEC MW amount. • Not less than Generator’s established Minimum INC/DEC MW amount.

  6. Bid Validation Rules Price • Positive U.S. currency value per MWh • Not exceeding established Maximum INC/DEC Bid Price Limit. ($400) • Not less than established Minimum INC/DEC Bid Price Limit. ($0)

  7. Submitting a Bid • Submitted or changed up to 20 minutes prior to flow hour. • No further into the future than 5 days. (Day +5)

  8. Bid Tool Demonstration

  9. Calculate Redispatch Background

  10. Simplified RRP Map

  11. Introduction • A generator’s impact on a flowgate is measured by its Power Transfer Distribution Factor or PTDF. • PTDF is also known as Path Utilization Factor (PUF) and Transmission Loading Relief (TLR).

  12. Introduction cont. • The PTDF is the ratio impact to the loading on a specific flowgate based on an increase (INC) at the generator and a like decrease (DEC) at a reference bus (Grand Coulee for our studies). • A positive PTDF will increase the loading. • A negative PTDF will decrease the loading and provide relief.

  13. Flowgates and PTDFs/PUFs Reference Bus PUFs are zero Flowgates

  14. Redispatch • To relieve the loading on the path, we find the pairs of generators that will provide relief. • We look for combinations of INC generator and DEC generators with a combined PTDF that is negative. • The combined PTDF is the INC PTDF – DEC PTDF. • Numbers closer to -1.0 are more effective. + -

  15. Single Redispatch Pair JDA-CNT Redispatch: 35 MW Impact: 35*-0.508= -17.8 MW

  16. Redispatch Solution • To get more relief, redispatch more pairs of generators. • Since a single generator could be involved in multiple pairs, the amounts are summed and each generator is called once.

  17. Calculate Redispatch 35-MW Paul-Allston Example

  18. 35-MW Paul-Allston Example

  19. 35-MW Paul-Allston Example

  20. 35-MW Paul-Allston Example

  21. 35-MW Paul-Allston Example

  22. 35-MW Paul-Allston Example

  23. 35-MW Paul-Allston Example

  24. 35-MW Paul-Allston Example

  25. 35-MW Paul-Allston Example

  26. 35-MW Paul-Allston Example

More Related