An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PAKS EVENT LESSONS LEARNED Presented By: Chuck Casto U.S. Nuclear Regulatory Commission

  2. Agenda • Background • Description of the event • Investigation of the event • Mission Insights • Pictures of the damaged fuel

  3. Background • PAKS, 4-unit VVER-440 supplies 40% of Hungary’s electricity • Neglected VVER-440 aging SG feed water sparger operating experience • By 2000, four of six SGs for U-2 could not be ignored (had to replace all 4 in one outage) • Replacement activities hampered by high radiation

  4. Background (cont’d) • SG chemical decon introduced crud deposits into RCS • Eventually three units derated (84-98%) • Core replacement did not help • Regulator wanted problem solved

  5. 1999 Magnetite deposits in the primary circuit 2000 2001 Unit 1 Background (cont’d)

  6. Unit 1 Unit 2 100 95 Unit 3 90 p2 p2 új paraméterek new parameters Reactor scram in December 85 p2 p2 January 2003.: Reactor shutdown (economic reason) 80 new parameters új paraméterek power scale Power loss caused by Magnetite deposition in the primary circuit 94% 94% 92%

  7. Background(cont’d) • “Fuel Deposit Team” created to look for solutions • Two options – internal and external fuel cleaning • Vendor worked on internal cleaning SE for months prior to the Unit 2 outage • At last minute changed option to externalcleaning

  8. Background(cont’d) • Previous experience of external cleaning seven “cool” assemblies at a time (total 150 assemblies) • Design expanded to 30 assemblies “hot” • The design as considered as “like-for-like” • License application submitted to regulator for “license in principle”

  9. System Configuration

  10. Unit 2: Location of Cleaning System Refueling machine Interim cover reactor cleaningequipment Pool No. 1. cleaning tank

  11. The Event • Unit 2 outage - April 4 - 10, 2003, 5 loads of fuel cleaned (some hot, some cool) • Sixth load was cleaned April 10, completed at 4:00p.m. but crane not available • Shut down of cleaning system and tank remained sealed

  12. The Event (cont’d) • 10p.m. reactor building high radiation • 2:00a.m. hydraulic lock opened and lid released • Sharp increase in radioactivity • Classified INES level 2 • April 16, video inspection revealed major damage – re-classified INES level 3

  13. Events during the incident Rad Level MBq End of cleaning 16:00 Cover lifting failed: 04:20 Startup of submersible pump 16:40 Area of spent f.p.: 12 mSv/h 02:45 Discharge of water 16:56 Hydraulic lock open, bubble outbursts: 02:15 Spent fuel pool water level increase 19:20 Venting fans started: 23:45 Increase of KR-85 activity in the cleaning system 21:50 Supervisor ordered to leave the R. hall 23:30

  14. Investigation of the event • The Paks plant submitted an investigation report on May 10 to the HAEA • The report was published on the plant’s homepage also in Hungarian and English languages (www.atomeromu.hu) • Framatome completed an investigation report • The HAEA final investigation report wasissued at the end of May • HAEA requested a review by the IAEA

  15. Mission Insights • Time pressure • Heavy reliance on contractor • Novel technology • Inadequate safety review

  16. Mission Insights(cont’d) • Inadequate safety review • Inaccurate bypass flow calculations • Simple thermodynamic calculation • Outlet connection at tank bottom • Undersized submersible pump • Relied upon 12 min 9 sec time to boiling • Single failure criteria not met • Nointernal instrumentation

  17. Mission Insights(cont’d) • Fuel deposit team • Not budgeted • Consisted mainly of managers • Solving the problem was the priority not the technique (subcommittee) • Managers from independent groups (QA/NAS) • During safety reviews, same line managers processed the safety evaluation

  18. Mission Insights(cont’d) • Safety evaluation assumptions not translated into design, operating procedures and training for workers (OJT) • Inadequate independent safety review by PAKS • Safety Culture assessments by HAEA were not adequately addressed

  19. Mission Insights(cont’d) • Inadequate root cause evaluation by PAKS/HAEA • Complex HAEA licensing process • HAEA safety review process did not meet international standards • Failure to verify contractor’s claims • Inadequate technical content of licensing package

  20. Mission Insights(cont’d) • Regulator failed to understand relationships between cleaning modification and safety • INES classification changes diminished public confidence

  21. AdditionalConfiguration Management Issues • Five types of licenses • Principle modification • Fabrication and import • Installation • Modification (includes fab, import and installation • Operations

  22. Additional Configuration Management Issues(cont’d) • License type determined by “safety significance” and “safety class” (design criteria) in that order • Reverse logic from the IAEA 1999 standard • Considered cleaning tank a “cask” but did not follow licensing process for a cask

  23. Additional Configuration Management Issues(cont’d) • Content of Licenses not specified • For the tank modification, regulator accepted an incomplete license package

  24. Additional Configuration Management Issues(cont’d) • Specific plant issues: • Did not process concerns for undersized pump • Did not use remote verification of fuel assembly alignment • Did not install dedicated crane • Did not provide redundant power supplies for cooling pump • Did not notify of past delays in opening the tank