An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RSVP Safety and Environmental Protection Costs E. Lessard Associate Chair for ESHQ Collider-Accelerator Department

  2. Basic Changes to AGS and Extraction • New magnet systems within the AGS • New AGS extraction line in Building 912 • Caps for AGS and Booster

  3. Basic Changes to Building 912 • Two new target caves • Two new beam dumps • New activated soil areas • New activated beam-line components

  4. RSVP QA Requirements • QA Plan • Procurement and Specification Reviews • Action Tracking System • Management, EMS and OSH Assessments • Operations Procedure Reviews • Configuration Management • Records Management

  5. NEPA Requirements • Pre-Construction • Baseline groundwater monitoring (~3 wells added) • Baseline external radiation monitoring • Environmental Assessment and FONSI • Covered by AGS EA #0909 • Air and water related permits

  6. RSVP Commissioning / Operations Requirements • Needed: • USIs for Radiation, Vacuum Vessel and Cryogenic Issues (DOE) • Accelerator Safety Envelope (DOE) • Environmental Process Evaluation • Facility Risk Assessments • Job Risk Assessments • Accelerator Readiness Review (DOE)

  7. 1.4.5.5 QA for RSVP Authorization $85,000 unburdened total

  8. 1.4.5.6 ESH for RSVP Authorization $245,000 unburdened total

  9. Approximate Time Line for RSVP ESHQ • Year 1 • Write QA Plan, Preliminary Hazards Analysis, Safety Plan • Perform initial ESH design reviews • QA: procurement/specification reviews, action tracking • Years 2 and 3 • Write USIs, update C-AD SAD and obtain approved ASE • Install monitoring wells • Obtain baseline radiological measurements • Write Process Evaluations • Complete ESH reviews • QA: configuration and records management, procurement/specification reviews, action tracking • Year 4 • Test access controls system • Update procedures • Perform JRAs and FRAs • QA: configuration and records management, EMS and OSH assessments, action tracking • Write commissioning plan • Perform ARR