Minuteman Vocational Technical Regional High School Progress

Minuteman Vocational Technical Regional High School Progress. January 22 nd 2019 – February 25 th 2019. February 25 th View of Area A+B – Upper Level MEP Ceiling Devices Installed. Millwork Installation in Progress. February 25 th View of Area G – Upper Level

kcarrol
Download Presentation

Minuteman Vocational Technical Regional High School Progress

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Minuteman Vocational Technical Regional High School Progress January 22nd 2019 – February 25th 2019

  2. February 25thView of Area A+B – Upper Level MEP Ceiling Devices Installed. Millwork Installation in Progress

  3. February 25thView of Area G – Upper Level MEP Ceiling Devices Installed. Millwork Installation in Progress February 25thView of Area G – Lower Level Ceiling Grid Installation substantially complete. MEP Ceiling Devices Installation in Progress.

  4. February 25thView of Area D – Upper Level Prime & First Coat of Paint Substantially Complete. Ceiling grid installation to commence this week.

  5. February 25thView of Area D – Gymnasium Prime painting of walls, roof deck and MEP’s Substantially Complete. Rough-In of Overhead Electrical in Progress.

  6. February 25thView of Area D – Mechanical Room Terminations to equipment is in progress is nearing completion. Installation of insulation to commence this week.

  7. February 25thView of Area E – East Elevation Masonry Stone Veneer Complete at Lower Level. Metal Panel Soffit and Wall Panels in Progress. February 25thView of Area E – Faculty Parking Retaining Wall Construction in Progress.

  8. February 25thView of Area E – Lower Level Drywall installation substantially complete. Taping and Sanding activities in progress. February 25thView of Area E – Upper Level Installation of Railings at Skylight openings in progress. Soffit framing at openings in progress.

  9. February 25thView of Area E+F – Cafeteria Soffit framing in progress. Framing at along Bridge Level Substantially Complete. Installation of railings in space in progress.

  10. February 25thView of Area F – Lower Level Interior framing substantially complete. Sheetrocking & taping top of walls in progress. Rough-in of in-wall MEP’s in progress.

  11. February 25thView of Area C – West Elevation Masonry Veneer activities on the lower level complete. Window Installation Complete. January 22ndView of Area C – Mezzanine Level Overhead rough-in of major MEP’s complete. Painting of ceiling and MEP items complete. Concrete placement in misc metal stairs in progress this week.

  12. February Construction Schedule Look Ahead: Area A+B • Continue Ceiling Grid Installation on Lower B • Continue installation of Lights, Registers and other MEP devices in ceiling grid • Continue Millwork installation on Upper B • Commence Installation of Ceramic Wall Tile Area G • Complete Ceiling Grid installation on the Lower Level • Continue installation of Lights, Registers and other MEP devices in ceiling grid • Continue Millwork installation on Upper G • Commence Installation of Ceramic Wall Tile Area D • Complete Prime Painting on Upper Level • Commence Ceiling Grid Installation • Complete Mechanical Terminations to equipment in Mechanical Room Area E • Complete Soffit Framing activities on all levels • Complete Sheetrocking & Taping activities on all levels. • Commence Prime Painting on all levels. Area F • Complete Rough-In of in-wall MEP’s • Commence Sheetrocking & Taping activities Area C • Continue Rough-In of OH MEP’s over the theater & stage space. • Concrete placement in misc metal stair systems. Exterior/Sitework • Permanent power established to the building’s switchgear on schedule for February 26th • Project team meeting with National Grid on 3/7 to obtain a schedule for the gas installation • Complete the water main connection, test and flush system for use. • Continue shaping the swales at the perimeter of the building