1 / 27

SRF Vertical Test Cryostat Design Review

SRF Vertical Test Cryostat Design Review. 16 May 2006 IB1. Introduction. Welcome and introductions Charge to the committee: Assess the technical design of the ILCTA IB1 SRF Vertical Cryostat and its readiness for the procurement/fabrication process

maddox
Download Presentation

SRF Vertical Test Cryostat Design Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SRF Vertical Test CryostatDesign Review 16 May 2006 IB1

  2. Introduction • Welcome and introductions • Charge to the committee: • Assess the technical design of the ILCTA IB1 SRF Vertical Cryostat and its readiness for the procurement/fabrication process • Comment on all technical aspects of the Cryostat design, including integration to the IB1 cryogenic system • Provide a written report. ILCTA-VTC Design Review

  3. …not a facility safety review • Focus on • Cryostat technical specifications • Readiness for procurement • Review outline • Location of and purpose of facility in IB1 (Joe Ozelis) • Cryostat system requirements (Mayling Wong) • Integration with IB1 Cryogenic System, P&ID, and Cryogenic Design Parameters (Roger Rabehl and Yuenian Huang) • 3D model overview (Clark Reid / Mayling Wong) • Documentation requirements (Mayling Wong) • Cost estimate, procurement plan, and schedule (Cosmore Sylvester) ILCTA-VTC Design Review

  4. Goals of the ILC Vertical Cavity Test Program • Verify cavity processing improvements by quantifying cavity performance in a reliable, reproducible, and efficient manner. • Measure Q0 vs Temperature • Measure Q0 vs E • Measure Field Emission (radiation) • Investigate effect of low temperature externally performed bakeout on Q-drop • Initial throughput expected to be ~ 2 cavities/month, increasing to ~ 2 cavities/week. Multiple tests/cavity (Q-drop) increase this. • System is to be capable of testing cavities designed for the ILC Main Linac cryomodule. • Baseline Design: Tesla cell shape, 9 cells, 1.3 GHz. Alternate geometries, # cells, superstructures, may also be evaluated. ILCTA-VTC Design Review

  5. Cavity Test Facility Location ILCTA-VTC Design Review

  6. Cavity Test Facility Location Existing cryogenic services Approx size/location of cryostat pit/hole ILCTA-VTC Design Review

  7. Cavity Test Facility Cryostat/Cryogenic Requirements • LHe bath capable of operation between 4.3 and ≤ 1.6K • Cooldown rate from 300K to 4K that minimizes Q–disease susceptibility (minimize time spent between 100-150K) • Sufficient volume of LHe above cavity to preclude need for active LHe level control during testing (190-200cm – 165cm to top cavity flange) • Instrumentation to provide readout of Dewar pressure, temperature, and LHe level • Fast turnaround – • Cooldown & fill : 4-6 hours • Pumpdown : 2-4 hours (can be concurrent w/ fill if not performing Q0 vs T measurements) • Remnant LHe boiloff : 3-5 hours (150-180W for 800L) • Warmup to 300K : 10-12 hours (400K He gas at ~2g/s) ILCTA-VTC Design Review

  8. Example Test Cycle (w/ Q0 vs T measurement) Insert stand into Dewar Leak check Dewar seal Leak check test stand Attach RF & instrumentation cables Pump/purge Dewar w/ GHe, check for contamination Cooldown Fill @ 4K Cable calibrations @ 4K Measure cavity frequencies (all modes) Perform low field (2-3 MV/m) Q0 measurement (1W amplifier) Begin pumpdown to ~1.5K, take low field Q0 data Warm back up to 2K Perform Q vs E measurements at 2K Boiloff remnant LHe Warm Dewar 0.5hr 0.5hr 1hr 0.25hr 1hr 1.5hrs 4hrs 0.5hr 0.25hr 0.5hr 3hrs 0.5hr 2hrs 4hrs 12hrs Total warm-warm cycle time = 31.5hrs ILCTA-VTC Design Review

  9. Example Test Cycle (w/o Q0 vs T measurement) Insert stand into Dewar Leak check Dewar seal Leak check test stand Attach RF & instrumentation cables Pump/purge Dewar w/ GHe, check for contamination Cooldown Fill @ 4K, begin pumping to 2K when LHE collects Cable calibrations @ 2K Measure cavity frequencies (all modes) Perform Q vs E measurements at 2K Boiloff remnant LHe Warm Dewar 0.5hr 0.5hr 1hr 0.25hr 1hr 1.5hrs 4hrs 0.5hr 0.25hr 2hrs 4hrs 12hrs Total warm-warm cycle time = 27.5hrs ILCTA-VTC Design Review

  10. Example Test Schedule (includes Q0 vs T msmt) Day 1 : Load test stand, all checkouts, cooldown & fill to 4K Day 2 : Q0 vs T, Q0 vs E, boiloff Lhe and begin Dewar warmup Day 3 : Remove test stand, setup for 120° C bake – 24 hours Day 4 : Load test stand, all checkouts, cooldown & fill to 4K Day 5 : Q0 vs T, Q0 vs E, boiloff LHe and begin Dewar warmup This scenario supports 2 tests per week of the same cavity, with a 24hr 120° C bake between tests. If Day 3 is a Friday, can do a 48hr bake over a weekend. ILCTA-VTC Design Review

