130 likes | 136 Views
Minuteman Vocational Technical Regional High School Progress. January 22 nd 2019 – February 25 th 2019. February 25 th View of Area A+B – Upper Level MEP Ceiling Devices Installed. Millwork Installation in Progress. February 25 th View of Area G – Upper Level
E N D
Minuteman Vocational Technical Regional High School Progress January 22nd 2019 – February 25th 2019
February 25thView of Area A+B – Upper Level MEP Ceiling Devices Installed. Millwork Installation in Progress
February 25thView of Area G – Upper Level MEP Ceiling Devices Installed. Millwork Installation in Progress February 25thView of Area G – Lower Level Ceiling Grid Installation substantially complete. MEP Ceiling Devices Installation in Progress.
February 25thView of Area D – Upper Level Prime & First Coat of Paint Substantially Complete. Ceiling grid installation to commence this week.
February 25thView of Area D – Gymnasium Prime painting of walls, roof deck and MEP’s Substantially Complete. Rough-In of Overhead Electrical in Progress.
February 25thView of Area D – Mechanical Room Terminations to equipment is in progress is nearing completion. Installation of insulation to commence this week.
February 25thView of Area E – East Elevation Masonry Stone Veneer Complete at Lower Level. Metal Panel Soffit and Wall Panels in Progress. February 25thView of Area E – Faculty Parking Retaining Wall Construction in Progress.
February 25thView of Area E – Lower Level Drywall installation substantially complete. Taping and Sanding activities in progress. February 25thView of Area E – Upper Level Installation of Railings at Skylight openings in progress. Soffit framing at openings in progress.
February 25thView of Area E+F – Cafeteria Soffit framing in progress. Framing at along Bridge Level Substantially Complete. Installation of railings in space in progress.
February 25thView of Area F – Lower Level Interior framing substantially complete. Sheetrocking & taping top of walls in progress. Rough-in of in-wall MEP’s in progress.
February 25thView of Area C – West Elevation Masonry Veneer activities on the lower level complete. Window Installation Complete. January 22ndView of Area C – Mezzanine Level Overhead rough-in of major MEP’s complete. Painting of ceiling and MEP items complete. Concrete placement in misc metal stairs in progress this week.
February Construction Schedule Look Ahead: Area A+B • Continue Ceiling Grid Installation on Lower B • Continue installation of Lights, Registers and other MEP devices in ceiling grid • Continue Millwork installation on Upper B • Commence Installation of Ceramic Wall Tile Area G • Complete Ceiling Grid installation on the Lower Level • Continue installation of Lights, Registers and other MEP devices in ceiling grid • Continue Millwork installation on Upper G • Commence Installation of Ceramic Wall Tile Area D • Complete Prime Painting on Upper Level • Commence Ceiling Grid Installation • Complete Mechanical Terminations to equipment in Mechanical Room Area E • Complete Soffit Framing activities on all levels • Complete Sheetrocking & Taping activities on all levels. • Commence Prime Painting on all levels. Area F • Complete Rough-In of in-wall MEP’s • Commence Sheetrocking & Taping activities Area C • Continue Rough-In of OH MEP’s over the theater & stage space. • Concrete placement in misc metal stair systems. Exterior/Sitework • Permanent power established to the building’s switchgear on schedule for February 26th • Project team meeting with National Grid on 3/7 to obtain a schedule for the gas installation • Complete the water main connection, test and flush system for use. • Continue shaping the swales at the perimeter of the building