Turning on the lhc commissioning with beam and the outlook for 2010
This presentation is the property of its rightful owner.
Sponsored Links
1 / 39

Turning on the LHC: commissioning with beam and the outlook for 2010 PowerPoint PPT Presentation


  • 116 Views
  • Uploaded on
  • Presentation posted in: General

Mike Lamont for the LHC commissioning team. Turning on the LHC: commissioning with beam and the outlook for 2010. Prep: beam tests through the years. CNGS. 2004:TI8. 2003:TT40. 2004: FIRST HOLE. TI2. 2008: SEPT 10. 2008: FIRST BEAM TO LHC. 2008: FIRST BEAM TO IR3. 2009: Sector test.

Download Presentation

Turning on the LHC: commissioning with beam and the outlook for 2010

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Turning on the lhc commissioning with beam and the outlook for 2010

Mike Lamontfor the LHC commissioning team

Turning on the LHC: commissioning with beam and the outlook for 2010


Prep beam tests through the years

Prep: beam tests through the years

CNGS

2004:TI8

2003:TT40

2004: FIRST HOLE

TI2

2008: SEPT 10

2008: FIRST BEAM TO LHC

2008: FIRST BEAM TO IR3

2009: Sector test

2009: FIRST IONS TO LHC

2009!

LHC commissioning & plans


Prep dry runs and machine checkout

Prep: dry runs and machine checkout

Re-phasing in the SPS:

And some serious hardware commissioning of cold circuits

LHC commissioning & plans


Beam milestones 2009 1 2

Beam milestones 2009 1/2

LHC commissioning & plans


Milestones 2 2

Milestones 2/2

  • 3 days - first collisions at 450 GeV

  • 9 days - first ramp to 1.2 TeV

  • 16 days - stable beams at 450 GeV

  • 18 days - two beams to 1.2 GeV & first collisions

General agreement that this wasn’t bad

LHC commissioning & plans


Injection reminder

Injection - reminder

Layout (point 8)

5 x MSI septa

4 x MKI kickers

TDI collimator

TCDD absorber

Nominal batch from the SPS: 288 bunches of 1.15 e11 protons at 450 GeV

We injected a single bunch of 2 e10

LHC commissioning & plans


Injection

Injection

  • Delicate process

    • We will sling around a lot of beam during this process

    • Complex dance of hardware, timing, RF, interlocks etc.

    • Have to carefully position collimators and other protection devices to make sure we catch any losses

    • Issues with BLMs triggering the beam interlock system due to fast losses during the injection process

  • Full program of beam based checks performed

  • Generally impressive, clearly benefits from experience gained during injection tests.

  • However, for the moment one would worry about routinely injecting unsafe beam.

LHC commissioning & plans


What you can

What you can

TT40 Damage during 2004 High Intensity SPS Extraction / Goddard, B ; Kain, V ; Mertens, V ; Uythoven, J ; Wenninger, J

Or what you can do with 2.9 MJ

During high intensity extraction on 25/10/04 an incident occurred in which the vacuum chamber of the TT40 magnet QTRF4002 was badly damaged.

The beam was a 450 GeV full LHC injection batch of 3.4 1013 p+ in 288 bunches, and was extracted from SPS LSS4 with the wrong trajectory

= 4.4 e12 at 3.5 TeV

LHC commissioning & plans


450 gev

450 GeV

Performance of hardware, instrumentation and software was impressive

Good preparation – fast problem resolution

  • Measurement and control of key beam parameters

    • Orbit, tune, chromaticity, coupling, dispersion

    • Beam loss, Beam size

    • Energy matching

    • Aperture checks

  • Experiments’ magnets

    • Solenoids & dipole –on and corrected

  • Two beam operation both with and without bumps

  • Optics checks

  • Full program of polarity checks of correctors and BPMs

LHC commissioning & plans


450 gev 8 khz the hump

450 GeV: 8 kHz & the hump

8 kHz line, broad frequency “hump”, and other spectra perturbations:

  • Reduction of beam life-time, emittance blow-up, …

Maybe not of direct interest to this audience but this sort of thing can give you a real headache

LHC commissioning & plans


Synchrotron light monitor

Synchrotron light monitor

Vertical emittance blow-up – beam 2

LHC commissioning & plans


Aperture

Aperture

Beam clearance seems to be OK

Some measured bottlenecks agree with model predictions using measured functions.

