An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The programme – as presented yesterday LHC 8:30 meeting

  2. Programme last evening LHC 8:30 meeting

  3. Programme this morning LHC 8:30 meeting

  4. Thursday 14th February • 07:24 Last dump from Stable Beams for a long time… • Operator dump! • 08:30 At injection, start of DS Quench Tests. • 13:19 Dump ramp 1 of collimation quench test at dispersion suppressor, slow losses, • 3 bunches for ADT tests, with asynchdump • Asynch dump OK • 15:09 Dump ramp 2 of collimation quench test due to interlock from collimators when moving to relaxed settings • Several source, open TCDQ energy threshold • Access for installing scope Q6 quench test at injection • Took down the sector, not foreseen by some • Pre-cycle etc. • 20:21 Dump ramp 3 of DS quench test, 144 bunches, about 500 kW losses, dumped by BLMs without quench • Increase BLM limits LHC 8:30 meeting

  5. First ‘real’ DS test ramp with 144 bunches Blue - excitation strength Green - intensity Red - excitation running The beam was dumped 3 seconds before the excitation strength started to increase to provide constant loss rate. LHC 8:30 meeting

  6. By the collimation team: • In more detail • dumped on the RS10 for the BLMQI.09L7.B2I10_MQ; for this magnet the MF was still at 0.1. • We achieved a peak loss rate of 8-8.5e11p/s over about 2 s (exceeding what was achieved in 2011). • Other faster RS's achieved up to 85% of dump levels (TCPs, TCLAs). • We achieved (without quenching) losses up to 1.5 times larger than the assumed quench limit (first time for proton losses). • We decided to proceed as it follows: • Increase MF on a selection of DS magnets to 0.5. • Change the master thresholds by a factor 2.5 for the collimators that are close to dump limit for fast RS. • In the meantime, deploy the firmware change for the ADT to allow excitation on 2 trains. LHC 8:30 meeting

  7. Continue DS quench test 00:07 Dump again on BLMs (no quench) LHC 8:30 meeting

  8. Summary of second attempt to quench. • Achieved peak loss rates of 640 kW, corresponding to up to 1e12p/s. • Dumped on RS10 on the BLMQI.08L7.B2I10_MQ. We reached 3 times the quench limit in RS10, without quenching. • This monitor has MF=1 so we can go above that levels only by changing the MT. • Next attempt: • Increase the intensity by a factor ~1.5 (144+72b) • changing the limiting Q8 monitor by a factor 2.5 by changing the MT (in RS09 and above). • Other changes MF's in the DS, listed LHC 8:30 meeting

  9. DS quench test with B2 (144+72 bunches) • Dump at 3:15 • We achieved peak losses up to 1MW without quenching. Peak loss rate: about 1.65e12p/s • This time we dumped on a TCLA collimators (thresholds were at the electronics maximum) • RS08 • The Q8 reached for RS09 a factor 3.4 above the assumed quench limit. • The primary collimators experienced a temperature increase up to 10 deg. LHC 8:30 meeting

  10. Quench test at injection Q6.L8 • 05:46 It did quench • As we know we can with injecting beam • TCLIB closed • Some iteration on current and injected intensity • Quenched on • RQ6.L8 at 2500 A • One shot at 6.54E10 • However, not sure if it really quenches or just triggered the QPS • “RQ6.L8 trip analysis...it looks a bit quick to be a quench” • Presently • Access for scope installation ADT fast losses quench test • Access for IPQ threshold adjustment LHC 8:30 meeting

  11. The Plan LHC 8:30 meeting