1 / 22

EDS 4 Release 9.1 DAM/RUC/SASM

EDS 4 Release 9.1 DAM/RUC/SASM. 4.9.1 Market Call. January 11, 2008. Agenda. DAM/RUC EDS 4.9.1 Brief Review of Objectives Timeline Testing Window Filing Issues High Level View of Test Cases QSE Data Preparation Known Issues Next Steps Q&A and Roll Call Appendix

marycain
Download Presentation

EDS 4 Release 9.1 DAM/RUC/SASM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EDS 4 Release 9.1DAM/RUC/SASM 4.9.1 Market Call January 11, 2008 http://nodal.ercot.com 1

  2. Agenda • DAM/RUC EDS 4.9.1 • Brief Review of Objectives • Timeline • Testing Window • Filing Issues • High Level View of Test Cases • QSE Data Preparation • Known Issues • Next Steps • Q&A and Roll Call • Appendix • Connectivity and Digital Certificate information http://nodal.ercot.com 2

  3. DAM/RUC EDS 4.9.1 Overview: Objectives • 4.9.1 Objectives of EDS 4.9.1 • Verify QSE’s ability to use either or both the MISUser Interface or Web Services interface as indicated in their sign-up email to perform scenarios specified for the following: • CRR Offer (NOIE and PCRR Holders only) • PTP Obligation • Three-Part Supply Offers for Energy (Only QSE’s w/ Resources) • Capacity Trade • Energy Trade • AS Trade • DAM Energy-Only Offer • DAM Energy Bid • AS Self Arrangement (Only QSE’s with Load) • AS Offer (Only QSE’s with Resources) • Self Schedule • DC Tie Schedule • Verify QSEs understanding of DAM/RUC input validation rules http://nodal.ercot.com 3

  4. DAM/RUC 4.9.1 Timeline: Reminder of Sandbox Testing http://nodal.ercot.com 4

  5. DAM/RUC 4.9.1 Timeline: Example Activity Timeline EDS TIMELINE Example Activity Timeline http://nodal.ercot.com 5

  6. DAM/RUC 4.9.1 Testing: Testing Window • QSE’s should have already have signed up via email for a testing window • Testing Window includes: • 2 hour support and scripted testing call • Resolution of issues during the 2 hour support call • 7 day testing window for prioritized support and self guided testing • Self guided testing are test scenarios that the QSE has defined and executes independently in the EDS environment • See Appendix for • Connectivity/Digital Certificate information • Sign-up email to eds4@ercot.com http://nodal.ercot.com 6

  7. DAM/RUC 4.9.1 Testing: Support Calls • Next week begins… • Individual Support Calls Monday-Thursday every week • 2 Time Slots available 9am – 11am and 1pm – 3pm • Fridays Calls are reserved for: • Issue Resolution • Follow-up calls • Market wide status calls • Calendar is posted Weekly on the Readiness Center / EDS 4 / Documents: http://nodal.ercot.com/readiness/eds4/documents/index.html http://nodal.ercot.com 7

  8. DAM/RUC 4.9.1 Testing: Support Calls (continued…) • QSE’s using Web Services • Will perform all test scenarios on the web services during support call • Will perform a subset of scenarios on the MIS UI independently within 1 week of support call • Once MIS UI scenarios are complete, QSE will notify ERCOT • ERCOT will validate MIS UI submitted transactions • QSE’s using the MIS User Interface • Will perform all test scenarios on MIS User Interface during the support call • Validation will take place on the support call http://nodal.ercot.com 8

  9. DAM/RUC 4.9.1 Testing: Support Call Test Cases * See EDS 4.9.1 DAM / RUC Submissions Test Scripts Document to be posted to readiness 12/21/07 by EOB http://nodal.ercot.com 9

  10. DAM/RUC 4.9.1 Tracking: Master Schedule for Next Week http://nodal.ercot.com 10

  11. DAM/RUC 4.9.1 Tracking: Dashboard • To view the most updated copy refer to the readiness center at:http://nodal.ercot.com/readiness/eds4/documents/index.htmlUnder Weekly Status http://nodal.ercot.com 11

