DRE20 Recovery

Loading in 2 Seconds...

play fullscreen
1 / 19

DRE20 Recovery - PowerPoint PPT Presentation


  • 77 Views
  • Uploaded on

DRE20 Recovery. The Problem DRE20 was positioned at a combined angle of 45.5 degrees from the horizontal. The Objectives Recover DRE20: Safely. Minimise collateral damage to the machine. To allow return to work as soon as possible. DRE20 Recovery. The Problem Con’t. DRE20 Recovery.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'DRE20 Recovery' - libitha


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
dre20 recovery
DRE20 Recovery
  • The Problem
    • DRE20 was positioned at a combined angle of 45.5 degrees from the horizontal.
  • The Objectives
    • Recover DRE20:
      • Safely.
      • Minimise collateral damage to the machine.
      • To allow return to work as soon as possible.

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery1
DRE20 Recovery
  • The Problem Con’t

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery2
DRE20 Recovery
  • The Problem Con’t
    • Material in the area does not have a high bearing capacity.
    • Machine could not safely be recovered using traditional methods of material removal from under the tub due to the type of material and the angle of the machine.
      • In previous recoveries, machines had slipped along the centreline of the machine (ie Nose down, or ballast box down).
      • Initial meetings determined that traditional recovery methods were not able to be applied in this situation.
    • Initial Centre of Gravity checks determined that the machine required a restraint to be used to control movement.

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery3
DRE20 Recovery
  • The Solution:
    • The recovery of DRE20 required the collaboration of experts in their field of Engineering.
  • The Recovery Method:
    • After the slip, the machine was stabilised and planning had begun on the method of recovery to meet the objectives.
    • Excavation to a level to allow DRE20 to sit level.
    • Attach winch frame and position dragline buckets as anchor points
    • Complete excavation under tub
    • Winch machine back to a level position to allow it to walk out under its own propel system
    • Repair machine as needed.

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery4
DRE20 Recovery
  • Overall Recovery Plan

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery5
DRE20 Recovery
  • The Righting Frame
    • Weighed 30 Tonnes and was made of 1200mm Welded Beams.
    • When load is applied, it moves the CoG toward the rear of the machine 1m for every 100t applied.

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery6
DRE20 Recovery
  • Dragline Bucket and Winch Location

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery7
DRE20 Recovery
  • Dragline Bucket Installation and Winch Location

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery8
DRE20 Recovery
  • Ready to Winch

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery9
DRE20 Recovery
  • Video – Initial Cut with Excavator

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery10
DRE20 Recovery
  • Video – RC Dozer in action

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery11
DRE20 Recovery
  • Video – RC Dozer in action

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery12
DRE20 Recovery

Video – RC Dozer in action

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery13
DRE20 Recovery
  • Video – RC Dozer in action

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery14
DRE20 Recovery
  • Video – RC UG Miner in Action

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery15
DRE20 Recovery
  • Almost level

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery16
DRE20 Recovery
  • Level!!!!

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery17
DRE20 Recovery
  • Repairs post Levelling
    • LHS Boom Foot Stiffening between Clusters 1 and 2.
    • Lube Room Panel Beating
    • Crack repairs
    • Motor Armature cables replaced
    • Oil re-filled

H:\01 Administration\Presentations\State of Nations\2008\State of Nation – July 2008

dre20 recovery18
DRE20 Recovery
  • Thanks
    • To everyone involved, as the recovery would not have gone as smoothly without your input and help.