Aperture is out of budget due to the large beta beating

Correcting beta beating (optics) seems mandatory at 450 GeV

LHC commissioning & plans


Beating 450 1180 gev

Beating: 450 & 1180 GeV

LHC commissioning & plans


Collisions at 450 gev

Collisions at 450 GeV

  • Man was never meant to do collisions at 450 GeV (in the LHC at least)

  • Full program of machine protection, collimation, aperture and LBDS checks allowed “stable beams” to be declared.

  • Multi-bunch and higher intensities achieved

    • 16 bunches – total 1.85 x 1011

  • Luminosity scans tested successfully

  • Lots of events collected

    • 6 reasonably happy experiments

LHC commissioning & plans


Collisions at 450 gev1

Collisions at 450 GeV

After 20 days commissioning

LHC commissioning & plans


Nominal cycle ramp

Nominal cycle: ramp

8 ramp attempts

Not bad

LHC commissioning & plans


Ramp 7 8 bare tunes

Ramp 7 & 8 – bare tunes

Ramp looked good (and reproducible)

Both tune feedback and feed-forward operational

Encouraging

LHC commissioning & plans


Squeeze

Squeeze

One attempt in CMS: from 11 to 7 m.

  • First beam tests of betatron squeeze were successful!

    • Mechanics of the squeeze works well.

    • Good agreement with the expected beta values.

  • Some issues were identified and are being addressed

    • Not the smoothest night shift ever seen in the CCC

  • Feedbacks:

    • Orbit feedback will be needed as expected,

    • If simulations are confirmed, tune feedback seem less critical.

LHC commissioning & plans


Magnet model

Magnet model

  • Largest momentum offsets by sector:

    • -0.27 per mil in sector 56 / beam1

    • +0.32 per mil in sector 78 / beam2

The knowledge of the magnetic model of the LHC is remarkable and has been one of the key elements of a very smooth beam commissioning

Huge parameter space, mistakes made, lessons learnt etc but…

Tunes, energy matching, optics close to the model already

Some discrepancies being hunted down (450 GeV particularly)

Bodes very well for the future.

LHC commissioning & plans


Turning on the lhc commissioning with beam and the outlook for 2010

Beam Dump – very briefly

…in case of asynchronous beam dump

  • TCDS (fixed) – 6 m long diluter protects extraction septum

  • TCDQ (mobile) – 7 m long diluter kept at about 7-8 s from the beam, at all times

LHC commissioning & plans


Lhc beam dump system

LHC Beam Dump System

  • The beam dumping systems worked very well

    • Only real failures were the synchronous-asynchronous dumps: solved after firmware upgrade

LHC commissioning & plans


Collimation

Collimation

Excellent initial beam based commissioningfollowing careful preparation and tests

This and the beam dump are what stands between your silicon and 7 TeV protons (eventually).

  • Full program of beam based positioning

  • System works as designed.

    • Expected cleaning and leakage processes seen.

  • Possible to verify passive protection: losses at primary collimators.

