The Version 6 Rollercoaster!!
Download
1 / 32

The Version 6 Rollercoaster!! David McDonald BEng, MIET Maximo UK & Ireland User Group - PowerPoint PPT Presentation


  • 96 Views
  • Uploaded on

The Version 6 Rollercoaster!! David McDonald BEng, MIET Maximo UK & Ireland User Group 12 th November 2008. Outline. Introduction Motives for development, future work, roadmap etc. Structure of project wrt NIS / IBM / NIE. Version 6 Project – Key points

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' The Version 6 Rollercoaster!! David McDonald BEng, MIET Maximo UK & Ireland User Group' - khalil


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

The Version 6 Rollercoaster!!

David McDonald BEng, MIET

Maximo UK & Ireland User Group

12th November 2008


Outline

  • Introduction

  • Motives for development, future work, roadmap etc.

  • Structure of project wrt NIS / IBM / NIE.

  • Version 6 Project – Key points

  • Roll-out plan, including training programmes, Maxdemo test (including full trial demanded from IBM), timescale.

  • Version 6 – The Highs & Lows

  • Maximo Mobile

  • Long term Strategy


Northern Ireland Electricity

  • NIE is part of the Viridian Group, owned by Arcapita.

  • Viridian turnover was £1022M in 2007, with NIE contributing regulated income of £166M.

  • NIE has sole responsibility for Transmission and Distribution of electricity to 790,000 customers in Northern Ireland.

  • NIE Infrastructure (the wires business) includes Customer Operations, Lines & Cables Product, and Plant Product.


Viridian Group

PES Contracting

NIE Energy

NIE Infrastructure

Huntstown Power

Energia

Plant

Customer Operations

Lines & Cables

Networks

Maximo

Group Structure


Plant Product

  • Designs, constructs and maintains substations across Northern Ireland.

  • Installed network:-

    • 8 275/110 kV (with 3 new sites planned)

    • 40 110/33kV Substations

    • 210 33/11kV Substations

    • 8,500 Secondary Distribution (Ground Mounted)

  • Determines maintenance policy. Moving towards RCM / CBM policies and practices.

  • Maximo as Asset Register / Work Management system.


Maximo in Plant Product

  • Introduced as version 3 in 1997 to bring together Distribution data (up to 33kV) from 3 legacy databases.

  • Upgraded in 1999 for Y2K compliance to version 4.

  • Transmission data (110kV and 275kV) transferred from En Garde in 2002.

  • Integrated with Job Management System in 2004.

  • Delivered via Citrix in 2005.

  • Upgraded in 2008 to version 6.2.1.

  • …and much more to come!


NIE -Why upgrade to Version 6?

  • Requirements to comply with Legislative, regulatory and Auditory requirements.

  • Improved Substation Inspections and Defect Management

  • Maximo Version 4.0.1 unsupported

  • Increased Functionality

    • Condition based Maintenance

    • Image and Document Management

    • Workflow & Work Scheduling

    • Protection & Control

    • Dashboard


Version 6 roadmap
Version 6 Roadmap

V7

CBM

Links

Databases » Maximo

Maximo Mobile / Defect Management


Version 6 Project

  • 3 stakeholders…NIE, IBM and Northgate Information Systems (NIS), the desktop provider for NIE.

  • Implemented in IE6 within a Citrix environment.

  • Circa. 50 users, across 7 locations.

  • ‘Train the trainer’ approach. NIS and NIE staff trained by IBM. NIE users then trained by NIE staff.

  • Rollout briefed across organisation.

  • Downtime limited to two working days.


Hardware
Hardware

Maximo Citrix Users

Citrix Server

Application Server

Actuate Server

Database Server


Configuration

  • Oracle triggers. Redefined in version 6, using Crossover Domains.

  • Training. Three sessions for every user, a sandpit, and post go-live handholding.

  • Actuate reporting. Conversion from Business Objects and Access.

  • Screen design. Fidelity with version 4, but also harnessing the additional features from version 6.

  • Organisational structure including user names.


Initial user testing

Training carried out in October 2007

Planned to take place 1 week before Go-Live

Training completed with demo data

Some major issues identified during training / testing

Performance

Print Issue

Detailed Configuration

Asset Catalogue

The List Window

Initial User Testing






Version 6 the highs

The List Tab

Navigation

User sign-on

Company wide access

Integration with other software

Publishing of reports

Saved Queries

Start Centres

Version 6 - The Highs


Version 6 the lows

Version 6.2.1 – The fix list (book!)

The List Window

Performance – Changing status & WO print slower than V4

Work Order print…how did we get rid of those pesky pop-ups? Install the known fix of course!

Data Migration issues (Asset Catalogue & Asset Move History)

Lines of communication

Version 6 - The Lows


Version 6 roadmap1
Version 6 Roadmap

V7

CBM

Links

Databases » Maximo

Maximo Mobile / Defect Management


Roadmap Prioritisation

  • Legislative requirement? Are we obliged to deliver certain elements to comply with legislation?

  • Regulatory requirement? What information does the regulator demand from NIE?

  • Business benefit?

  • Promotion of Maximo?

  • Effort…do we need to employ IBM or an IBM partner? Do we need to employ NIS or other business partner?

  • Cost. Not just in financial terms, but in terms of resources.


Mobile Working

  • Approval and Sanction granted for Maximo Mobile

  • To replace 10,000 paper inspections per year.

  • 20 devices initially deployed, rising to 50.

  • Digital image collection, for immediate action on defects.

  • 3G infrastructure, backed up by docking as required.

  • Maps, diagrams, ISO procedures in the field.

  • May move towards GPS.

  • First pass removes clerical resource requirement of 1.5FTE.



TETRA Development

  • Terrestrial Trunked Radio (professional mobile radio and two way transceiver.)

  • Blue Light Services - Government Agencies and Emergency Response

  • Rolled out to Orange Light Services (utilities)

  • TETRA voice implemented in NIE 2007

  • Used for all High Voltage Switching from site to Control centre

  • Intention to deploy Maximo via TETRA


Defect Management

  • Coded, rather than free text, output from Mobile.

  • Defects attached to relevant assets and locations.

  • Escalations and Workflow used to route defects to the relevant resource.

  • Where defects are not resolved, Maximo provides escalation through the organisation.

  • Visibility of defect issues not currently available, and some of these defects will be safety critical.

  • Longer term – integrated GIS to allow effective area working.


Version 6 roadmap2
Version 6 Roadmap

Lines

V7

CBM

Links

Databases » Maximo




Architecture

On-Line Monitor

Trip Coil Profiles

Distribution Control

On-line Oil Analyser

Maximo

PI Historian

On-line Bushing Monitor

Transmission Control

DGA Oil Sampling


Conclusions

  • Maximo 6 provides significant ‘out of the box’ functionality improvements that can be easily accessed by the end user for quick and powerful gain.

  • Mobile working elevates basic inspection tasks to new levels. Defect capture, prioritisation and resolution all gain major improvements.

  • Maximo 6 provides the platform for true Condition Based Maintenance. It provides the ability to integrate Plant and the Asset Management system, to harness real-time condition information, allowing maintenance decisions to be focussed and cost-effective.


Long term partnership

There are currently 20 upgrade projects to be implemented over the next three years

NIE are keen to sign a 3 year framework contract to implement these 20 projects

These projects will significantly improve Asset Management within NIE

Expand Maximo to other parts of the business

Long term Partnership


Thank you for your attention! over the next three years

Questions?