  12. DAM/RUC 4.9.1 Tracking: Readiness Metrics • Sign-Up Testing Window Scheduled • QSE signs up by 1/4/2008 – Status is GREEN • QSE’s that have not signed up by • 01/04/08 – Will turn Amber until signed up • 03/15/08 – Will turn red • MP8 - QSE Ability to Submit Transactions Via MIS • Expected completion date March 15 • MP9 – QSE Ability to Submit Web Service Transactions • Expected completion date March 15 • Execution • MP’s that have met readiness metric M8 or M9 by 3/15/08 are GREEN • MP’s that have attempted readiness metric M8 or M9 by 3/15/08 are AMBER • MP’s that have not yet attempted readiness metric M8 or M9 by 3/15/08 are RED • MP16 - MP EDS-4 Trials Participation (phase 2) • ERCOT is calling all QSEs that have not signed up for EDS4 http://nodal.ercot.com 12

  13. DAM/RUC 4.9.1 Reference: Relevant Documents http://nodal.ercot.com 13

  14. DAM/RUC 4.9.1 Reference: Relevant Documents http://nodal.ercot.com 14

  15. DAM/RUC 4.9.1 Reference: QSE Data Preparation Download Settlement Points and QSE Short Name List (both files posted on Readiness- http://nodal.ercot.com/readiness/eds4/documents/index.html) • QSE Short Names used in transactions • Your QSE short name is needed as <source> in XML Header • All QSE short names listed, but may change • Can use ERCOT test QSE of “TSTQSE” to avoid populating and changing QSE list in your systems • Settlement Point used as points of business in submission testing • Naming examples -> http://nodal.ercot.com 15

  16. DAM/RUC 4.9.1 Reference: Known issues • Known issues will be posted to the Noda Readiness Center under EDS 4: • File will be posted by COB 1/14 • http://nodal.ercot.com/readiness/eds4/documents/index.html • User Interface • Performance issues are being encountered http://nodal.ercot.com 16

  17. DAM/RUC 4.9.1 Reference: QSE Activity Summary • If not signed-up for testing, please do: eds4@ercot.com • Download and review the EDS 4 Test Package • Send sample XML to ERCOT no less than 2 weeks prior to Testing Window • Make Modifications (if any) to XML’s that ERCOT provides • Prepare final XML files for Support Call • Prepare systems with Settlement Point data • Read and be familiar with Documents on previous slides • Send all questions to eds4@ercot.com http://nodal.ercot.com 17

  18. Q&A / Open Forum http://nodal.ercot.com 18

  19. APPENDIX http://nodal.ercot.com 19

  20. DAM/RUC 4.9.1 Testing: Basic Communications Test (“Ping” Test) (continued….) • Prior to this test QSE’s using External Web Services will need to have their network and security teams make the following changes: • QSE’s Market System must be able to access:https://nodaleds.ercot.com:80/2007-08/Nodal/eEDS/EWS/NOTE: this SSL URL is on port 80NOTE: this is changed from Release 3.5 • QSE’s must be able to receive messages from 66.128.17.136 • QSE’s must be able to send messages to EDS Environment: 66.128.17.32Sandbox Environment: 66.128.16.84 http://nodal.ercot.com 20

  21. DAM/RUC 4.9.1 Testing: Basic Communications Test (“Ping” Test) (continued….) • QSE’s using MIS User Interface will need to have their network and security teams make the following changes: • Must be able to access: MIS URL: https://nodaleds.ercot.com/pps/tibco/mis/NOTE: MMS User Interface will have link from MISNOTE: MIS/MMS UI are on port 443 http://nodal.ercot.com 21

  22. DAM/RUC 4.9.1 Testing: Digital Certificates • 1 digital certificate w/ a Generic Userid (NODALTEST) will be Generated for Each QSE and Sub-QSE • The MP’s USA does not need to take any action • This is the only certificate that will work in the EDS environment • This certificate will also work in the Nodal Sandbox environment • It will not work in production, MOTE, or any other ERCOT environment • The Digital Certificate will be sent to the MP USA • Distribution will occur after the QSE signs up for a Testing Window and Just Prior to the Support Call • (for those requiring the basic communications test, it will be sent prior to that session) • All valid ERCOT issued digital certificates will continue to work in the Nodal Sandbox http://nodal.ercot.com 22