1 / 17

Squamish Neighbourhood Energy Utility: Final Feasibility Presentation

Squamish Neighbourhood Energy Utility: Final Feasibility Presentation. Prepared for: District of Squamish and Project Sponsors Prepared by: Compass Resource Management Ltd. June 15, 2010. Study Overview. Demand forecast (five target areas) Analysis of business as usual (BAU)

lacy-bass
Download Presentation

Squamish Neighbourhood Energy Utility: Final Feasibility Presentation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Squamish Neighbourhood Energy Utility:Final Feasibility Presentation Prepared for: District of Squamish and Project Sponsors Prepared by: Compass Resource Management Ltd. June 15, 2010

  2. Study Overview • Demand forecast (five target areas) • Analysis of business as usual (BAU) • Screening of many supply options • Detailed analysis of short-listed scenarios • Area A + expansion scenarios (Waterfront and Oceanfront) • Biomass, ocean heat, and natural gas co-generation • Staging and sensitivity analysis

  3. Demand Forecast – Focus Areas and Phasing

  4. Demand Forecast – Phasing

  5. Supply Screening – Shortlist • Biomass • Abundant local resource • One of lowest cost options in screening and greatest GHG emission reductions • Ocean Heat • Potentially slightly higher cost than GX but more available resource • Best heat pump option for this location • Some further optimization may be possible with cooling service to commercial loads • Natural gas cogeneration • BC Hydro is interested in systems which also produce electricity • Best commercial electricity production option at this scale. • Natural gas cogeneration is a stepping stone to biogas cogeneration • GHG emissions depend on whether we use provincial perspective or regional trade perspective.

  6. Summary Results – Base Case No Grants, Private Financing, Property Taxes Included

  7. Total Capital Costs by Demand and Supply Scenario ($,000)

  8. Sample Phasing of Capital (All Three Service Areas)

  9. Sample Cashflows - Municipal Financing

  10. Summary Results - GHG Reductions

  11. Summary Results – Gas and Electricity System Impacts

  12. Summary Results - Grant Requirements Grant required to achieve competitive rates and target return on investment. Municipal financing scenario assumes 100% debt financing and no property taxes.

  13. Summary Results – Conclusions • All options require some level of grants to achieve competitiveness and break-even requirements. • Biomass is least cost option in all demand scenarios and has the highest total GHG emission reductions and greatest reliance on local resources. • All options exhibit economies of scale. Competitiveness increases as total system size increases. Securing a large service area is critical to success. • Under a municipal financing model and excluding property taxes, the larger biomass system starts to approach BAU costs, even before taking into account grants.

  14. Possible Optimizations (Design Phase) • Solar DHW • Alternate siting of energy centre • Multiple energy centres • Distribution layout • Actual sizing and staging of capital items • Specific technology / vendor selection

  15. Key Implementation Risks for District Energy • Securing loads • Marketing • Relationship building • Policy / bylaw support • Minimizing installed capital costs • Technology selection • Coordination with other infrastructure • Competitive tendering • Performance contracting • Phasing of equipment relative to loads • Just in time capital where possible • Build in flexibility • Optimize staging and siting • Ensuring optimal building performance • Developer design document • Design and commissioning support • Retrofit support

  16. Paths Forward

  17. District Policy Role • Establishing target core service area boundaries • Cultivating community support • Developing measures to promote/require interconnection • Establishing commitment to interconnect municipal buildings • Creating mechanisms to support efficient planning/installation of linear infrastructure • Establishing policies and programs to encourage/facilitate access to energy resources • Facilitating the selection of site(s) for energy center(s) • Establishing policies for property taxes and franchise fees