  11. Example Test Schedule (w/o Q0 vs T msmt) Day 1 : Load test stand, all checkouts, cooldown, fill, pump to 2K, Q vs E, start boiloff & warmup script (long day) Day 2 : Remove test stand, setup for 120° C bake – 48 hours, swap cavities Day 3 : Load test stand, all checkouts, cooldown, fill, pump to 2K, Q vs E, start boiloff & warmup script (long day) Day 4 : Remove test stand, setup for 120° C bake – 48 hours, swap cavities (baked one) Day 5: Load test stand, all checkouts, cooldown, fill, pump to 2K, Q vs E, start boiloff & warmup script (long day) This scenario supports 3 tests per week, 2 different cavities, one of which gets a 48hr 120° C bake between tests. ILCTA-VTC Design Review

  12. Conclusions • The aggressive test schedules described here can be fully supported by a • cryostat/cryogenic system that provides: • LHe bath capable of operation between 4.3 and ≤ 1.6K • Cooldown rate from 300K to 4K that minimizes Q–disease susceptibility (minimize time spent between 100-150K) • Fast turnaround – • Cooldown & fill : 4-6 hours • Pumpdown : 2-4 hours (can be concurrent w/ fill if not performing Q0 vs T measurements) • Remnant LHe boiloff : 3-5 hours (150-180W for 800L) • Warmup to 300K : 10-12 hours (400K He gas at ~2-4g/s) • The present design will be shown to meet these requirements. • Additionally, it does not preclude testing of alternate cavity designs or • more extensive (R&D) testing. ILCTA-VTC Design Review

  13. Cryogenic System Requirements ILCTA-VTC Design Review

  14. Cryogenic System Requirements ILCTA-VTC Design Review

  15. IB1 Refrigeration Capability • Calculated cooling capacity of 125 W at 2 K. • Assumes 88-90% efficient J-T heat exchanger pre-cooling the supplied LHe. This HX is identical to one used in the MTF LHC quadrupole feed box. • Assumes 3 Torr pressure drop through the pumping line between the new test facility and the Kinney pumps. ILCTA-VTC Design Review

  16. ILCTA-IB1 Vertical Dewar P&ID ILCTA-VTC Design Review

  17. Integration with IB1 Refrigerator • LHe supplied across the roof of IB1 through the existing transfer line from the 10 kl dewar. Drawn off a phase separator, 5 K boiloff will cool a dewar intercept and a baffle. • GHe pumped away via Kinney pumps, returned directly to compressor suction, or vented to atmosphere. The first option requires a new pumping line, the last two options will use existing VMTF piping. • LN2 supplied from 10 kgal dewar, tying into existing VMTF piping. • GN2 vented to atmosphere, tying into existing VMTF piping. ILCTA-VTC Design Review

  18. Helium Vessel Thermal Design • Heat load to 2 K helium bath is controlled 80 K shield and heat intercepts at 80 K and 5 K level • 80 K shield and intercept will be cooled by LN2 • 5 K heat intercept will be cooled by GHe vapor from phase separator, 10 W heater to control vapor flow • Heat load to 2 K from other sources (pumping line and instrumentations wired) will be estimated later, however, it should be around 2 W or so level ILCTA-VTC Design Review

  19. Helium Vapor Pressure Drop • The total vapor pressure drop will be about 3 torr and that’s our design goal • 2” line is 150 ft and 6” line is 300 ft • Total vapor pressure drop breaks down to three parts in the pumping line in our calculation • Pressure drop within JT heat exchanger, < 1 torr • Pressure drop along 150 ft, 2” insulated piping, 3.5 K inlet and 5 K outlet, the average pressure drop is 1.01 torr • Pressure drop along 300 ft, un-insulated 6” piping, 5 K inlet and 300 K outlet, the average pressure drop is estimated to be 0.843 torr ILCTA-VTC Design Review

  20. Cryostat Layout ILCTA-VTC Design Review

  21. Helium Vessel • ASME BPVC vessel • Dimensions - 304SS shell • 28-inch OD • 0.094-inch thick • Thickness driven by external pressure (due to leak in insulating vacuum) • To minimize thickness (& conduction heat load) use Stiffeners every 30-inch along length • L1X1X1/4-inch angle bent & intermittently welded • 16-feet long ILCTA-VTC Design Review

  22. Helium Vessel (cont’d) • Relief system • Burst disc • 65-psig set pressure • 1.5-inch - Sized assuming complete helium vaporization during leak of insulating vacuum (resulting flux of 0.6 W/cm2) • Code Relief valve • 50-psig set pressure • Connected to top plate of removable insert (not part of this assembly/procurement) • Heater for dewar warm-up • Temperature of helium 420K • Helium pressure 3-psig ILCTA-VTC Design Review

  23. Top flange of helium vessel • Thickness 1-inch • Sized to ensure welded joint to the helium vessel shell is adequate, following guidelines of ASME BPVC Top flange of Helium vessel ILCTA-VTC Design Review

  24. Status of Documentation • Engineering drawings • 75% exist for initial design iteration • Engineering notes • Helium vessel: 75% complete • Vacuum vessel • Pressure drop calculations • Heat load analysis • Relief valve sizing • Technical specification for vendor (required at the time the RFP is issued) ILCTA-VTC Design Review

  25. Cost Estimate ILCTA-VTC Design Review

  26. Procurement Plan • Complete the Design of the Cryostat assembly and release via. an RFP. Select the “best” qualified vendor based on a technical evaluation of the vendor’s proposal - not solely on lowest bid. While cryostat Procurement is underway- • Continue to work towards a final design of the magnetic shielding and release these drawings for fabrication (estimated del: 6 weeks ARO) • Continue to work on the final design of the top plate and suspension components and then release these for fabrication • located a supplier of the Lead and has a quote and estimated delivery (6 weeks ARO) • located a supplier for an encapsulant (rated for 4.5K use) which could be used on the exposed lead surfaces ILCTA-VTC Design Review

  27. Schedule ILCTA-VTC Design Review

More Related