  • Hierarchy established and respected in tests

  • Collimation setup remained valid over 6 days, relying on orbit reproducibility and optics stability

  • Even the Roman pots got a run out

LHC commissioning & plans


Collimation1

Collimation

Ralph Assmann

LHC commissioning & plans


Machine protection system

Machine Protection System

Provides the mechanism to dump the beam in around 3 turns if anything out there decides it’s had enough

Careful testing before beam

Full set of beam based tests

Clearly the critical path

  • Mission critical backbone

    • Beam Interlock System

    • Safe Machine Parameters

    • Plus inputs to/from other systems (e.g. timing, BCT)

  • A large multitude of user inputs

  • The beam driving a subtle interplay of:

    • LBDS, Collimation, protection devices, RF…

    • Instrumentation (BLMs, BCT, BPMs…)

    • Aperture

    • Optics

LHC commissioning & plans


Beam instrumentation

Beam Instrumentation

The Enabler

Excellent

  • Base-Band-Tune (BBQ) system was a work horse from day one giving tune, chromaticity, coupling.

  • Beam Position Monitors

    • Excellent performance

    • Very stable orbit (V drift ~ 15µm/h)

  • Beam Loss Monitors

    • BLMs correctly removes the BEAM PERMIT signal if measurements are over threshold. No reliability issues observed.

  • Profile monitors

    • Synchrotron light, wire-scanners operational

LHC commissioning & plans


Availability during initial commissioning

Availability during initial commissioning

LHC commissioning & plans


Unavailability

Unavailability

LHC commissioning & plans


Turning on the lhc commissioning with beam and the outlook for 2010

2010

LHC commissioning & plans


1 st quarter restart

1st quarter – restart

2nd quarter – physics start-up & LHC

LHC commissioning & plans


3 rd quarter production running

3rd quarter – production running

4th quarter – ions

LHC commissioning & plans


2010 overview

2010 overview

  • Hardware commission to 3.5 TeV

    • New quench protection system (nQPS)

    • Nearly there…

  • Beam commissioning continued

    • Through to colliding, safe, stable, squeezed beams

  • Consolidation & pilot physics

  • Phased intensity increase and associated machine protection qualification

    • Establish secure and reproducible operations and fully field test

    • Move very, very carefully

  • Consolidation & physics

LHC commissioning & plans


Beam commissioning strategy 2010

Beam commissioning strategy 2010

Global machine checkout

450 GeV re-commissioning

Machine protection commissioning

Ramp commissioning

Establish stable safe beams at 3.5 TeV

Collisions at 3.5 TeV

System/beam commissioning continuedSqueeze

Collisions at 3.5 TeV squeezed

Full machineprotection qualification

LHC commissioning & plans


Timeline to first collisions estimate

Timeline to first collisions - estimate

LHC status and plans


2010 to 2 mj

2010 to 2 MJ

Main challenge will be learning to operate safely with destructive beams

Approved steps to 2 MJ

pb-1

LHC commissioning & plans


2010 2011

2010 - 2011

Months!

LHC commissioning & plans


Turning on the lhc commissioning with beam and the outlook for 2010

2011

3.5 TeV: run flat out at ~100 pb-1 per month

16% nominal

Hope to be able to deliver around 1 fb-1

LHC commissioning & plans


Lhc startup 2010

LHC – startup 2010

It still works!

Circulating beams re-established last weekend

LHC commissioning & plans


Conclusions 1 2

Conclusions 1/2

Long way to go before we are ready to go much beyond the safe beam limit

  • A lot of hard work over the years has enable a truly impressive period of initial commissioning with beam.

  • Initial indications are that the LHC:

    • is reproducible;

    • magnetically well understood;

    • optically in good shape;

    • is armed with a mighty set of instrumentation, software, and hardware systems.

  • Lots still to sort out, in particular…

  • Operations, controls, instrumentation etc. have the capability to unnecessarily stress the machine protection system – issues must be resolved.

LHC commissioning & plans


Conclusions 2 2

Conclusions 2/2

  • Starting now ~4 weeks to establish stable, safe beams at 3.5 TeV and provide first collisions

  • Extended running period around the safe beam limit:

    • With blocked MD periods as required

  • A very careful stepwise increase in intensity through the year with each step up in intensity to be followed by an extended running period

  • Aiming for 1031 - 1032 cm-2s-1 in 2010 and hopefully between 100 – 200 pb-1

LHC commissioning & plans


  • Login