1 / 8

Conventional Pavement Structure

Conventional Pavement Structure. 12.25 inches Asphaltic Concrete Paving. stress. 12.00 inches Graded Aggregate Base. Prepared Subgrade. Inverted Pavement Structure. 2.00 inches Asphaltic Concrete Paving. 6.00 inches Graded Aggregate Base. stress. 10.00 inches Cement Treated Base.

Download Presentation

Conventional Pavement Structure

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Conventional Pavement Structure 12.25 inches Asphaltic Concrete Paving stress 12.00 inches Graded Aggregate Base Prepared Subgrade

  2. Inverted Pavement Structure 2.00 inches Asphaltic Concrete Paving 6.00 inches Graded Aggregate Base stress 10.00 inches Cement Treated Base Prepared Subgrade

  3. Inverted Base Construction Asphaltic Concrete Paving Graded Aggregate Base Cement Treated Base Subgrade Minimum CBR Value of 15

  4. Inverted Base Construction Asphaltic Concrete Paving Graded Aggregate Base Cement Treated Base 145 psi to 435 psi Subgrade

  5. Inverted Base Construction Asphaltic Concrete Paving Graded Aggregate Base 86% of Apparent Density Cement Treated Base Subgrade

  6. Inverted Base Construction Asphaltic Concrete Paving For Protection of GAB Layer Graded Aggregate Base Cement Treated Base Subgrade

  7. Cost Comparisons Inverted Base Structure GDOT Interstate Structure Total Placement Cost = $39.41 y² Total Placement Cost = $54.03 y²

More Related