The Version 6 Rollercoaster!! David McDonald BEng, MIET Maximo UK & Ireland User Group

Loading in 2 Seconds...

play fullscreen
1 / 32

The Version 6 Rollercoaster!! David McDonald BEng, MIET Maximo UK & Ireland User Group - PowerPoint PPT Presentation


  • 105 Views
  • Uploaded on

The Version 6 Rollercoaster!! David McDonald BEng, MIET Maximo UK & Ireland User Group 12 th November 2008. Outline. Introduction Motives for development, future work, roadmap etc. Structure of project wrt NIS / IBM / NIE. Version 6 Project – Key points

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' The Version 6 Rollercoaster!! David McDonald BEng, MIET Maximo UK & Ireland User Group' - khalil


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

The Version 6 Rollercoaster!!

David McDonald BEng, MIET

Maximo UK & Ireland User Group

12th November 2008

slide2

Outline

  • Introduction
  • Motives for development, future work, roadmap etc.
  • Structure of project wrt NIS / IBM / NIE.
  • Version 6 Project – Key points
  • Roll-out plan, including training programmes, Maxdemo test (including full trial demanded from IBM), timescale.
  • Version 6 – The Highs & Lows
  • Maximo Mobile
  • Long term Strategy
slide3

Northern Ireland Electricity

  • NIE is part of the Viridian Group, owned by Arcapita.
  • Viridian turnover was £1022M in 2007, with NIE contributing regulated income of £166M.
  • NIE has sole responsibility for Transmission and Distribution of electricity to 790,000 customers in Northern Ireland.
  • NIE Infrastructure (the wires business) includes Customer Operations, Lines & Cables Product, and Plant Product.
slide4

Viridian Group

PES Contracting

NIE Energy

NIE Infrastructure

Huntstown Power

Energia

Plant

Customer Operations

Lines & Cables

Networks

Maximo

Group Structure

slide5

Plant Product

  • Designs, constructs and maintains substations across Northern Ireland.
  • Installed network:-
    • 8 275/110 kV (with 3 new sites planned)
    • 40 110/33kV Substations
    • 210 33/11kV Substations
    • 8,500 Secondary Distribution (Ground Mounted)
  • Determines maintenance policy. Moving towards RCM / CBM policies and practices.
  • Maximo as Asset Register / Work Management system.
slide6

Maximo in Plant Product

  • Introduced as version 3 in 1997 to bring together Distribution data (up to 33kV) from 3 legacy databases.
  • Upgraded in 1999 for Y2K compliance to version 4.
  • Transmission data (110kV and 275kV) transferred from En Garde in 2002.
  • Integrated with Job Management System in 2004.
  • Delivered via Citrix in 2005.
  • Upgraded in 2008 to version 6.2.1.
  • …and much more to come!
slide7

NIE -Why upgrade to Version 6?

  • Requirements to comply with Legislative, regulatory and Auditory requirements.
  • Improved Substation Inspections and Defect Management
  • Maximo Version 4.0.1 unsupported
  • Increased Functionality
      • Condition based Maintenance
      • Image and Document Management
      • Workflow & Work Scheduling
      • Protection & Control
      • Dashboard
version 6 roadmap
Version 6 Roadmap

V7

CBM

Links

Databases » Maximo

Maximo Mobile / Defect Management

slide9

Version 6 Project

  • 3 stakeholders…NIE, IBM and Northgate Information Systems (NIS), the desktop provider for NIE.
  • Implemented in IE6 within a Citrix environment.
  • Circa. 50 users, across 7 locations.
  • ‘Train the trainer’ approach. NIS and NIE staff trained by IBM. NIE users then trained by NIE staff.
  • Rollout briefed across organisation.
  • Downtime limited to two working days.
hardware
Hardware

Maximo Citrix Users

Citrix Server

Application Server

Actuate Server

Database Server

slide11

Configuration

  • Oracle triggers. Redefined in version 6, using Crossover Domains.
  • Training. Three sessions for every user, a sandpit, and post go-live handholding.
  • Actuate reporting. Conversion from Business Objects and Access.
  • Screen design. Fidelity with version 4, but also harnessing the additional features from version 6.
  • Organisational structure including user names.
initial user testing
Training carried out in October 2007

Planned to take place 1 week before Go-Live

Training completed with demo data

Some major issues identified during training / testing

Performance

Print Issue

Detailed Configuration

Asset Catalogue

The List Window

Initial User Testing
version 6 the highs
The List Tab

Navigation

User sign-on

Company wide access

Integration with other software

Publishing of reports

Saved Queries

Start Centres

Version 6 - The Highs
version 6 the lows
Version 6.2.1 – The fix list (book!)

The List Window

Performance – Changing status & WO print slower than V4

Work Order print…how did we get rid of those pesky pop-ups? Install the known fix of course!

Data Migration issues (Asset Catalogue & Asset Move History)

Lines of communication

Version 6 - The Lows
version 6 roadmap1
Version 6 Roadmap

V7

CBM

Links

Databases » Maximo

Maximo Mobile / Defect Management

slide20

Roadmap Prioritisation

  • Legislative requirement? Are we obliged to deliver certain elements to comply with legislation?
  • Regulatory requirement? What information does the regulator demand from NIE?
  • Business benefit?
  • Promotion of Maximo?
  • Effort…do we need to employ IBM or an IBM partner? Do we need to employ NIS or other business partner?
  • Cost. Not just in financial terms, but in terms of resources.
slide21

Mobile Working

  • Approval and Sanction granted for Maximo Mobile
  • To replace 10,000 paper inspections per year.
  • 20 devices initially deployed, rising to 50.
  • Digital image collection, for immediate action on defects.
  • 3G infrastructure, backed up by docking as required.
  • Maps, diagrams, ISO procedures in the field.
  • May move towards GPS.
  • First pass removes clerical resource requirement of 1.5FTE.
slide24

TETRA Development

  • Terrestrial Trunked Radio (professional mobile radio and two way transceiver.)
  • Blue Light Services - Government Agencies and Emergency Response
  • Rolled out to Orange Light Services (utilities)
  • TETRA voice implemented in NIE 2007
  • Used for all High Voltage Switching from site to Control centre
  • Intention to deploy Maximo via TETRA
slide25

Defect Management

  • Coded, rather than free text, output from Mobile.
  • Defects attached to relevant assets and locations.
  • Escalations and Workflow used to route defects to the relevant resource.
  • Where defects are not resolved, Maximo provides escalation through the organisation.
  • Visibility of defect issues not currently available, and some of these defects will be safety critical.
  • Longer term – integrated GIS to allow effective area working.
version 6 roadmap2
Version 6 Roadmap

Lines

V7

CBM

Links

Databases » Maximo

slide29

Architecture

On-Line Monitor

Trip Coil Profiles

Distribution Control

On-line Oil Analyser

Maximo

PI Historian

On-line Bushing Monitor

Transmission Control

DGA Oil Sampling

slide30

Conclusions

  • Maximo 6 provides significant ‘out of the box’ functionality improvements that can be easily accessed by the end user for quick and powerful gain.
  • Mobile working elevates basic inspection tasks to new levels. Defect capture, prioritisation and resolution all gain major improvements.
  • Maximo 6 provides the platform for true Condition Based Maintenance. It provides the ability to integrate Plant and the Asset Management system, to harness real-time condition information, allowing maintenance decisions to be focussed and cost-effective.
long term partnership
There are currently 20 upgrade projects to be implemented over the next three years

NIE are keen to sign a 3 year framework contract to implement these 20 projects

These projects will significantly improve Asset Management within NIE

Expand Maximo to other parts of the business

Long term Partnership